Home / Browse projects / Thane, Maharashtra / UNNATHI WOODS PHASE VIII
UNNATHI WOODS PHASE VIII
RG-MH-03365 · RERA P51700020921 · Last updated on MahaRERA portal: 11 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 5 complaints at MahaRERA
- Completion date moved by 30 months
- 1 extension taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
- All 4 earlier projects delivered on promise
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
UNNATHI WOODS PHASE VIII is a Residential / Group Housing project by UNNATHI ESTATES in Thane, Maharashtra, registered with MahaRERA as P51700020921 on 23 May 2019. Possession is promised by 31 Dec 2027. The completion date has moved by 30 months from the original filing. 238 of the 296 units on this registration are recorded sold or booked, and 17 of 22 construction stages are filed complete. 5 complaints are on record with the regulator.
At a glance
Project
- NameUNNATHI WOODS PHASE VIII
- TypeResidential / Group Housing
- Location
- G. B. ROAD
- KAVESAR
- Thane (M Corp.)
- Thane
- 400615
- Pincode400615
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700020921
- ReraGenie IDRG-MH-03365
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on23 May 2019
- Promised completion31 Dec 2027
- Revised completionRevised to 31 Dec 2027 (originally 30 Jun 2025)
- Buildings2 building records
- Documents filed92 files
Current status
Figures as on 11 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SUPREME A 1ST TO 24TH FLOOR | NA | 25 | 25 | 153 | 0 | 153 |
| SUPREME A 25TH TO 45TH FLOOR | NA | 22 | 22 | 143 | 0 | 143 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 11 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
17 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Installation of Lifts, at 90%.
SUPREME A 1ST TO 24TH FLOOR90%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
SUPREME A 25TH TO 45TH FLOOR86%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 90% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 60% |
Progress on shared amenities15
As on 11 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 50% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 80% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 90% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 50% |
Parking filed190
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| SUPREME A 1ST TO 24TH FLOOR | 189 | 189 |
| SUPREME A 25TH TO 45TH FLOOR | 1 | 1 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| SUPREME A 1ST TO 24TH FLOOR | NA | Rs 50.00 cr | Rs 49.20 cr |
| SUPREME A 25TH TO 45TH FLOOR | NA | Rs 50.00 cr | Rs 49.20 cr |
| - | NA | Rs 24.00 cr | Rs 25.06 cr |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | GODBOLE MUKADAM & ASSOCIATES |
| Engineer | RAJAN TIPNIS |
| Engineer | UMASHANKAR ROUTRAY |
| Engineer | HARSHAL MANOHARRAO POTODE |
| Chartered Accountant | ANKIT GOYANKA |
| Chartered Accountant | SANDEEP SHETH |
| Partner | Role in project |
|---|---|
| UNNATHI ESTATES | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDear Sir, We have registered the above referred project namely UNNATHI WOODS PHASE VIII comprising of Ground (P) + Stilt (P) + 1st to 22nd + 23rd Recreational Floor + 24th Floor under the provision of RERA, Mumbai vide registration no. P51700020921 for a period commencing from 23/05/2019 and ending with 30/06/2025. We had envisaged the construction of tower consisting of 50 floors. However based on the available FSI at the relevant time we proposed the building upto 24th floor only with permission to propose additional floors/ building to consume full fSI. As per the revised sanctioned plan da
Complaints filed with MahaRERA5
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000408632 | Vikramaditya Ahuja | Unnathi Estates | 25/12/2023 |
| CC12504234 | Anita Bhoopati Borkar | UNNATHI ESTATES | 29/11/2025 |
| CC12602291 | Santosh Yoginder Kaul | UNNATHI ESTATES | 18/04/2026 |
| CC12600965 | naveen nagar | UNNATHI ESTATES | 22/02/2026 |
| CC12603133 | Ashish Chandorkar | UNNATHI ESTATES | 26/05/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 15 May 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 12 Jan 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 12 Jan 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 12 Jan 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2027
Documents filed92
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 92 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2025-2026)File: Form 2A Raunak Supreme UE.pdf | 11 Jun 2026 |
| Withdrawal Update Form 1File: Form 1 Supreme 31032026.pdf | 24 Apr 2026 |
| Withdrawal Update Form 2File: Withdrawal Application Form 2 Supreme.pdf | 24 Apr 2026 |
| Withdrawal Update Form 3File: CA Certificate VIII 31032026.pdf | 24 Apr 2026 |
| Withdrawal Update Form 1File: Form1 Supreme Dec 25.pdf | 10 Feb 2026 |
| Withdrawal Update Form 2File: Form2 Supreme (DEC 25).pdf | 10 Feb 2026 |
| Withdrawal Update Form 3File: CA Certificate VIII 31122025.pdf | 10 Feb 2026 |
| Withdrawal Update Form 1File: Form 1 Supreme.pdf | 14 Nov 2025 |
| Withdrawal Update Form 1File: Supreme Form1 300625.pdf | 14 Nov 2025 |
| Withdrawal Update Form 2File: Form 2 Supreme.pdf | 14 Nov 2025 |
| Withdrawal Update Form 2File: Form 2 Supreme 300625.pdf | 14 Nov 2025 |
| Withdrawal Update Form 3File: Signed CA Certificate VIII 30092025.pdf | 14 Nov 2025 |
| Withdrawal Update Form 3File: Signed CA Certificate RR 30062025.pdf | 14 Nov 2025 |
| Form 5 (FY 2024-2025)File: UW Ph VIII Supreme.pdf | 1 Nov 2025 |
| Form 2A (FY 2024-2025)File: Form 2A UE Supreme.pdf | 13 Oct 2025 |
| Form 1File: Form 1 Supreme 31325.pdf | 29 Jun 2025 |
| Form 2File: Form 2 Supreme.pdf | 29 Jun 2025 |
| Form 3File: Signed CA Certificate VIII 31032025.pdf | 29 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Unnathi Woods supreme Sold Inventory 31032025.pdf | 29 Jun 2025 |
| Certificates of CA (Form 3)File: Signed CA Certificate VIII 311224.pdf | 10 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer's Certificate UW VIII 311224.pdf | 10 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: Supreme 31122024.pdf | 10 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Raunak Supreme 30092024.pdf | 13 Dec 2024 |
| Certificates of CA (Form 3)File: Signed CA Certificate VIII 30092024.pdf | 13 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Supreme.pdf | 29 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 27_Form-2A-Unnathi Woods VIII.pdf | 2 Jul 2024 |
| Other - TechnicalFile: Work Schedule.pdf | 7 Feb 2024 |
| Proforma of Allotment letterFile: Allotment Letter N.pdf | 16 Jan 2024 |
| Proforma of Agreement for saleFile: FSA UW Phase VIII.pdf | 16 Jan 2024 |
| Deviation Report with respect to Allotment letterFile: Deviation report.pdf | 16 Jan 2024 |
| Deviation Report with respect to model copy of AgreementFile: DEVIATION FSI N.pdf | 16 Jan 2024 |
| Layout approvalFile: 10_Supreme-Layout.pdf | 12 Jan 2024 |
| Building plan approvalFile: Building Plan - 1.pdf | 12 Jan 2024 |
| Building plan approvalFile: Building Plan - 2.pdf | 12 Jan 2024 |
| PAN CardFile: 1_Pan-Card.pdf | 12 Jan 2024 |
| Copy of Layout Approval (in case of layout)File: 10_Supreme-Layout.pdf | 12 Jan 2024 |
| Building Plan Approval (IOD)File: Building Plan - 1.pdf | 12 Jan 2024 |
| Building Plan Approval (IOD)File: Building Plan - 2.pdf | 12 Jan 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: 9_CC-Dt-05-12-2023.pdf | 12 Jan 2024 |
| Declaration about Commencement CertificateFile: Declaration of CC - 45 Floor.pdf | 12 Jan 2024 |
| Declaration about Commencement CertificateFile: Declaration of CC - 45 Floor.pdf | 12 Jan 2024 |
| Declaration in FORM BFile: 7_Form-B.pdf | 12 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Ar Certificate ph VIII.pdf | 12 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ER Certificate.pdf | 12 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: UW_VIII.pdf | 12 Jan 2024 |
| CERSAI detailsFile: Cersai Declaration.pdf | 12 Jan 2024 |
| Certificates of CA (Form 3)File: CA Certificate-VIII.pdf | 12 Jan 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration - separate bank account.pdf | 12 Jan 2024 |
| Building plan approvalFile: UW SUPREME BUILDING PLAN.pdf | 9 Jan 2024 |
| Layout approvalFile: UW SUPREME LAYOUT PLAN.pdf | 9 Jan 2024 |
| Copy of Layout Approval (in case of layout)File: UW SUPREME LAYOUT PLAN.pdf | 9 Jan 2024 |
| Building Plan Approval (IOD)File: UW SUPREME BUILDING PLAN.pdf | 9 Jan 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: SUPREME CC.pdf | 9 Jan 2024 |
| Declaration about Commencement CertificateFile: Declaration of CC.pdf | 9 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AC_Supreme.pdf | 9 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EC_supreme.pdf | 9 Jan 2024 |
| Certificates of CA (Form 3)File: CA Certificate - VIII.pdf | 9 Jan 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration of seprate Bank Account.pdf | 9 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Sold-UW Phase VIII Supreme 31122023.pdf | 6 Jan 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Kushal Kirti Shah.pdf | 6 Jan 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: RNB.pdf | 6 Jan 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Sangeeta Kirti Shah.pdf | 6 Jan 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Shyamal Vijay Mody.pdf | 6 Jan 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Sumit Vijay Mody.pdf | 6 Jan 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Rera - Disclosure of Interest in other RERA_KKS.pdf | 5 Jan 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Rera - Disclosure of Interest in other RERA_RNB.pdf | 5 Jan 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form5_UW_Supreme.pdf | 23 Nov 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Unnathi Woods Phase-VIII Form 2A 2023.pdf | 4 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: UE_FORM5_UNNATHI WOODS PHASE VIII_21-22.pdf | 22 Oct 2022 |
| Details of encumbrancesFile: Supreme-BHFL.pdf | 18 May 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: UW_VIII.pdf | 2 May 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Unnathi Woods Phase VIII.pdf | 8 Apr 2022 |
| Proforma of Allotment letterFile: Unnathi Woods Phase VIII - Supreme.pdf | 1 Feb 2022 |
| Engineers Certificate on Quality Assurance (Form 2A)File: Unnathi Woods VIII.pdf | 18 Jan 2022 |
| Engineers Certificate on Quality Assurance (Form 2A)File: Unnati Woods VIII.pdf | 18 Oct 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Unnathi Woods - VIII.pdf | 17 Mar 2021 |
| Declaration in FORM BFile: Form B UW Phase VIII.pdf | 15 Dec 2020 |
| Details of Restarting of Construction work post lockdownFile: UE - UW - VIII RERA Updation - Restarting Work.pdf | 26 Jun 2020 |
| Engineers Certificate on Quality Assurance (Form 2A)File: Unnathi Woods Phase VIII.pdf | 3 Jan 2020 |
| Engineers Certificate on Quality Assurance (Form 2A)File: Form - 2A UW-VIII.pdf | 7 Nov 2019 |
Promoter's earlier projects4
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| UNNATHI WPPDS PHASE III C2 | ANAND NAGAR BEHIND MUCHCHHALA COLLEGE KAVESAR GHODBUNDER ROAD THANE | 124 | Completed | Dec 2016 | Oct 2016 |
| UNNATHI WOODS PHASE II | ANAND NAGAR BEHIND MUCHCHHALA COLLEGE KAVESAR GHODBUNDER ROAD THANE | 252 | Completed | Mar 2012 | Mar 2012 |
| UNNATHI WOODS PHASE I | ANAND NAGAR BEHIND MUCHCHHALA COLLEGE KAVESAR GHODBUNDER ROAD THANE | 270 | Completed | Mar 2012 | Mar 2012 |
| UNNATHI WOODS PHASE IV BUILDING D AND E | ANAND NAGAR BEHIND MUCHCHHALA COLLEGE KAVESAR GHODBUNDER ROAD THANE | 378 | Completed | Mar 2011 | Mar 2011 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 6 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 92 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep UNNATHI WOODS PHASE VIII on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near KAVESAR7,600+ in Thane
Filed coordinates, straight-line distance. 167 registered projects within 2 km.
Godrej Emerald Thane
Godrej Greenview Housing Private Limited
NORTH IMPERIAL GREENS -TOWER 2
Skylark Buildspace Private Limited
VIHANG MARINA
BALAJI ENTERPRISES
Puranik City Reserva Phase 1
Puranik Builders Limited
NORTH IMPERIAL GREENS - TOWER 1
Skylark Buildspace Private Limited
RAUNAK 108
UNNATHI ASSOCIATES
See every Thane project, with the district possession charts
Builder: UNNATHI ESTATES
UNNATHI ESTATES has 7 registrations on MahaRERA, including UNNATHI WOODS PHASE VII A and UNNATHI WOODS PHASE III - C1. Its filings disclose 6 earlier MahaRERA projects: declares 6 of 6 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What are my rights if UNNATHI WOODS PHASE VIII is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of UNNATHI WOODS PHASE VIII?
The registered promoter entity is UNNATHI ESTATES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in UNNATHI WOODS PHASE VIII?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against UNNATHI WOODS PHASE VIII?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for UNNATHI WOODS PHASE VIII?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at UNNATHI WOODS PHASE VIII?
The professionals named in the filing: Architect: GODBOLE MUKADAM & ASSOCIATES; Engineer: RAJAN TIPNIS; Engineer: UMASHANKAR ROUTRAY; Engineer: HARSHAL MANOHARRAO POTODE; Chartered Accountant: ANKIT GOYANKA; Chartered Accountant: SANDEEP SHETH. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in UNNATHI WOODS PHASE VIII?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback