Home / Browse projects / Pune, Maharashtra / TWIN TOWERS PH 1

Registration lapsed No litigation declared Others project

TWIN TOWERS PH 1

By LEGACY TOWERS ASSOCIATES LLP

RG-MH-99025 · RERA P52100016464 · Last updated on MahaRERA portal: 27 Mar 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 43 months past the filed date
  • 2 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Mar 2023Possession promised43 months past this date
50 of 55Construction stages doneacross 5 buildings; furthest along: Podiums (if any), 0%
2Complaints at MahaRERAon this registration
Jump to the 69 documents Report an error

TWIN TOWERS PH 1 is a Others project by LEGACY TOWERS ASSOCIATES LLP in Pune, Maharashtra, registered with MahaRERA as P52100016464 on 11 May 2018. Possession was promised by 30 Mar 2023 and is now 43 months past that date. 2 complaints are on record with the regulator.

At a glance

Project

  • NameTWIN TOWERS PH 1
  • TypeOthers
  • Location
    • MHASKHE WASTI ROAD
    • RAVET
    • Pimpri Chinchawad (M Corp.)
    • Haveli
    • Pune
    • 412101
  • Pincode412101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100016464
  • ReraGenie IDRG-MH-99025

Builder

  • NameLEGACY TOWERS ASSOCIATES LLP
  • Entity typePartnership
  • PartnersAMIT VINOD BANSAL, ATUL NAGRAJ JAIN, DIVESH VINOD JAIN, YOGESH NAGRAJ JAIN, AMIT NAGRAJ JAIN, JITENDRA MOHANLAL JAIN, KIRANRAJ KESHARIMAL SONIGARA

Key dates

43 months past promisethis monthRegisteredMay 2018PromisedMar 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on11 May 2018
  • Promised completion30 Mar 2023
  • Revised completionNone
  • Buildings5 building records
  • Documents filed69 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING ANA130000
WING BNA130000
WING CNA110000
WING DNA110000
WING ENA00000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 27 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

50 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Podiums (if any), at 0%.

WING A91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
WING B91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
WING C91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
WING D91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
WING E91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 27 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes0%

Parking filed2

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots2
Closed/Covered2
BuildingClosed/CoveredTotal
WING A11
WING B11

Land and ownership7

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area8,012 sq m
Land owned byThe promoter, with other names on the file
Named landowners7
LandownerVillageDistrict
KHEMCAND UTTMCHAND BHOJWANIPimpri Chinchawad (M Corp.)Pune
ANIL CHANDIRAM PHERWANIPimpri Chinchawad (M Corp.)Pune
RAJESH KANKARAJ PATNIPimpri Chinchawad (M Corp.)Pune
ARUN SHANKAR BHONDVEPimpri Chinchawad (M Corp.)Pune
SUDAM SHANKAR BHONDVEPimpri Chinchawad (M Corp.)Pune
YAMUNA KISAN BHONDVEPimpri Chinchawad (M Corp.)Pune
KIRAN CHANDU RAMNANIPimpri Chinchawad (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPCMC
Permissible FSI12024.41
Proposed, not sanctioned6,216 sq m
Buildings approved5
Buildings sanctioned5

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchEMPIRE ESTATE CHINCHWAD

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRICHA POTDAR
EngineerBHAVESH D CHAVAN
Chartered AccountantSUMEET SURESH KATE&CO
PartnerRole in project
LEGACY TOWERS ASSOCIATES LLP-

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC005000000043739KIRAN CHANDU RAMNANILEAGACY TOWERS ASSOCIATES LLP02/12/2019
CC005000000147228Kiran Chandu RamnaniLegacy Towers now it is known as Legacy Towers Associates LLP Thr its Partner Mr. Sachin Sonigara16/06/2022

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Apr 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 19 Sep 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Apr 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Sep 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 27 Mar 2025

Documents filed69

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: ilovepdf_merged (50).pdf27 Mar 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: w.pdf25 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS CER FINAL .pdf10 Mar 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: AB SOCIETY.pdf10 Mar 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: CD SOCIETY.pdf10 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS CER FINAL .pdf10 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM5 LEGACY.pdf2 Feb 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: CDE COMPLICTION.pdf30 Jan 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: PART COM.pdf30 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS _compressed.pdf4 Aug 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: COMPLI.pdf4 Aug 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHI.pdf2 May 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHI.pdf2 May 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHDCE.pdf2 May 2022
Certificates of CA (Form 3)File: CA FORM.pdf2 May 2022
Certificates of CA (Form 3)File: CA.pdf2 May 2022
Certificates of CA (Form 3)File: CA -31-03-2021.pdf7 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: AB.pdf26 Jun 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: CDE.pdf26 Jun 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: CDE.pdf9 Dec 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: AB.pdf9 Dec 2020
Certificates of CA (Form 3)File: 3092020L.pdf9 Dec 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: CED.pdf24 Aug 2020
Certificates of CA (Form 3)File: 31-3-2020 CA LEGACY.pdf13 Aug 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA AB.pdf12 Jun 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: C E D.pdf12 Jun 2020
Certificates of CA (Form 3)File: 30-9-2019 CA TWIN TOWERS.pdf12 Feb 2020
Certificates of CA (Form 3)File: CA TWIN TOWERS.pdf12 Feb 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: C D E WING.pdf5 Feb 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: SCAN_20191225_163403972.pdf25 Dec 2019
OtherFile: SCAN_20191225_164553909.pdf25 Dec 2019
OtherFile: SCAN_20191220_112908330.pdf20 Dec 2019
OtherFile: rera bank letter.pdf25 Nov 2019
Details of encumbrancesFile: SCAN_20191115_170452319.pdf15 Nov 2019
Details of encumbrancesFile: 1_compressed.pdf15 Nov 2019
Details of encumbrancesFile: 2_compressed.pdf15 Nov 2019
Details of encumbrancesFile: 3_compressed.pdf15 Nov 2019
Details of encumbrancesFile: 4_compressed.pdf15 Nov 2019
Details of encumbrancesFile: 5_compressed.pdf15 Nov 2019
Details of encumbrancesFile: 6_compressed.pdf15 Nov 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS -30-9-2019.pdf8 Nov 2019
Proforma of Allotment letterFile: DRAFT.pdf26 Sep 2019
Certificates of CA (Form 3)File: CA.pdf21 Sep 2019
Layout approvalFile: PLAN COPY.pdf19 Sep 2019
Copy of Layout Approval (in case of layout)File: PLAN COPY.pdf19 Sep 2019
Commencement Certificates / NA Order for plotted developmentFile: C C CPOY_compressed.pdf19 Sep 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS.pdf19 Sep 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS 30-6-2019_compressed (1).pdf8 Aug 2019
Certificates of CA (Form 3)File: TWIN TOWERS -31-3-2019.pdf13 Jul 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 31-3-2019.pdf13 May 2019
Certificates of CA (Form 3)File: CA.pdf4 Mar 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 31-12-2018 -LEGACY.pdf14 Jan 2019
Certificates of CA (Form 3)File: 30-9-2018.pdf12 Dec 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS -30-9-2018.pdf11 Oct 2018
Certificates of CA (Form 3)File: 30-6-2018.pdf19 Sep 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 30-6-2018.pdf23 Jul 2018
Proforma of Allotment letterFile: LEGACY TOWER -RERA AGREE 123.pdf3 May 2018
Details of encumbrancesFile: LITIGATION.pdf30 Apr 2018
Declaration in FORM BFile: FORM B 930-ilovepdf-compressed.pdf30 Apr 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1st architect certificate-ilovepdf-compressed.pdf30 Apr 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS CERTIFICATE.pdf30 Apr 2018
Layout approvalFile: LAY OUT-ilovepdf-compressed.pdf27 Apr 2018
Building plan approvalFile: PLAN COPY-ilovepdf-compressed.pdf27 Apr 2018
PAN CardFile: PAN.pdf27 Apr 2018
Copy of the legal title reportFile: SEARCH-ilovepdf-compressed.pdf27 Apr 2018
Copy of Layout Approval (in case of layout)File: LAY OUT-ilovepdf-compressed.pdf27 Apr 2018
Building Plan Approval (IOD)File: PLAN COPY-ilovepdf-compressed.pdf27 Apr 2018
Commencement Certificates / NA Order for plotted developmentFile: C C COPY-ilovepdf-compressed.pdf27 Apr 2018
Certificates of CA (Form 3)File: CA.pdf27 Apr 2018

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep TWIN TOWERS PH 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near RAVET13,700+ in Pune

2 kmTWIN TOWERS PH 1Completed 114Lapsed / revoked 44Other 105Dot size: filed unitsN

Filed coordinates, straight-line distance. 263 registered projects within 2 km.

Builder: LEGACY TOWERS ASSOCIATES LLP

LEGACY TOWERS ASSOCIATES LLP has 1 registration on MahaRERA, including TWIN TOWERS PH 1. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that TWIN TOWERS PH 1 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if TWIN TOWERS PH 1 is delayed beyond 30 Mar 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of TWIN TOWERS PH 1?

The registered promoter entity is LEGACY TOWERS ASSOCIATES LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in TWIN TOWERS PH 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against TWIN TOWERS PH 1?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for TWIN TOWERS PH 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at TWIN TOWERS PH 1?

The professionals named in the filing: Architect: RICHA POTDAR; Engineer: BHAVESH D CHAVAN; Chartered Accountant: SUMEET SURESH KATE&CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in TWIN TOWERS PH 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About TWIN TOWERS PH 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save TWIN TOWERS PH 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.