Registration lapsed No litigation declared Residential / Group Housing project

TRIDHAATU ATHARVA VENKATESH SADAN

By TRIDHAATU VENKATESH SADAN DEVELOPERS LLP

RG-MH-24290 · RERA P51800004988 · Last updated on MahaRERA portal: 12 Mar 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 22 months past the filed date
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2024Possession promised22 months past this date
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 76 documents Report an error

TRIDHAATU ATHARVA VENKATESH SADAN is a Residential / Group Housing project by TRIDHAATU VENKATESH SADAN DEVELOPERS LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800004988 on 9 Aug 2017. Possession was promised by 27 Dec 2024 and is now 22 months past that date. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameTRIDHAATU ATHARVA VENKATESH SADAN
  • TypeResidential / Group Housing
  • Location
    • V N Purav Marg
    • Chembur
    • Kurla
    • Mumbai Suburban
    • 400071
  • Pincode400071
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800004988
  • ReraGenie IDRG-MH-24290

Builder

  • NameTRIDHAATU VENKATESH SADAN DEVELOPERS LLP
  • Entity typeOthers
  • Named personDHANANJAY SANDU

Key dates

22 months past promisethis monthRegisteredAug 2017First promiseDec 2023Revised toDec 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on9 Aug 2017
  • Promised completion27 Dec 2024
  • Revised completionRevised to 27 Dec 2024 (originally 30 Dec 2023)
  • Buildings1 building record
  • Documents filed76 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TRIDHAATU ATHARVA VENKATESH SADANNA100000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 12 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

TRIDHAATU ATHARVA VENKATESH SADAN: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 12 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes25%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed15

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots15
Closed/Covered15

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area965 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI2605.07
Proposed, not sanctioned2,605 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNear New Vijay Cinema 609 V N Purav Marg Sion Trombay Road Chembur East Mumbai 400071

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDEOLE BROS
EngineerMilind Kulkarni Consulting Engineers
PartnerRole in project
TRIDHAATU VENKATESH SADAN DEVELOPERS LLP-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800018565Dec 2023 → Dec 2024

Reason as filed by the promoterThe Project Building ‘Tridhaatu Atharva Venkatesh Sadan comprises of Ground + 8 floors. Work to date has been completed in accordance with the current approvals in place. The said Project is registered on the MahaRERA website under the Registration number P51800004988. At the time of registration, the project completion date was 31st March 2022. Due to the onset of the COVID-19 pandemic in March 2020 followed by the second wave in 2021 (“pandemic), the Government of India declared nation-wide lockdowns and the pandemic was acknowledged as a Force Majeure event. Consequentially the completion d

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 26 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Feb 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Dec 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed76

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
OtherFile: Reply - Atharva Vankatesh Sadan.pdf12 Mar 2025
Declaration in FORM BFile: Scanned-Form B- Affidavit cum Declaration-.pdf2 Jan 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory Venktesh Sadan 02012024.pdf2 Jan 2024
Commencement Certificates / NA Order for plotted developmentFile: VENKATESH CC REVALIDATED.pdf28 Dec 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 31-03-2022.pdf19 Dec 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 31-03-2023.pdf19 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Atharva-Venkatesh Sadan- Mar 23.pdf2 Dec 2023
Certificates of CA (Form 3)File: Form 3-Venkatesh Sadan-Mar 23.pdf2 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Atharva-Venkatesh Sadan- Mar 19.pdf30 Nov 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Atharva-Venkatesh Sadan- Mar 22.pdf30 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 2019 2020.pdf22 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 2020 2021.pdf22 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 2021 2022.pdf22 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 2022 2023.pdf22 Nov 2023
Certificates of CA (Form 3)File: Form 3-Venkatesh Sadan-Mar 19.pdf23 Oct 2023
Certificates of CA (Form 3)File: Form 3-Venkatesh Sadan-Mar 22.pdf23 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5- Venkatesh Sadan- FY 21-22.pdf23 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Venkateshsadan-form 5-signed 31032023.pdf11 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5-Tridhaatu Venkatesh Sadan-Atharva-FY 22-23.pdf5 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Tridhaatu Atharva FY 19 20.pdf2 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Tridhaatu Atharva FY 20 21.pdf2 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5_Tridhaatu Atharva.pdf2 May 2023
Declaration about Commencement CertificateFile: Fortmat D- Venkatesh Sadan ( Atharva).pdf22 Jun 2021
Commencement Certificates / NA Order for plotted developmentFile: Fortmat D- Venkatesh Sadan ( Atharva).pdf15 Jun 2021
OtherFile: Regi Unilateral Indenture Of Mortgage AUM Page 34 to 35.pdf31 Mar 2021
OtherFile: Regi Unilateral Indenture of Mortgage Page 1 to 7.pdf30 Mar 2021
OtherFile: Regi Unilateral Indenture of Mortgage Page 9 to 15.pdf30 Mar 2021
OtherFile: Regi Unilateral Indenture of Mortgage Page 17 to 21.pdf30 Mar 2021
OtherFile: Regi Unilateral Indenture of Mortgage Page 39 to 40.pdf30 Mar 2021
OtherFile: Regi Unilateral Indenture of Mortgage Page 41 to 43.pdf30 Mar 2021
OtherFile: Regi Unilateral Indenture of Mortgage Page 46 to 47.pdf30 Mar 2021
OtherFile: Regi Unilateral Indenture Of Mortgage AUM Page 1 to 5.pdf30 Mar 2021
OtherFile: Regi Unilateral Indenture Of Mortgage AUM Page 7 to 9.pdf30 Mar 2021
OtherFile: Regi Unilateral Indenture Of Mortgage AUM Page 27 to 28.pdf30 Mar 2021
OtherFile: Regi Unilateral Indenture Of Mortgage AUM Page 29 to 30.pdf30 Mar 2021
OtherFile: Regi Unilateral Indenture Of Mortgage AUM Page 31 to 33.pdf30 Mar 2021
Details of Restarting of Construction work post lockdownFile: Construction Status Post Lockdown-Tridhaatu Atharva Venkatesh Sadan.pdf2 Dec 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form-5 Venkatesh Sadan.pdf16 Dec 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: VENKATESH.pdf9 Dec 2019
Certificates of CA (Form 5)File: Form-5 Venkatesh.pdf27 Sep 2019
Certificates of CA (Form 5)File: Form-5 Venkatesh Sadan.pdf27 Sep 2019
Certificates of CA (Form 5)File: Form 5- ATHARVA-2017-18.pdf1 Oct 2018
Commencement Certificates / NA Order for plotted developmentFile: FURTHER CC UPTO 8TH FLOOR 210318.pdf11 Jul 2018
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Registration Certificate Venkatesh Sadan.pdf31 Mar 2018
Building plan approvalFile: Amended Letter.pdf22 Feb 2018
Building plan approvalFile: Amended Plans 2.pdf22 Feb 2018
Building plan approvalFile: Amended Plans 3.pdf22 Feb 2018
Building plan approvalFile: Amended Plans 1.pdf22 Feb 2018
Building Plan Approval (IOD)File: Amended Letter.pdf22 Feb 2018
Building Plan Approval (IOD)File: Amended Plans 1.pdf22 Feb 2018
Building Plan Approval (IOD)File: Amended Plans 2.pdf22 Feb 2018
Building Plan Approval (IOD)File: Amended Plans 3.pdf22 Feb 2018
Commencement Certificates / NA Order for plotted developmentFile: CC REVALIDATION.pdf22 Feb 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Atharva Venkatesh sadan.pdf22 Feb 2018
Building plan approvalFile: Amended Letter.pdf2 Sep 2017
Building plan approvalFile: Amended Plans-1-1.pdf2 Sep 2017
Building plan approvalFile: Amended Plans-2-2.pdf2 Sep 2017
Building plan approvalFile: Amended Plans-2-2.pdf2 Sep 2017
Building Plan Approval (IOD)File: Amended Letter.pdf2 Sep 2017
Building Plan Approval (IOD)File: Amended Plans-1-1.pdf2 Sep 2017
Building Plan Approval (IOD)File: Amended Plans-2-2.pdf2 Sep 2017
Building Plan Approval (IOD)File: Amended Plans-2-2.pdf2 Sep 2017
OtherFile: Disclosure Letter.PDF27 Jul 2017
Layout approvalFile: VENKATESH SADAN IOD PLAN.pdf26 Jul 2017
Building plan approvalFile: VENKATESH SADAN IOD.pdf26 Jul 2017
PAN CardFile: Venkatesh PAN Card.PDF26 Jul 2017
Copy of the legal title reportFile: Venkatesh Sadan-Title Certificate.pdf26 Jul 2017
Details of encumbrancesFile: Details of encumbrances.PDF26 Jul 2017
Copy of Layout Approval (in case of layout)File: VENKATESH SADAN IOD PLAN.pdf26 Jul 2017
Building Plan Approval (IOD)File: VENKATESH SADAN IOD.pdf26 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: VENKATESH SADAN CC UPTO 2ND FLOOR.pdf26 Jul 2017
Declaration in FORM BFile: Declaration Form B.PDF26 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- Venkatesh Sadan.pdf26 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate - Venkatesh sadan.pdf26 Jul 2017
Certificates of CA (Form 3)File: Form 3 - RERA - Venkatesh-compressed.pdf26 Jul 2017
Proforma of Allotment letterFile: Merged-AFS and Allotment Letter.pdf26 Jul 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 12 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep TRIDHAATU ATHARVA VENKATESH SADAN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Chembur6,700+ in Mumbai Suburban

2 kmTRIDHAATU ATHARVA VENKATCompleted 170Lapsed / revoked 138Other 171Dot size: filed unitsN

Filed coordinates, straight-line distance. 479 registered projects within 2 km.

Builder: TRIDHAATU VENKATESH SADAN DEVELOPERS LLP

TRIDHAATU VENKATESH SADAN DEVELOPERS LLP has 1 registration on MahaRERA, including TRIDHAATU ATHARVA VENKATESH SADAN. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that TRIDHAATU ATHARVA VENKATESH SADAN shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if TRIDHAATU ATHARVA VENKATESH SADAN is delayed beyond 27 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of TRIDHAATU ATHARVA VENKATESH SADAN?

The registered promoter entity is TRIDHAATU VENKATESH SADAN DEVELOPERS LLP, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in TRIDHAATU ATHARVA VENKATESH SADAN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for TRIDHAATU ATHARVA VENKATESH SADAN?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at TRIDHAATU ATHARVA VENKATESH SADAN?

The professionals named in the filing: Architect: DEOLE BROS; Engineer: Milind Kulkarni Consulting Engineers. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in TRIDHAATU ATHARVA VENKATESH SADAN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About TRIDHAATU ATHARVA VENKATESH SADAN. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save TRIDHAATU ATHARVA VENKATESH SADAN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.