Home / Browse projects / Pune, Maharashtra / TheCrown
TheCrown
RG-MH-94126 · RERA P52100034902 · Last updated on MahaRERA portal: 14 Jan 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 13 months past the filed date
- Completion date moved by 6 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
TheCrown is a Commercial project by Marimagnum Constructions in Pune, Maharashtra, registered with MahaRERA as P52100034902 on 28 Apr 2022. Possession was promised by 30 Sep 2025 and is now 13 months past that date. The completion date has moved by 6 months from the original filing. 9 of the 27 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.
At a glance
Project
- NameTheCrown
- TypeCommercial
- Location
- Undri
- Haveli
- Pune
- 411060
- Pincode411060
- RERA no.P52100034902
- ReraGenie IDRG-MH-94126
Builder
- NameMarimagnum Constructions
- Entity typePartnership
- PartnersASHOK KAUROMAL IDNANI, VIJAY MOHANDAS ATHWANI, Vishal Raju Athwani, Raju Mohandas Athwani
- Other registrations1 more →
- Completed1 of 2
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on28 Apr 2022
- Promised completion30 Sep 2025
- Revised completionRevised to 30 Sep 2025 (originally 31 Mar 2025)
- Buildings1 building record
- Documents filed119 files
Current status
Figures as on 14 Jan 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| The Crown | NA | 9 | 6 | 0 | 27 | 27 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 14 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 95%.
The Crown: 68% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 60% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 70% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 60% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 60% |
Progress on shared amenities15
As on 14 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 60% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 80% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed18
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| The Crown | NA | Rs 4.10 cr | Rs 4.04 cr |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Shirish Dasunkar and Associates |
| Engineer | DESIGN WERKZ ENGINEERING PVT.LTD |
| Engineer | Vasim Shaikh |
| Chartered Accountant | Hemant Dave and Associates |
| Partner | Role in project |
|---|---|
| Marimagnum Constructions | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterReseason for Delay to get completion before March 31.03.2025 is more time in involved in getting Fire NOC and Occupancy certificate from Pune Municipal authority hence we request you to give us extension for next 6 month i.e. 30.09.2025
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 11 Apr 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 1 Aug 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 11 Apr 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 11 Apr 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed119
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 119 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Rera From 1 - Sep 25.pdf | 14 Jan 2026 |
| Withdrawal Update Form 1File: Rera From 1 - Sep 25.pdf | 14 Jan 2026 |
| Withdrawal Update Form 2File: Rera Form 2 - Sep 25.pdf | 14 Jan 2026 |
| Withdrawal Update Form 2File: Rera Form 2 - Sep 25.pdf | 14 Jan 2026 |
| Withdrawal Update Form 3File: Rera Form 3-Sep 25.pdf | 14 Jan 2026 |
| Withdrawal Update Form 3File: Rera Form 3-Sep 25.pdf | 14 Jan 2026 |
| Withdrawal Update Form 1File: Rera From 1 - Sep 25.pdf | 17 Oct 2025 |
| Withdrawal Update Form 2File: Rera Form 2 - Sep 25.pdf | 17 Oct 2025 |
| Withdrawal Update Form 3File: Rera Form 3-Sep 25.pdf | 17 Oct 2025 |
| Details of encumbrances concerned to FinanceFile: Encumbrance.pdf | 23 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 23 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 for December 2024.pdf | 23 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 for March 2025.pdf | 23 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 September 2024.pdf | 23 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 June 2024.pdf | 23 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 March 2024.pdf | 23 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 December 2023.pdf | 23 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 September 2023.pdf | 23 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 June 2023.pdf | 23 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 March 2023.pdf | 23 May 2025 |
| Disclosure of sold/ booked inventoryFile: CIRCULAR 29.pdf | 23 May 2025 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: Format A.pdf | 23 May 2025 |
| Details of encumbrances concerned to LegalFile: Encumbrance.pdf | 23 May 2025 |
| Other - TechnicalFile: CPM.pdf | 23 May 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A - 22-23.pdf | 23 May 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - 23-24.pdf | 23 May 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 23-24.pdf | 23 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_FY 24-25_Q1.pdf | 27 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- FY 24-25_Q2.pdf | 27 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- FY 24-25_Q3.pdf | 27 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- FY 24-25- Q4.pdf | 27 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FROM 2 FY 24-25_Q4.pdf | 27 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 FY 24-25_Q3.pdf | 27 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 FY 24-25_Q2.pdf | 27 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 FY 24-25_Q1.pdf | 27 Apr 2025 |
| Other - TechnicalFile: Extension Application.pdf | 27 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 19 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Jan-March 25.pdf | 19 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng Form 2 - January to March 2025.pdf | 19 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Sales Details - March 2025.pdf | 19 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1 DECEMBER 2024.pdf | 11 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3 DECEMBER 2024.pdf | 11 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 DECEMBER 2024.pdf | 11 Apr 2025 |
| Declaration in FORM BFile: Form B.pdf | 15 Mar 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - December 24.pdf | 19 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 19 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: MM Eng - Form 2 December 2024.pdf | 19 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: Sales - December 24.pdf | 19 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5_The Crown_FY 23-24.pdf | 10 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1 September 2024.pdf | 19 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng Form 2 - September 2024.pdf | 19 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Sale Details - September 2024.pdf | 19 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Q2.pdf | 19 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1 September 2024.pdf | 19 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Q2.pdf | 19 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng Form 2 - September 2024.pdf | 19 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Sale Details - September 2024.pdf | 19 Nov 2024 |
| Layout approvalFile: Page No - 11_Updated.pdf | 1 Aug 2024 |
| Layout approvalFile: Plant Updated.pdf | 1 Aug 2024 |
| Copy of Layout Approval (in case of layout)File: Plant Updated.pdf | 1 Aug 2024 |
| Copy of Layout Approval (in case of layout)File: Page No - 11_Updated.pdf | 1 Aug 2024 |
| Declaration about Commencement CertificateFile: C C.pdf | 1 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Q1.pdf | 25 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form -2 - Q1.pdf | 25 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form- 2A - Q1.pdf | 25 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_The Crown Q1.pdf | 25 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Jan-March 24.pdf | 15 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Jan-March 24.pdf | 15 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: THE CROWN-SOLD BOOKING DECLERATION MAR24.pdf | 15 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_The Crown_Q4.PDF | 15 Apr 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 FY 2022-23.pdf | 2 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1- Q3 FY 23-24.pdf | 27 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Q3 FY 23-24.pdf | 27 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Sale Details-Q3 FY 23-24.pdf | 27 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Q3 FY 23-24.pdf | 27 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Q1.pdf | 3 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Q2 FY 22-23.pdf | 3 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Q3 FY 22-23.pdf | 3 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Q4 FY 22-23.pdf | 3 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Q1 FY 23-24.pdf | 3 Feb 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration, which the RERA portal never shows together
- All 119 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep TheCrown on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Undri13,700+ in Pune
THE SPECTRUM
SHRIRAM PROPERTIES LIMITED
GANGA MILLENNIA UNDRI BUILDING J,K,L,M AND N
GOEL GANGA INDIA PVT LTD
NYATI ESTEBAN II
NYATI REALTORS LLP
Lodha Pune NIBM Project
Lodha Developers Limited
KHUSH VISTA
Elated Housing LLP
The Atrium
Arhumashtika Life Spaces
Builder: Marimagnum Constructions
Marimagnum Constructions has 2 registrations on MahaRERA, including Mi Casa and TheCrown. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that TheCrown shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if TheCrown is delayed beyond 30 Sep 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of TheCrown?
The registered promoter entity is Marimagnum Constructions, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in TheCrown?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for TheCrown?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at TheCrown?
The professionals named in the filing: Architect: Shirish Dasunkar and Associates; Engineer: DESIGN WERKZ ENGINEERING PVT.LTD; Engineer: Vasim Shaikh; Chartered Accountant: Hemant Dave and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in TheCrown?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback