Home / Browse projects / Pune, Maharashtra / Tropica Phase II
Tropica Phase II
By Om Developers Project Ravet
RG-MH-19624 · RERA P52100008711 · Last updated on MahaRERA portal: 12 May 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 25 months past the filed date
- 17 complaints at MahaRERA
- Completion date moved by 44 months
- 5 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Tropica Phase II is a Residential / Group Housing project by Om Developers Project Ravet in Pune, Maharashtra, registered with MahaRERA as P52100008711 on 19 Aug 2017. Possession was promised by 30 Sep 2024 and is now 25 months past that date. The completion date has moved by 44 months from the original filing. 17 complaints are on record with the regulator.
At a glance
Project
- NameTropica Phase II
- TypeResidential / Group Housing
- Location
- Pimpri Chinchawad (M Corp.)
- Haveli
- Pune
- 412101
- Pincode412101
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100008711
- ReraGenie IDRG-MH-19624
Builder
- NameOm Developers Project Ravet
- Entity typePartnership
- PartnersArvind Gajanan Awati, Devendra Arvind Awati, Shirish Govind Sukhatme, Nandkumar Shriram Chandorkar, Atul Ratnakar Mahashabde, VIJAY SURESH MANTRI
- Other registrations2 more →
- Completed1 of 3
- No longer live2 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on19 Aug 2017
- Promised completion30 Sep 2024
- Revised completionRevised to 30 Sep 2024 (originally 30 Jan 2021)
- Buildings3 building records
- Documents filed138 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Building E | NA | 14 | 0 | 0 | 0 | 0 |
| Building F | NA | 14 | 0 | 0 | 0 | 0 |
| Building H | NA | 14 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 12 May 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
23 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Staircases, at 98%.
Building E84%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 70% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 98% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 90% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 75% |
Building F86%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 75% |
| Sanitary Fittings within the flats / premises | 71% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building H91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 12 May 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 90% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 50% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 90% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 66% |
| Fire protection and fire safety requirements | Yes | 70% |
| Electrical meter room, sub-station, receiving station | Yes | 50% |
| Aggregate area of recreational Open Space | Yes | 30% |
| Open Parking | Yes | 0% |
Parking filed246
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| Building E | 28 | 66 | 94 |
| Building F | 26 | 66 | 92 |
| Building H | 20 | 40 | 60 |
Land and ownership2
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Mr. Shashikant Shankar Sahasrabuddhe | Pimpri Chinchawad (M Corp.) | Pune |
| Ravishankar Shashikant Sahasrabuddhe | Pimpri Chinchawad (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Vikas Achalkar |
| Engineer | Mr. Bal Kulkarni - DELCONS |
| Partner | Role in project |
|---|---|
| Om Developers Project Ravet | - |
Extensions applied for5
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDUE TO COVID SUFFER FINACIAL CRUNCH AND NO NEW BOOKING .
Reason as filed by the promoterWE ARE UNABLE TO COMPLETE WHITEN SAID TIME PERIOD ,BECAUSE COVID EFFECT ON OUR PROJECT & TODAYS LABOUR COST ,MATERIEL COST RISE .SO PLEASE EXTENSION OUR RERA COMPLETION DATE.
Reason as filed by the promoterDUE TO PANDAMIC LABOUR SHORTAGE WE COULD NOT ACHIEVE COMPLETION STAGE. OUT OF 3 BUILDINGS WE HAVE COMPLETED ONE BUILDING i.e.H Building.Applying for completion. We have completed rcc , brickwork . Plaster work is @ 80% complete. for E building Flooring is also complete for44 flats , for 88 flats is complete cncealed plumbing.internal gypsum is 80% complete. F buildind internal gypsum 80% complete.
Reason as filed by the promoterDUE TO PANDAMIC LABOUR SHORTAGE WE COULD NOT ACHIEVE COMPLETION STAGE. OUT OF 3 BUILDINGS WE HAVE COMPLETED ONE BUILDING i.e.H Building.Applying for completion. We have completed rcc , brickwork . Plaster work is @ 100% complete. for E building Flooring is also complete for 68 flats , for 88 flats is complete cncealed plumbing.internal gypsum is 80% complete. F buildind RCC BRICK WORK PLASTER internal gypsum 90% complete and tilling of flat and comon area complete with lifts.
Reason as filed by the promoterSOME OUR FINANCIAL ISSUE BECAUSE WE ARE CLOSED IIFL CONSTRUCTION LOAN & CUSTOMER BOOKING ARE VERY DOWN THERE IS WE ARE UNABLE COMPLETE OUR PROJECT.
Litigation declared3
| Case | Court | Status |
|---|---|---|
| 1366/2015 | Karande Court | Pending for evidence |
| 2246/2014 | Bhosale Court | Hearing before charge |
| 994/2012 | Paldewar Court | Argument on exhibit |
Complaints filed with MahaRERA17
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000258951 | shirish govind sukhatme | M/S Om Developer | 02/06/2023 |
| CC005000000043631 | Barun Kumar Singh | Atul Ratnakar Mahashabde | 06/12/2019 |
| CC005000000053901 | Shripad Vijay Katkamwar | Mr. Atul Ratnakar Mahashabde | 12/01/2020 |
| CC005000000075122 | Ravi Pant | Devendra Arvind Awati | 10/06/2021 |
| CC005000000085413 | Vinay Vasant Bhalerao | Tropica Phase II ThroughMr. Devendra Awati | 01/04/2021 |
| CC005000000085421 | Girish Gautam Kate | Devendra Arvind Awati | 18/04/2021 |
| CC005000000085681 | Manish Kumar | Devendra Arvind Awati | 17/01/2022 |
| CC005000000085667 | Prasad Nandkumar Pagar | Devendra Arvind Awati | 11/06/2021 |
| CC005000000106435 | Charudatta Jagannath Andhare | Atul Ratnakar Mahashabde, Devendra Arvind Awati (M/S OM developers) | 26/01/2022 |
| CC005000000106441 | Suhas Deshmukh | Ravishankar Shashikant Sahasrabuddhe | 05/03/2022 |
| CC005000000106507 | Himanshu Gambhire | OM Developer Through Promoter Mr. Atul Mahashabde | 19/01/2022 |
| CC005000000106665 | Rupesh Dhule | Devendra Awati, Atul Mahashabhde | 08/03/2022 |
| CC005000000106667 | Srikakolapu Venkata Mohana Krishna | Devendra Awati, Atul Mahashabde | 08/03/2022 |
| CC005000000106855 | Lalit Rade | Atul Ratnakar Mahashabde | 28/03/2022 |
| CC005000000279839 | Navnath Vitthal Bhise | Mr. Devendra Arvind Awati | 10/12/2023 |
| CC005000000279942 | SUNIL SHANKARRAO BANDAL | DEVENDRA ARVIND AWATI | 25/12/2023 |
| CC005000000289971 | Nikhil Anil Golande | Devendra Auti | 29/12/2023 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 29 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 3 May 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 3 May 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 29 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed138
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 138 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 Certificates of Architect (Form 1) 2017-18.pdf | 12 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 14 Certificates of Architect (Form 1)(Mandatory for only ongoing project).pdf | 12 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: ENGINEERS Certificate on Quality Assurance 2017-18.pdf | 12 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: ENGINEERS Certificate on Quality Assurance 2018-19.pdf | 12 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: ENGINEERS Certificate on Quality Assurance 2019-20.pdf | 12 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21).pdf | 12 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 2 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24).pdf | 12 May 2024 |
| Disclosure of sold/ booked inventoryFile: 2017-18.pdf | 12 May 2024 |
| Disclosure of sold/ booked inventoryFile: 2018-19.pdf | 12 May 2024 |
| Disclosure of sold/ booked inventoryFile: 2019-20.pdf | 12 May 2024 |
| Disclosure of sold/ booked inventoryFile: 2020-21.pdf | 12 May 2024 |
| Disclosure of sold/ booked inventoryFile: 2021-22 Q3.pdf | 12 May 2024 |
| Disclosure of sold/ booked inventoryFile: 2021-22 Q4.pdf | 12 May 2024 |
| Disclosure of sold/ booked inventoryFile: 2022-23 Q1.pdf | 12 May 2024 |
| Disclosure of sold/ booked inventoryFile: 2022-23 Q2.pdf | 12 May 2024 |
| Disclosure of sold/ booked inventoryFile: 2022-23 Q3.pdf | 12 May 2024 |
| Disclosure of sold/ booked inventoryFile: 2022-23 Q4.pdf | 12 May 2024 |
| Disclosure of sold/ booked inventoryFile: 2023-24 Q1.pdf | 12 May 2024 |
| Disclosure of sold/ booked inventoryFile: 2023-24 Q2.pdf | 12 May 2024 |
| Disclosure of sold/ booked inventoryFile: 5 Disclosure of sold_ booked inventory.pdf | 12 May 2024 |
| Disclosure of sold/ booked inventoryFile: 6 Disclosure of sold_ booked inventory (1).pdf | 12 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 18-19 IMP.pdf | 7 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 19-20 IMP.pdf | 7 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch 20-21 xx_page-0001.pdf | 7 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch 21-22 Q3 xx_page-0001.pdf | 7 May 2024 |
| Disclosure of sold/ booked inventoryFile: ODR SOLD UNSOLD INVENTORY.pdf | 7 May 2024 |
| Layout approvalFile: page 1_compressed.pdf | 3 May 2024 |
| Building plan approvalFile: page 15.pdf | 3 May 2024 |
| Building plan approvalFile: page 16.pdf | 3 May 2024 |
| Building plan approvalFile: page 17.pdf | 3 May 2024 |
| Building plan approvalFile: page 18.pdf | 3 May 2024 |
| Building plan approvalFile: page 19.pdf | 3 May 2024 |
| Building plan approvalFile: page 20.pdf | 3 May 2024 |
| Building plan approvalFile: page 21.pdf | 3 May 2024 |
| Building plan approvalFile: page 22.pdf | 3 May 2024 |
| Building plan approvalFile: page 27.pdf | 3 May 2024 |
| Building plan approvalFile: page 28.pdf | 3 May 2024 |
| Building plan approvalFile: page 29.pdf | 3 May 2024 |
| Building plan approvalFile: page 30.pdf | 3 May 2024 |
| Copy of Layout Approval (in case of layout)File: page 1_compressed.pdf | 3 May 2024 |
| Building Plan Approval (IOD)File: page 15.pdf | 3 May 2024 |
| Building Plan Approval (IOD)File: page 16.pdf | 3 May 2024 |
| Building Plan Approval (IOD)File: page 17.pdf | 3 May 2024 |
| Building Plan Approval (IOD)File: page 18.pdf | 3 May 2024 |
| Building Plan Approval (IOD)File: page 19.pdf | 3 May 2024 |
| Building Plan Approval (IOD)File: page 20.pdf | 3 May 2024 |
| Building Plan Approval (IOD)File: page 21.pdf | 3 May 2024 |
| Building Plan Approval (IOD)File: page 22.pdf | 3 May 2024 |
| Building Plan Approval (IOD)File: page 27.pdf | 3 May 2024 |
| Building Plan Approval (IOD)File: page 28.pdf | 3 May 2024 |
| Building Plan Approval (IOD)File: page 29.pdf | 3 May 2024 |
| Building Plan Approval (IOD)File: page 30.pdf | 3 May 2024 |
| Layout approvalFile: Layout Plan Tropica.pdf | 25 Apr 2024 |
| Copy of Layout Approval (in case of layout)File: Layout Plan Tropica.pdf | 25 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch 22-23 Q1_page-0001.pdf | 23 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch 22-23 Q1_page-0001.pdf | 23 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch 22-23 Q2_page-0001.pdf | 23 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch 22-23 Q3_page-0001.pdf | 23 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch 22-23 Q4_page-0001.pdf | 23 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch 23-24 Q1_page-0001.pdf | 23 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch 23-24 Q2_page-0001.pdf | 23 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch 23-24 Q3_page-0001.pdf | 23 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch 23-24 Q4_page-0001.pdf | 23 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch 18-19.pdf | 23 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch 19-20.pdf | 23 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG 17-18.pdf | 23 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG 18-19.pdf | 23 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG 19-20.pdf | 23 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG 20-21.pdf | 23 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG 21-22 Q3.pdf | 23 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG 21-22 Q4.pdf | 23 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG 22-23 Q1.pdf | 23 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG 22-23 Q2.pdf | 23 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG 22-23 Q3.pdf | 23 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG 22-23 Q4.pdf | 23 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG 23-24 Q1.pdf | 23 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG 23-24 Q2.pdf | 23 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG 23-24 Q3.pdf | 23 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG 23-24 Q4.pdf | 23 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: ENGINEERS Certificate on Quality Assurance (Form 2A FY 2022 - 2023)_page-0001.pdf | 23 Apr 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 138 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Tropica Phase II on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Pimpri Chinchawad (M Corp.)13,700+ in Pune
Filed coordinates, straight-line distance. 247 registered projects within 2 km.
Godrej Park Greens
Godrej Skyline Developers Limited
FOREST GROVE AT GODREJ PARK GREENS
Godrej Skyline Developers Limited
Om Mangalam Samruddhi
NDG Homes LLP
PCMC EWS KIWALE
Pimpri Chinchwad Municipal Corporation
Godrej Nurture
Godrej Skyline Developers Limited
My Home Sanctuary Phase I
MAMURDI DEVELOPERS LLP
Builder: Om Developers Project Ravet
Om Developers Project Ravet has 3 registrations on MahaRERA, including Tropica Phase II and TROPICA PHASE I. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that Tropica Phase II shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Tropica Phase II is delayed beyond 30 Sep 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Tropica Phase II?
The registered promoter entity is Om Developers Project Ravet, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Tropica Phase II?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Tropica Phase II?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Tropica Phase II?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Tropica Phase II?
The professionals named in the filing: Architect: Vikas Achalkar; Engineer: Mr. Bal Kulkarni - DELCONS. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Tropica Phase II?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback