Home / Browse projects / Pune, Maharashtra / THE UNICORN BUILDING C WING C1 & C2

Registered Litigation declared Residential / Group Housing project

THE UNICORN BUILDING C WING C1 & C2

By DOLPHIN BUILDCON

RG-MH-62725 · RERA P52100052724 · Last updated on MahaRERA portal: 18 May 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 3 cases
  • Completion date moved by 12 months
  • 1 extension taken
  • Rs 35.00 crore secured on the land, in favour of Aditya Birla Capital Limited

Clear

  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 12 months from the original
2 of 22Construction stages doneacross 2 buildings; furthest along: Basement (if any), 0%
246 of 260Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 180 documents Report an error

THE UNICORN BUILDING C WING C1 & C2 is a Residential / Group Housing project by DOLPHIN BUILDCON in Pune, Maharashtra, registered with MahaRERA as P52100052724 on 22 Sep 2023. Possession is promised by 30 Dec 2027. The completion date has moved by 12 months from the original filing. 14 of the 260 units on this registration are recorded sold or booked, and 2 of 22 construction stages are filed complete.

At a glance

Project

  • NameTHE UNICORN BUILDING C WING C1 & C2
  • TypeResidential / Group Housing
  • Location
    • OPP NIVRUTTI LAWNS AUNDH RAVET BRT ROAD RAVET
    • RAVET
    • Haveli
    • Pune
    • 412101
  • Pincode412101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100052724
  • ReraGenie IDRG-MH-62725

Builder

  • NameDOLPHIN BUILDCON
  • Entity typePartnership
  • GSTIN27AAJFD2552P2ZZ
  • PartnersMUKESH KUMAR SAH, PREMPRAKASH RAMESHWARDAS AGARWAL, RAMESH KESARIMAL SONIGARA, SACHIN KIRANRAJ SONIGARA, ASHISH ASHOK SIROYA, SAGAR RAJKUMAR AGARWAL, SHREE NANDKUMAR SANE, DINESH SATYANARAYAN GUPTA, DILIP SATYANARAYAN GUPTA
  • Other registrations3 more →
  • Completed1 of 4
  • Declared earlier projects2 →

Key dates

this monthRegisteredSep 2023First promiseDec 2026Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on22 Sep 2023
  • Promised completion30 Dec 2027
  • Revised completionRevised to 30 Dec 2027 (originally 31 Dec 2026)
  • Buildings2 building records
  • Documents filed180 files

Current status

5%14 of 260 units booked
2.2%Work done, per cost certificate

Figures as on 18 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
THE UNICORN BUILDING C WING C1 & C2WING C124191300130
THE UNICORN BUILDING C WING C1 & C2WING C224191300130

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 18 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Basement (if any), at 0%.

THE UNICORN BUILDING C WING C1 & C2 · wing WING C19%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
THE UNICORN BUILDING C WING C1 & C2 · wing WING C29%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 18 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYesNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYesNot applicable
Community BuildingsNo0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNo0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNo0%
Open ParkingYesNot applicable

Parking filed454

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots454
Stilt / Ground194
Basement260
BuildingStilt / GroundBasementTotal
THE UNICORN BUILDING C WING C1 & C2 WING C197130227
THE UNICORN BUILDING C WING C1 & C2 WING C297130227

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area16,000 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofAditya Birla Capital Limited
Secured amountRs 35.00 crore
CERSAI search filedYes
Declared on9 May 2026

Approvals and building plan

Sanctioning authorityPIMPRI CHINCHWAD MUNICIPAL CORPORATION
Permissible FSI26251.38
Proposed, not sanctioned26,251 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 1 GROUND FLOOR PRIME SQUARE S NO 125/5 ANUDH ANNEXE
Estimated costRs 80.62 cr
Cost incurredRs 1.77 cr
Work done2.2%
BuildingWingEstimatedIncurred
THE UNICORN BUILDING C WING C1 & C2WING C1Rs 38.31 crRs 88.69 lakh
THE UNICORN BUILDING C WING C1 & C2WING C2Rs 38.31 crRs 88.69 lakh
-NARs 4.00 cr-

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectCUBIX ARCHITECTS ASSOCIATES
EngineerSonali Amrutkar
Chartered AccountantNAVDEEP JINDAL & ASSOCIATES
Chartered AccountantAkshay Lad
Chartered AccountantB S Ghadage
PartnerRole in project
DOLPHIN BUILDCON-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100019346Dec 2026 → Dec 2027

Reason as filed by the promoterWe had planned to complete our project before 31/12/2026. However, we are estimating at least 1 more year for the completion, due to non-availability of labour and other resources. Hence our completion date for the project “CASA GRANDE BUILDING C, WING C1” will get extended to 30/12/2027. Also, we would like to bring to your notice that we have not sold any units till now. Hence, having no sold units, we do not require any consent from the allottees. Therefore, we request your approval under 7(3).

Litigation declared3

CaseCourtStatus
164/2015/2015DISTRICT JUDGE PUNENOTICE UNREADY
474/2016/2016C J S D PUNEEXH FIVE PARTY ALLOWED AGAINST SILVER STAR GROUP
RCS 0000089/2010C J J D AND JMFC PIMPRI CHINCHWADISSUES

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 7 Jul 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 11 Feb 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 11 Feb 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 5 Sep 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Dec 2027

Documents filed180

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 180 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Form 2A DOLPHIN 31-03-2026.pdf18 May 2026
Form 5 (FY 2024-2025)File: Form 5 CA The Unicorn FY 2024-25.pdf18 May 2026
Form 5 (FY 2025-2026)File: Form 5 CA The Unicorn FY 2025-26.pdf18 May 2026
Withdrawal Update Form 1File: Form 1 Architect Certificate - March 2026.pdf28 Apr 2026
Withdrawal Update Form 2File: Form 2 Engineer Certificate - March 2026.pdf28 Apr 2026
Withdrawal Update Form 3File: Form 3 CA Certificate March 2026.pdf28 Apr 2026
Layout approvalFile: Layout Approved final.pdf11 Feb 2026
Building plan approvalFile: Building Plan 1.pdf11 Feb 2026
Building plan approvalFile: Building Plan 2.pdf11 Feb 2026
Building plan approvalFile: Building Plan 3.pdf11 Feb 2026
Building plan approvalFile: Building Plan 4.pdf11 Feb 2026
Building plan approvalFile: Building Plan 5.pdf11 Feb 2026
Building plan approvalFile: Building Plan 6.pdf11 Feb 2026
Building plan approvalFile: Building Plan 7.pdf11 Feb 2026
Building plan approvalFile: Building Plan 8.pdf11 Feb 2026
Building plan approvalFile: Building Plan 9.pdf11 Feb 2026
Building plan approvalFile: Building Plan 10.pdf11 Feb 2026
Building plan approvalFile: Building Plan 11.pdf11 Feb 2026
Building plan approvalFile: Building Plan 12.pdf11 Feb 2026
Building plan approvalFile: Building Plan 13.pdf11 Feb 2026
Building plan approvalFile: Building Plan 14.pdf11 Feb 2026
Building plan approvalFile: Building Plan 15.pdf11 Feb 2026
Building plan approvalFile: Building Plan 16.pdf11 Feb 2026
Withdrawal Update Form 1File: Form 1 Architect Certificate - December 2025.pdf29 Jan 2026
Withdrawal Update Form 1File: Form 1 Architect Certificate - December 2025.pdf29 Jan 2026
Withdrawal Update Form 2File: Form 2 Engineer Certificate - December 2025.pdf29 Jan 2026
Withdrawal Update Form 2File: Form 2 Engineer Certificate - December 2025.pdf29 Jan 2026
Withdrawal Update Form 3File: Form 3 CA Certiciate - December 2025 - Final.pdf29 Jan 2026
Withdrawal Update Form 3File: Form 3 CA Certificate - Signed.pdf29 Jan 2026
Layout approvalFile: Layout Approved.pdf23 Dec 2025
Building plan approvalFile: Building Plan 1.pdf23 Dec 2025
Building plan approvalFile: Building Plan 2.pdf23 Dec 2025
Building plan approvalFile: Building Plan 3.pdf23 Dec 2025
Building plan approvalFile: Building Plan 4.pdf23 Dec 2025
Building plan approvalFile: Building Plan 5.pdf23 Dec 2025
Building plan approvalFile: Building Plan 6.pdf23 Dec 2025
Building plan approvalFile: Building Plan 7.pdf23 Dec 2025
Building plan approvalFile: Building Plan 8.pdf23 Dec 2025
Building plan approvalFile: Building Plan 9.pdf23 Dec 2025
Building plan approvalFile: Building Plan 10.pdf23 Dec 2025
Building plan approvalFile: Building Plan 11.pdf23 Dec 2025
Building plan approvalFile: Building Plan 12.pdf23 Dec 2025
Building plan approvalFile: Building Plan 13.pdf23 Dec 2025
Building plan approvalFile: Building Plan 14.pdf23 Dec 2025
Building plan approvalFile: Building Plan 15.pdf23 Dec 2025
Building plan approvalFile: Building Plan 16.pdf23 Dec 2025
Withdrawal Update Form 1File: Form 1 Architect Certificate September 2025.pdf27 Nov 2025
Withdrawal Update Form 1File: Form 1 Architect Certificate September 2025.pdf27 Nov 2025
Withdrawal Update Form 2File: Form 2 Engineer Certificate September 2025.pdf27 Nov 2025
Withdrawal Update Form 2File: Form 2 Engineer Certificate September 2025.pdf27 Nov 2025
Withdrawal Update Form 3File: Form 3 CA Certificate - Sept 2025.pdf27 Nov 2025
Withdrawal Update Form 3File: Dolphin Unicorn form 3.pdf27 Nov 2025
Withdrawal Update Form 1File: Form 1 Architech Certificate June 2025.PDF16 Aug 2025
Withdrawal Update Form 2File: Form 2 Engineer Certificate June 2025.PDF16 Aug 2025
Withdrawal Update Form 3File: Form 3 CA Certificate June 2025 - Final.pdf16 Aug 2025
Form 2A (FY 2024-2025)File: FORM 2A 31-03-2025.PDF4 Aug 2025
Form 2A (FY 2023-2024)File: FORM 2A 31-03-2024.PDF4 Aug 2025
Withdrawal Update Form 1File: Form 1 Architech Certificate June 2025.PDF2 Aug 2025
Withdrawal Update Form 1File: Form 1 Architech Certificate June 2025.PDF2 Aug 2025
Withdrawal Update Form 2File: Form 2 Engineer Certificate June 2025.PDF2 Aug 2025
Withdrawal Update Form 2File: Form 2 Engineer Certificate June 2025.PDF2 Aug 2025
Withdrawal Update Form 3File: Form 3 CA Certificate June 2025.PDF2 Aug 2025
Withdrawal Update Form 3File: Form 3 CA Certificate June 2025.PDF2 Aug 2025
Form 5 (FY 2023-2024)File: Form 5 - FY 2023-24.pdf1 Aug 2025
Layout approvalFile: Layout Approved.pdf30 Jul 2025
Building plan approvalFile: Building Plan 1.pdf30 Jul 2025
Building plan approvalFile: Building Plan 2.pdf30 Jul 2025
Building plan approvalFile: Building Plan 3.pdf30 Jul 2025
Building plan approvalFile: Building Plan 4.pdf30 Jul 2025
Building plan approvalFile: Building Plan 5.pdf30 Jul 2025
Building plan approvalFile: Building Plan 6.pdf30 Jul 2025
Building plan approvalFile: Building Plan 7.pdf30 Jul 2025
Building plan approvalFile: Building Plan 8.pdf30 Jul 2025
Building plan approvalFile: Building Plan 9.pdf30 Jul 2025
Building plan approvalFile: Building Plan 10.pdf30 Jul 2025
Building plan approvalFile: Building Plan 11.pdf30 Jul 2025
Building plan approvalFile: Building Plan 12.pdf30 Jul 2025
Building plan approvalFile: Building Plan 13.pdf30 Jul 2025
Building plan approvalFile: Building Plan 14.pdf30 Jul 2025
Building plan approvalFile: Building Plan 15.pdf30 Jul 2025

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
CASA GRANDE B WINGSR NO 89 OPP NIVRUTTI LAWNS AUNDH RAVET BRT ROAD RAVET PUNE 412101126CompletedJun 2022Jun 2022

How this compares with Pune

5%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 12 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep THE UNICORN BUILDING C WING C1 & C2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near RAVET13,700+ in Pune

2 kmTHE UNICORN BUILDING C WCompleted 115Lapsed / revoked 54Other 119Dot size: filed unitsN

Filed coordinates, straight-line distance. 288 registered projects within 2 km.

Builder: DOLPHIN BUILDCON

DOLPHIN BUILDCON has 4 registrations on MahaRERA, including CASA GRANDE B WING and THE UNICORN BUILDING C WING C1 & C2. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if THE UNICORN BUILDING C WING C1 & C2 is delayed beyond 30 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of THE UNICORN BUILDING C WING C1 & C2?

The registered promoter entity is DOLPHIN BUILDCON, a partnership as per the filing. Its GSTIN 27AAJFD2552P2ZZ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in THE UNICORN BUILDING C WING C1 & C2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for THE UNICORN BUILDING C WING C1 & C2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at THE UNICORN BUILDING C WING C1 & C2?

The professionals named in the filing: Architect: CUBIX ARCHITECTS ASSOCIATES; Engineer: Sonali Amrutkar; Chartered Accountant: NAVDEEP JINDAL & ASSOCIATES; Chartered Accountant: Akshay Lad; Chartered Accountant: B S Ghadage. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in THE UNICORN BUILDING C WING C1 & C2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About THE UNICORN BUILDING C WING C1 & C2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save THE UNICORN BUILDING C WING C1 & C2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.