Home / Browse projects / Pune, Maharashtra / VAASTU IMPERIAL Wing A

Registered No litigation declared Residential / Group Housing project

VAASTU IMPERIAL Wing A

By M/S Twin Star Infrastructure

RG-MH-24690 · RERA P52100009509 · Last updated on MahaRERA portal: 14 Aug 2026

Source: official MahaRERA filing

Red flags

  • 139 complaints at MahaRERA
  • Completion date moved by 30 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2027Possession promisedmoved 30 months from the original
5 of 11Construction stages donefurthest along: Slabs of Super Structure, 94%
13 of 88Units unsoldnot recorded sold or booked
139Complaints at MahaRERAon this registration
Jump to the 92 documents Report an error

VAASTU IMPERIAL Wing A is a Residential / Group Housing project by M/S Twin Star Infrastructure in Pune, Maharashtra, registered with MahaRERA as P52100009509 on 22 Aug 2017. Possession is promised by 30 Jun 2027. The completion date has moved by 30 months from the original filing. 75 of the 88 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete. 139 complaints are on record with the regulator.

At a glance

Project

  • NameVAASTU IMPERIAL Wing A
  • TypeResidential / Group Housing
  • Location
    • Ravet
    • Pimpri Chinchawad (M Corp.)
    • Haveli
    • Pune
    • 412101
  • Pincode412101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100009509
  • ReraGenie IDRG-MH-24690

Builder

  • NameM/S Twin Star Infrastructure
  • Entity typePartnership
  • PartnersRohit Kumar Jhunjhunwala, Jhunjhunwala Homes Pvt Ltd
  • Other registrations2 more →
  • No longer live1 lapsed, de-registered or revoked

Key dates

this monthRegisteredAug 2017First promiseDec 2024Revised toJun 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on22 Aug 2017
  • Promised completion30 Jun 2027
  • Revised completionRevised to 30 Jun 2027 (originally 30 Dec 2024)
  • Buildings1 building record
  • Documents filed92 files

Current status

85%75 of 88 units booked
0.0%Work done, per cost certificate

Figures as on 14 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING ANA241588088

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 14 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 94%.

WING A: 67% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure94%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises47%
Sanitary Fittings within the flats / premises6%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks5%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.49%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.33%

Progress on shared amenities15

As on 14 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes80%
Water SupplyYes83%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes70%
Storm Water DrainsYes90%
Landscaping & Tree PlantingYes70%
Street LightingYes50%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes70%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes50%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes55%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed151

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots151
Closed/Covered121
Open Space30

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,280 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on27 Aug 2026

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Municipal Corporation
Permissible FSI13568.59
Proposed, not sanctioned5,595 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchRAVET PUNE
Estimated costRs 62.09 cr
Work done0.0%
BuildingWingEstimatedIncurred
WING ANARs 58.98 cr-
-NARs 3.10 cr-

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectARCHITECT MILIND PATIL
ArchitectPatil and Bugade Associates
EngineerNIKHIL KHARAT
EngineerS K Consultants and Engineers
Chartered AccountantTILOKCHANDANI & ASSOCIATES
Chartered AccountantAshish Rathi and Co.
Chartered AccountantJain Jakhotiya and Associates
PartnerRole in project
M/S Twin Star Infrastructure-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100025863Dec 2024 → Jun 2026

Reason as filed by the promoterAwaiting Environment Clearance Certificate for Additional Construction and due to COVID outbreak the delay is caused

EA14082622150Dec 2024 → Jun 2027

Reason as filed by the promoterWe sincerely apologize for the delayin the completion of the project and the submission Of this request. The delay occurred primarily due to financial constraints faced during the initial stage of the project, as certain investors withdrew their investments and subsequently filed complaints. These unforeseen financial setbacks adversely impacted the project's cash flow, resulting in a slowdown in construction activities and consequent delay in the project's completion. Despite these challenges, we have taken necessary corrective measures to stabilize the financial position and are diligently w

Complaints filed with MahaRERA139

Case no.ComplainantRespondentFiled
CC005000000000146AMIT RAMANBHAI PATELM/S. TWIN STAR INFRASTRUCTURE02/09/2017
CC005000000010706Mukesh PatelAshwin Harish Vadiya16/01/2018
CC005000000011467Satishkumar Jayantibhai PatelM/S TWINSTAR INFRASTRUCTURE26/04/2018
CC005000000011469Dipteshkumar Parshottamdas PatelM/S TWIN STAR INFRASTRUCTURE26/04/2018
CC005000000011470Ketanbhai Kantibhai PatelM/S TWIN STAR INFRASTRUCTURE26/04/2018
CC005000000011472Gopaldas Bhanjibhai PatelM/S TWIN STAR INFRASTRUCTURE26/04/2018
CC005000000011471Dhirendrakumar Gopaldas PatelM/S TWIN STAR INFRASTRUCTURE26/04/2018
CC005000000011473Nareshkumar Pachanbhai PatelM/S TWIN STAR INFRASTRUCTURE26/04/2018
CC005000000011738TWINSTAR INFRASTRUCTUREKishore C Patel16/07/2018
CC005000000011759TWINSTAR INFRASTRUCTURESagar P Patel16/07/2018
CC005000000011760TWINSTAR INFRASTRUCTUREHareshkumar V Patel16/07/2018
CC005000000011762TWINSTAR INFRASTRUCTURERamanlal S Patel16/07/2018
CC005000000011763TWINSTAR INFRASTRUCTUREArvindbhai D Patel16/07/2018
CC005000000011764Twinstar InfrastructurePravinbhai P Patel16/07/2018
CC005000000011765TWINSTAR INFRASTRUCTUREMitesh C Patel16/07/2018
CC005000000011766TWINSTAR INFRASTRUCTUREMaheshkumar K Patel16/07/2018
CC005000000011767TWINSTAR INFRASTRUCTUREKantilal L Patel16/07/2018
CC005000000011768Twinstar InfrastructurePravinkumar D Patel16/07/2018
CC005000000011769TWINSTAR INFRASTRUCTURERasiklal S Patel16/07/2018
CC005000000011770TWINSTAR INFRASTRCUTUREHiralal B Patel17/07/2018
CC005000000011771Twinstar InfrastructureNilesh K Patel17/07/2018
CC005000000011772TWINSTAR INFRASTRUCTURESandipkumar N Pokar17/07/2018
CC005000000011773TWINSTAR INFRASTRUCTURENAVINBHAI J PATEL17/07/2018
CC005000000011774TWINSTAR INFRASTRUCTUREDipakkumar R Patel17/07/2018
CC005000000011775TWINSTAR INFRASTRUCTUREChirag I Patel17/07/2018
CC005000000011776TWINSTAR INFRASTRUCTUREBHARATBHAI K DHORU17/07/2018
CC005000000011777TWINSTAR INFRASTRUCTUREArvind D Patel18/07/2018
CC005000000011778TWINSTAR INFRASTRUCTUREHaribhai B Patel18/07/2018
CC005000000011779TWINSTAR INFRASTRUCTUREDilipkumar H Patel18/07/2018
CC005000000011780TWINSTAR INFRASTRUCTUREHANSRAJBHAI S PATEL18/07/2018
CC005000000011781TWINSTAR INFRASTRUCTURERamanlal S Patel18/07/2018
CC005000000011782TWINSTAR INFRASRTUCTURESuresh J Patel18/07/2018
CC005000000011783TWINSTAR INFRASTRUCTUREDakshaben R Patel18/07/2018
CC005000000011785TWINSTAR INFRASTRUCTURERiteshkumar G Patel18/07/2018
CC005000000011786TWINSTAR INFRASTRUCTUREIshwarbhai L Patel18/07/2018
CC005000000011787TWINSTAR INFRASTRUCTUREManish H Patel18/07/2018
CC005000000011789TWINSTAR INFRASTRUCTURERajubhai N Patel18/07/2018
CC005000000011790TWINSTAR INFRASTRUCTUREMITESHKUMAR H POKAR18/07/2018
CC005000000011791TWINSTAR INFRASTRUCTURELIMBAI JIGAR NATVAR18/07/2018
CC005000000011792TWINSTAR INFRASTRUCTURESureshkumar J Patel18/07/2018
CC005000000011793TWINSTAR INFRASTRUCTUREDeepakkumar B Patel18/07/2018
CC005000000011794TWINSTAR INFRASTRUCTUREDakshaben R Patel18/07/2018
CC005000000011795TWINSTAR INFRASTRUCTUREManojkumar R Patel18/07/2018
CC005000000011796TWINSTAR INFRASTRUCTUREVipul R Patel18/07/2018
CC005000000011797TWINSTAR INFRASTRUCTURETarunkumar A Patel18/07/2018
CC005000000011798TWINSTAR INFRASTRUCTUREPARTH P PATEL18/07/2018
CC005000000011799Pravin R PatelPravin R Patel18/07/2018
CC005000000011801TWINSTAR INFRASTRUCTUREKIRITKUMAR A PATEL18/07/2018
CC005000000011802TWINSTAR INFRASTRUCTUREKIRIT S PATEL18/07/2018
CC005000000011803TWINSTAR INFRASTRUCTUREIshwarkumar R Patel18/07/2018
CC005000000011804TWINSTAR INFRASTRUCTURENarendra A Patel18/07/2018
CC005000000011805TWINSTAR INFRASTRUCTURERamesh S Patel18/07/2018
CC005000000011806TWINSTAR INFRASTRUCTUREPravin S Patel18/07/2018
CC005000000011807Twinstar InfrastructureNitin N Patel18/07/2018
CC005000000011808TWINSTAR INFRASTRUCTUREChandresh V Patel18/07/2018
CC005000000011810TWINSTAR INFRASTRUCTUREPankajkumar V Patel19/07/2018
CC005000000011811TWINSTAR INFRASTRUCTUREAmbalal K Patel19/07/2018
CC005000000011812TWINSTAR INFRASTRUCTURENirmalkumar M Patel19/07/2018
CC005000000011813TWINSTAR INFRASTRUCTUREManojkumar R Patel19/07/2018
CC005000000011814TWINSTAR INFRASTRUCTURERashmikaben P Patel19/07/2018

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 1 Aug 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Feb 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Feb 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Dec 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jun 2027

Documents filed92

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 92 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 June 2026.pdf14 Aug 2026
Withdrawal Update Form 1File: Form 1 June 2026.pdf14 Aug 2026
Withdrawal Update Form 1File: Form 1 June 2026.pdf14 Aug 2026
Withdrawal Update Form 1File: Form 1 June 2026.pdf14 Aug 2026
Withdrawal Update Form 1File: Form 1 June 2026.pdf14 Aug 2026
Withdrawal Update Form 2File: Form 2 June 2026.pdf14 Aug 2026
Withdrawal Update Form 2File: Form 2 June 2026.pdf14 Aug 2026
Withdrawal Update Form 2File: Form 2 June 2026.pdf14 Aug 2026
Withdrawal Update Form 2File: Form 2 June 2026.pdf14 Aug 2026
Withdrawal Update Form 2File: Form 2 June 2026.pdf14 Aug 2026
Withdrawal Update Form 3File: Form 3 June 2026.pdf14 Aug 2026
Withdrawal Update Form 3File: Form 3 June 2026.pdf14 Aug 2026
Withdrawal Update Form 3File: Form 3 June 2026.pdf14 Aug 2026
Withdrawal Update Form 3File: Form 3 June 2026.pdf14 Aug 2026
Withdrawal Update Form 3File: Form 3 June 2026.pdf14 Aug 2026
Form 2A (FY 2025-2026)File: Form 2A FY 2025-26.pdf14 Aug 2026
Declaration in FORM BFile: Wing A Form B.pdf21 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20250313144904.pdf18 Mar 2025
Certificates of CA (Form 3)File: CA 21-08-2024_compressed.pdf18 Mar 2025
Certificates of CA (Form 3)File: 20250318074739.pdf18 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Adobe Scan Mar 17, 2025.pdf18 Mar 2025
CERSAI detailsFile: Cersai March.pdf18 Mar 2025
Declaration in FORM BFile: doc03415920250104165054.pdf6 Jan 2025
Declaration in FORM BFile: doc03415920250104165054.pdf6 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold Wing A.pdf6 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5 17-18.pdf27 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 9509 4.pdf27 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 18-19.pdf27 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 19-20.pdf27 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 20-21.pdf27 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 9509 3.pdf27 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 21-22.pdf27 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 9509 2.pdf27 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 9509 1.pdf27 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 9509.pdf27 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 23-24.pdf27 Dec 2024
Certificates of CA (Form 3)File: Form 3 21-8.pdf13 Dec 2024
Certificates of CA (Form 3)File: 20241213070757.pdf13 Dec 2024
Certificates of CA (Form 3)File: 20241213070713.pdf13 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 20241213070615.pdf13 Dec 2024
Commencement Certificates / NA Order for plotted developmentFile: Commencement Twinstar.pdf13 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Annual Report-1_rotated.pdf13 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20240713064648 (1).pdf1 Aug 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20240713064703 (2).pdf1 Aug 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20240713064814 (1).pdf1 Aug 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20240713064833 (1).pdf1 Aug 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20240713064846 (1).pdf1 Aug 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20240713064909 (3).pdf1 Aug 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20240801111542.pdf1 Aug 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20240801112916.pdf1 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 20240723040531.pdf1 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 20240723040548.pdf1 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 20240713064648 (1).pdf1 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 20240723040617.pdf1 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 20240801134828.pdf1 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 20240801134700.pdf1 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 04-05-2024 (3).pdf1 Aug 2024
Layout approvalFile: SKMBT_C36422090413190.pdf24 Feb 2024
Layout approvalFile: SKMBT_C36422090413190.pdf24 Feb 2024
Layout approvalFile: SKMBT_C36422090413190.pdf24 Feb 2024
Building plan approvalFile: HPSC0637_compressed.pdf24 Feb 2024
Building plan approvalFile: HPSC0637_compressed.pdf24 Feb 2024
PAN CardFile: Twinstar PanCard.pdf24 Feb 2024
PAN CardFile: Twinstar PanCard.pdf24 Feb 2024
Copy of Layout Approval (in case of layout)File: SKMBT_C36422090413190.pdf24 Feb 2024
Copy of Layout Approval (in case of layout)File: SKMBT_C36422090413190.pdf24 Feb 2024
Copy of Layout Approval (in case of layout)File: SKMBT_C36422090413190.pdf24 Feb 2024
Building Plan Approval (IOD)File: HPSC0637_compressed.pdf24 Feb 2024
Building Plan Approval (IOD)File: HPSC0637_compressed.pdf24 Feb 2024
Declaration about Commencement CertificateFile: SKMBT_C36422090413190.pdf24 Feb 2024
OtherFile: Deed Of Retirement.pdf14 Nov 2018
OtherFile: Self Decl.pdf21 Aug 2018
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf31 Mar 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch a.pdf31 Mar 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certi A wing.pdf31 Mar 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certi A wing.pdf31 Mar 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: eNG A.pdf31 Mar 2018
Certificates of CA (Form 3)File: CAC A.pdf31 Mar 2018
Layout approvalFile: PROPOSED LAYOUT ROYAL MANSION RAVET.pdf1 Aug 2017
Building plan approvalFile: A Floor Plan1.pdf1 Aug 2017

How this compares with Pune

85%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 30 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VAASTU IMPERIAL Wing A on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Ravet13,700+ in Pune

2 kmVAASTU IMPERIAL Wing ACompleted 108Lapsed / revoked 58Other 128Dot size: filed unitsN

Filed coordinates, straight-line distance. 294 registered projects within 2 km.

Builder: M/S Twin Star Infrastructure

M/S Twin Star Infrastructure has 3 registrations on MahaRERA, including VAASTU IMPERIAL Wing A and VAASTU IMPERIAL Wing B. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if VAASTU IMPERIAL Wing A is delayed beyond 30 Jun 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VAASTU IMPERIAL Wing A?

The registered promoter entity is M/S Twin Star Infrastructure, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VAASTU IMPERIAL Wing A?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against VAASTU IMPERIAL Wing A?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for VAASTU IMPERIAL Wing A?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VAASTU IMPERIAL Wing A?

The professionals named in the filing: Architect: ARCHITECT MILIND PATIL; Architect: Patil and Bugade Associates; Engineer: NIKHIL KHARAT; Engineer: S K Consultants and Engineers; Chartered Accountant: TILOKCHANDANI & ASSOCIATES; Chartered Accountant: Ashish Rathi and Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VAASTU IMPERIAL Wing A?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VAASTU IMPERIAL Wing A. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VAASTU IMPERIAL Wing A to a free account