Completed No litigation declared Residential / Group Housing project

TRISHABH GREENS - WING B

By RISHABH ENTERPRISES

RG-MH-47880 · RERA P51800018350 · Last updated on MahaRERA portal: 10 Feb 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 4 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2025Possession promisedregistration recorded completed
9 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 114 documents Report an error

TRISHABH GREENS - WING B is a Residential / Group Housing project by RISHABH ENTERPRISES in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800018350 on 24 Oct 2018. The registration is recorded completed; possession was promised by 30 Dec 2025.

At a glance

Project

  • NameTRISHABH GREENS - WING B
  • TypeResidential / Group Housing
  • Location
    • OFF R C MARG
    • CHEMBUR NAKA
    • CHEMBUR EAST
    • Kurla
    • Mumbai Suburban
    • 400071
  • Pincode400071
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800018350
  • ReraGenie IDRG-MH-47880

Builder

  • NameRISHABH ENTERPRISES
  • Entity typePartnership
  • PartnersSHANTILAL HARAKLAL BADALA, JAIPAL HARAKLAL JAIN, SURENDRA HARAKLAL JAIN, BHERULAL BHURALAL PARMAR, BHARAT PRITHVIRAJ RANAWAT
  • Other registrations4 more →
  • Completed3 of 5
  • No longer live2 lapsed, de-registered or revoked

Key dates

this monthRegisteredOct 2018PromisedDec 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on24 Oct 2018
  • Promised completion30 Dec 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed114 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TRISHABH GREENS - WING BNA160000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 10 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

TRISHABH GREENS - WING B: 82% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 10 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes70%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed12

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots12
Closed/Covered12

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area609 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI1640.0
Proposed, not sanctioned1,640 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 3 AND 4, GROUND FLOOR, VIKRANT INDUSTRIAL ESTATE, GOVANDI, MUMBAI-400088

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSHRI BANSI HASSANAND WADHWA OF B H WADHWA & CO
EngineerSHRI RAAJESH K LADHAD OF STRUCTURAL CONCEPT DESIGN PVT LTD
Chartered AccountantSHRI PIYUSH C BOLIA OF PIYUSH C BOLIA & CO
PartnerRole in project
RISHABH ENTERPRISES-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 13 Oct 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Oct 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 1 Feb 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 1 Feb 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 4 Dec 2024

Documents filed114

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 114 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Architect Certificate Form 4 TGB - with OC copy.pdf10 Feb 2025
Architect’s Certificate on Completion of Project (Form 4)File: Architect Certificate Form 4 TGB.pdf4 Dec 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Letter dated 29-11-2024.pdf4 Dec 2024
Details of encumbrancesFile: No encumbrance letter 29-10-2024 - TGB.pdf30 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1 TGB Q2 2024-25.pdf30 Oct 2024
Certificates of CA (Form 3)File: CA Certificate Form 3 TGB Q2 2024-25.pdf30 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Form 2 TGB Q2 2024-25.pdf30 Oct 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold-Booked Inventory Wing B as on 30-09-2024.pdf30 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Trishabh Greens-Wing B FY 2023-24_.pdf12 Oct 2024
Details of encumbrancesFile: No encumbrance letter 17-07-2024 - TGB.pdf25 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1 TGB Q1 2024-25.pdf25 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Form 2 TGB Q1 2024-25.pdf25 Jul 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold-Booked Inventory Wing B as on 30-06-2024.pdf25 Jul 2024
Certificates of CA (Form 3)File: CA Certificate Form 3 TGB Q1 2024-25.pdf25 Jul 2024
Details of encumbrancesFile: No encumbrance letter 17-04-2024 TGB.pdf25 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1 TGB Q4 2023-24.pdf25 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Form 2 TGB Q4 2023-24.pdf25 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold-Booked Inventory Wing B as on 31-03-2024.pdf25 Apr 2024
CERSAI detailsFile: CERSAI_Search_Report_200304109600_For_Asset_Based_Search_17_04_2024_19_52_00_091 TGB.pdf25 Apr 2024
Certificates of CA (Form 3)File: CA Certificate Form 3 TGB Q4 2023-24.pdf25 Apr 2024
Details of encumbrancesFile: No encumbrance letter 21-01-2024.pdf22 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1 TGB Q3 2023-24.pdf22 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Form 2 TGB Q3 2023-24.pdf22 Jan 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold-Booked Inventory Wing B as on 31-12-2023.pdf22 Jan 2024
Certificates of CA (Form 3)File: CA Certificate Form 3 TGB Q3 2023-24.pdf22 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Trishabh Greens-Wing B FY 2022-23.pdf26 Oct 2023
Details of encumbrancesFile: No encumbrance letter 18-10-2023 TGB.pdf18 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1 TGB Q2 2023-24.pdf18 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Form 2 TGB Q2 2023-24.pdf18 Oct 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold-Booked Inventory Wing B as on 30-09-2023.pdf18 Oct 2023
Certificates of CA (Form 3)File: CA Certificate Form 3 TGB Q2 2023-24.pdf18 Oct 2023
Details of encumbrancesFile: No encumbrance letter 14-07-2023 TGB.pdf22 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1 TGB Q1 2023-24.pdf22 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Form 2 TGB Q1 2023-24.pdf22 Jul 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold-Booked Inventory Wing B as on 30-06-2023.pdf22 Jul 2023
Certificates of CA (Form 3)File: CA Certificate Form 3 TGB Q1 2023-24.pdf22 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Site Supervisor Certificate TGB dt 31-03-2020_.pdf25 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Site Supervisor Certificate TGB dt 30-09-2021_.pdf25 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Site Supervisor Certificate TGB dt 31-03-2022_.pdf25 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1 TGB Q4 2022-23.pdf24 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Form 2 TGB Q4 2022-23.pdf24 Apr 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold-Booked Inventory Wing B as on 31-03-2023.pdf24 Apr 2023
Certificates of CA (Form 3)File: CA Certificate Form 3 TGB Q4 2022-23.pdf24 Apr 2023
Details of encumbrancesFile: No encumbrance letter 26-01-2023 TGB.pdf2 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1 TGB Q3 2022-23.pdf2 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: TGB-09-Engineer Certificate Form 2 TGB Q3 2022-23.pdf2 Feb 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold-Booked Inventory Wing B as on 31-12-2022.pdf2 Feb 2023
Certificates of CA (Form 3)File: TGA-10-CA Certificate Form 3 TGB Q3 2022-23.pdf2 Feb 2023
Details of encumbrancesFile: No encumbrance letter 31-10-2022 TGB.pdf31 Oct 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1 TGB Q2 2022-23.pdf24 Oct 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: TGB-09-Engineer Certificate Form 2 TGB Q2 2022-23.pdf24 Oct 2022
Disclosure of sold/ booked inventoryFile: Disclosure of Sold-Booked Inventory Wing B as on 30-09-2022.pdf24 Oct 2022
Certificates of CA (Form 3)File: TGA-09-CA Certificate Form 3 TGB Q2 2022-23.pdf24 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Trishabh Greens-Wing B Dt 31-03-2022.pdf20 Oct 2022
Details of encumbrancesFile: No encumbrance letter 15-07-2022.pdf19 Jul 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1 TGB Q1 2022-23.pdf19 Jul 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: TGB-08-Engineer Certificate Form 2 TGB Q1 2022-23.pdf19 Jul 2022
Disclosure of sold/ booked inventoryFile: Disclosure of Sold-Booked Inventory Wing B as on 30-06-2022.pdf19 Jul 2022
Certificates of CA (Form 3)File: TGA-08-CA Certificate Form 3 TGB Q1 2022-23.pdf19 Jul 2022
Details of encumbrancesFile: No encumbrance letter 01-05-2022.pdf2 May 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate Form 1 Trishabh Greens Wing B.pdf2 May 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Form 2 Trishabh Greens - Wing B.pdf2 May 2022
CERSAI detailsFile: CERSAI_Search_Report_200236453797_For_Debtor_Based_Search_01_05_2022_22_16_45_610 Asset id2 May 2022
Disclosure of sold/ booked inventoryFile: Disclosure of Sold-Booked Inventory Wing B as on 31-03-2022.pdf2 May 2022
Certificates of CA (Form 3)File: CA Certificate Form 3 Trishabh Greens Wing B.pdf2 May 2022
Declaration about Commencement CertificateFile: Declaration about CC Wing B dt 05-02-2022.pdf5 Feb 2022
Building plan approvalFile: Approved Plans 30-01-2022 pg 1 to 3.pdf1 Feb 2022
Building plan approvalFile: Approved Plans 30-01-2022 pg 4 to 6.pdf1 Feb 2022
Details of encumbrancesFile: No encumbrance letter 01-02-2022.pdf1 Feb 2022
Building Plan Approval (IOD)File: Approved Plans 30-01-2022 pg 1 to 3.pdf1 Feb 2022
Building Plan Approval (IOD)File: Approved Plans 30-01-2022 pg 4 to 6.pdf1 Feb 2022
Commencement Certificates / NA Order for plotted developmentFile: Full CC dated 17-01-2022.pdf1 Feb 2022
Disclosure of sold/ booked inventoryFile: Disclosure of Sold-Booked Inventory Wing B as on 31-12-2021.pdf1 Feb 2022
CERSAI detailsFile: CERSAI_Search_Report_200229265966_For_Debtor_Based_Search_01_02_2022_15_45_09_295 Asset id1 Feb 2022
Certificates of CA (Form 3)File: CA Certificate Form 3 Trishabh Greens Wing B.pdf1 Feb 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate Form 1.pdf16 Jan 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Form 2.pdf16 Jan 2022
Details of encumbrancesFile: No encumbrance letter 12-10-2021.pdf15 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate Form 1 Trishabh Greens Wing B.pdf15 Oct 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Form 2 TGB as on 30-09-2021.pdf15 Oct 2021

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep TRISHABH GREENS - WING B on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near CHEMBUR NAKA, CHEMBUR EAST6,700+ in Mumbai Suburban

2 kmTRISHABH GREENS - WING BCompleted 153Lapsed / revoked 127Other 149Dot size: filed unitsN

Filed coordinates, straight-line distance. 429 registered projects within 2 km.

Builder: RISHABH ENTERPRISES

Rishabh Enterprises has 5 registrations on MahaRERA, including Arya Heights and TRISHABH GREENS - WING A. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if TRISHABH GREENS - WING B is delayed beyond 30 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of TRISHABH GREENS - WING B?

The registered promoter entity is RISHABH ENTERPRISES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in TRISHABH GREENS - WING B?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for TRISHABH GREENS - WING B?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at TRISHABH GREENS - WING B?

The professionals named in the filing: Architect: SHRI BANSI HASSANAND WADHWA OF B H WADHWA & CO; Engineer: SHRI RAAJESH K LADHAD OF STRUCTURAL CONCEPT DESIGN PVT LTD; Chartered Accountant: SHRI PIYUSH C BOLIA OF PIYUSH C BOLIA & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in TRISHABH GREENS - WING B?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About TRISHABH GREENS - WING B. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save TRISHABH GREENS - WING B to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.