Home / Browse projects / Thane, Maharashtra / TRINITY HEIGHTS

Registration lapsed No litigation declared Residential / Group Housing project

TRINITY HEIGHTS

By ANIL thakurdas kursija

RG-MH-81526 · RERA P51700008758 · Last updated on MahaRERA portal: 19 Feb 2022

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 41 months past the filed date
  • 13 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
May 2023Possession promised41 months past this date
5 of 11Construction stages donefurthest along: Podiums (if any), 50%
13Complaints at MahaRERAon this registration
Jump to the 34 documents Report an error

TRINITY HEIGHTS is a Residential / Group Housing project by ANIL thakurdas kursija in Thane, Maharashtra, registered with MahaRERA as P51700008758 on 19 Aug 2017. Possession was promised by 30 May 2023 and is now 41 months past that date. 13 complaints are on record with the regulator.

At a glance

Project

  • NameTRINITY HEIGHTS
  • TypeResidential / Group Housing
  • Location
    • Ghodbunder Road
    • Thane (M Corp.)
    • Thane
    • 400615
  • Pincode400615
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700008758
  • ReraGenie IDRG-MH-81526

Builder

  • NameANIL thakurdas kursija
  • Entity typeIndividual
  • Other registrations2 more →
  • No longer live3 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

41 months past promisethis monthRegisteredAug 2017PromisedMay 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on19 Aug 2017
  • Promised completion30 May 2023
  • Revised completionNone
  • Buildings1 building record
  • Documents filed34 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TRINITY HEIGHTSNA350000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 19 Feb 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 50%.

TRINITY HEIGHTS: 54% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)50%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises20%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks20%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 19 Feb 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes50%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes50%

Parking filed104

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots104
Closed/Covered78
Open Space26

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,630 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI5960.45
Proposed, not sanctioned3,930 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchRAMMURTI RD

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNAVRACHANA
EngineerEpicon Consultants Pvt Ltd
Chartered AccountantM. N. PARMAR & ASSOCIATES
PartnerRole in project
ANIL thakurdas kursija-

Complaints filed with MahaRERA13

Case no.ComplainantRespondentFiled
CC006000000000785Jairam ChandnaniMr. Anil Thakurdas Kursija26/09/2017
CC006000000044150Jairam ChandnaniANIL THAKURDAS KURSIJA18/04/2018
CC006000000000210Amol Namdeo BhangreAnil Thakurdas Kursija20/08/2017
CC006000000055202sudhir shettyAnil Kursija02/07/2018
CC006000000001823Jitendra Balu PetkarShree Balaji Associates09/11/2017
CC006000000055438Aruna Ashok LokhandeM/s. Balaji Associates, Throu' its Proprietor, Mr. Anil Thakudas kursija08/08/2018
CC006000000055453Mr. Rajesh SinghShree Balaji Associates23/07/2018
CC006000000055571Mr. Dinesh VoraShree Balaji Associates30/07/2018
CC006000000090165Rupchand Gyanchand LohanaAnil T. Kursija, Proprietor of Shri Balaji Associates16/07/2019
CC006000000090166Prakash Amar ShadijaAnil T Kursija, Proprietor of Shri Balaji Associates16/07/2019
CC006000000090170Hema Gurumukh ThakkerAnil T. Kursija, Proprietor of Shri Balaji Associates16/07/2019
CC006000000196341NIKETA SHETTYANIL T KURSIJA12/03/2021
CC006000000197635Trinity heights Cooperative housing Society LimitedShree Balaji Associates19/07/2021

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 20 Jan 2022

Documents filed34

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20220219 - Form I.pdf19 Feb 2022
PAN CardFile: ATK New Pan card.pdf20 Jan 2022
Declaration about Commencement CertificateFile: Trinity Heights - Commencement Certificate_11zon.pdf20 Jan 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: trinity heights declaration - occupation certificate.pdf20 Jan 2022
Status of ConveyanceFile: Trinity Heights - Status of Conveyance.pdf20 Jan 2022
Status of Formation of Legal Entity (Society/Co Op etc.)File: 03 - Society Registration Certificate.pdf23 Aug 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: STATUS - SOCIETY REGISTRATION.pdf23 Aug 2021
Building plan approvalFile: Plan1-.pdf31 Jul 2017
Layout approvalFile: Plan1-.pdf31 Jul 2017
Layout approvalFile: Plan4-.pdf31 Jul 2017
Building plan approvalFile: Plan3-.pdf31 Jul 2017
Building plan approvalFile: Plan4-.pdf31 Jul 2017
Building plan approvalFile: Plan2-.pdf31 Jul 2017
Layout approvalFile: Plan3-.pdf31 Jul 2017
Layout approvalFile: Plan2-.pdf31 Jul 2017
Copy of the legal title reportFile: Title Report 1.pdf31 Jul 2017
Copy of the legal title reportFile: Title Report 2.pdf31 Jul 2017
Copy of the legal title reportFile: Title Report 3.pdf31 Jul 2017
Details of encumbrancesFile: Declaration Encumbrances.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: Plan1-.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: Plan2-.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: Plan3-.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: Plan4-.pdf31 Jul 2017
Building Plan Approval (IOD)File: Plan1-.pdf31 Jul 2017
Building Plan Approval (IOD)File: Plan2-.pdf31 Jul 2017
Building Plan Approval (IOD)File: Plan3-.pdf31 Jul 2017
Building Plan Approval (IOD)File: Plan4-.pdf31 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: C C Certificate-.pdf31 Jul 2017
Declaration in FORM BFile: Form B-.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1-.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2-.pdf31 Jul 2017
Certificates of CA (Form 3)File: Declaration of Form 3.pdf31 Jul 2017
Proforma of Allotment letterFile: Declaration Allottment letter.pdf31 Jul 2017
Proforma of Allotment letterFile: Declaration of Agreement for sale.pdf31 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationStatusPromisedDelivered
BALAJI INFOTECHWAGLE ESTATECompletedJan 2010Jan 2010

How this compares with Thane

24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep TRINITY HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Thane (M Corp.)7,600+ in Thane

2 kmTRINITY HEIGHTSCompleted 76Lapsed / revoked 24Other 50Dot size: filed unitsN

Filed coordinates, straight-line distance. 150 registered projects within 2 km.

Builder: ANIL thakurdas kursija

ANIL thakurdas kursija has 3 registrations on MahaRERA, including TRINITY HEIGHTS and TRINITY OASIS. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that TRINITY HEIGHTS shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if TRINITY HEIGHTS is delayed beyond 30 May 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of TRINITY HEIGHTS?

The registered promoter entity is ANIL thakurdas kursija, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in TRINITY HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against TRINITY HEIGHTS?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for TRINITY HEIGHTS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at TRINITY HEIGHTS?

The professionals named in the filing: Architect: NAVRACHANA; Engineer: Epicon Consultants Pvt Ltd; Chartered Accountant: M. N. PARMAR & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in TRINITY HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About TRINITY HEIGHTS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save TRINITY HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.