Home / Browse projects / Palghar, Maharashtra / THE SCENIC RESIDENCY PHASE I

Registration lapsed No litigation declared Residential / Group Housing project

THE SCENIC RESIDENCY PHASE I

By Virendra Ramesh Mehta

RG-MH-89430 · RERA P99000005001 · Last updated on MahaRERA portal: 11 Mar 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date
  • 3 complaints at MahaRERA
  • Completion date moved by 75 months
  • 3 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
8 of 22Construction stages doneacross 2 buildings; furthest along: Internal walls, 60%
0 of 40Units unsoldnot recorded sold or booked
3Complaints at MahaRERAon this registration
Jump to the 97 documents Report an error

THE SCENIC RESIDENCY PHASE I is a Residential / Group Housing project by Virendra Ramesh Mehta in Palghar, Maharashtra, registered with MahaRERA as P99000005001 on 9 Aug 2017. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 75 months from the original filing. 40 of the 40 units on this registration are recorded sold or booked, and 8 of 22 construction stages are filed complete. 3 complaints are on record with the regulator.

At a glance

Project

  • NameTHE SCENIC RESIDENCY PHASE I
  • TypeResidential / Group Housing
  • Location
    • CTS NO 2
    • MOR
    • VASAI
    • Mori
    • Vasai
    • Palghar
    • 401208
  • Pincode401208
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000005001
  • ReraGenie IDRG-MH-89430

Builder

  • NameVirendra Ramesh Mehta
  • Entity typeIndividual

Key dates

4 months past promisethis monthRegisteredAug 2017First promiseMar 2020Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on9 Aug 2017
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 31 Mar 2020)
  • Buildings2 building records
  • Documents filed97 files

Current status

100%40 of 40 units booked

Figures as on 11 Mar 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ANA3320020
BNA3320020

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 11 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 60%.

A46%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B46%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 11 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes80%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,100 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityDISTRICT COLLECTOR
Permissible FSI1768.03
Proposed, not sanctioned1,060 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHER E PANJAB ANDHERI EAST MUMBAI 400 093

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAjay Wade & Associates
EngineerPARESH UNNARKAR
Chartered AccountantMANISH B RANPARIYA & CO
PartnerRole in project
virendra-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000005972Mar 2020 → Mar 2021

Reason as filed by the promoter• The approvals for additional proposed FSI was not granted by Competent Authority in time and due to this delay we were unable to carry out the work any further. • The construction of structure is complete for the portion of project earlier approved and registered with MahaRERA. • Brick work and plastering for the completed structure is in progress. • The construction of building could not be carried out completely due to sluggish sales in the project. • The construction work for the proposed building is in progress and we are arranging for funds from other sources. • The promoter humbly requ

EXT99000012051Mar 2020 → Mar 2023

Reason as filed by the promoterDUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 30-03-2023

EXT99000025382Mar 2020 → Jun 2026

Reason as filed by the promoterextension is requested bcoz. we have applied for revised cc for additional FSi , and we need some more time to complete the project to the fullest.

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC006000000251808THE CONSTRUCTIONS COMR SAFARUDDIN KHAN09/07/2022
CC006000000302965अक्षय पांडुरंग मनवेM/S. THE CONSTRUCTIONS CO.17/10/2022
CC006000000292514THE CONSTRUCTIONS COPRAKASH BANMARE03/09/2022

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 26 Feb 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 26 Feb 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Feb 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed97

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 97 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Other - TechnicalFile: P99000005001_FileName_3.pdf11 Mar 2025
Declaration in FORM BFile: tcc form b affidavit.pdf3 Mar 2025
Layout approvalFile: LAYOU.pdf26 Feb 2025
Building plan approvalFile: BLDG.pdf26 Feb 2025
Copy of Layout Approval (in case of layout)File: LAYOU.pdf26 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH.pdf26 Feb 2025
Certificates of CA (Form 3)File: FROM 3.pdf26 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG CER.pdf26 Feb 2025
Commencement Certificates / NA Order for plotted developmentFile: REVISED CC.pdf26 Feb 2025
Building Plan Approval (IOD)File: BLDG.pdf26 Feb 2025
Disclosure of sold/ booked inventoryFile: sold unsold.pdf26 Feb 2025
Declaration about Commencement CertificateFile: CC DECLARATION.pdf26 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate dated .pdf9 Jan 2025
Certificates of CA (Form 3)File: CA Certificate dated .pdf9 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Structural engeenier certificate dated .pdf9 Jan 2025
CERSAI detailsFile: CERSAI_Search_Report_200334912049_For_Asset_Based_Search_09_01_2025_17_36_41_613.pdf9 Jan 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: BANK DECL PROMOTER with TCC stamp sign.pdf30 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A year 2021-2022 with TCC stamp sign.pdf30 Dec 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: DECLARATION PROP with TCC stmap sign.pdf30 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A year 2022-2023 with TCC stamp sign.pdf30 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A year 2023-2024 with TCC stamp sign.pdf30 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5 year 2023-2024 with stamp sign.pdf30 Dec 2024
Declaration in FORM BFile: affidavit notary tcc.pdf4 Dec 2024
Certificates of CA (Form 3)File: FORM 3 3132023.pdf4 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engin cert form 2.pdf4 Dec 2024
Disclosure of sold/ booked inventoryFile: sold unsold tcc.pdf4 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 3132023.pdf4 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GetUserDocumentFileContent.pdf6 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 15 Certificates of Architect (Form 1)(Mandatory for only ongoing project).pdf6 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Scan.pdf29 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Scan.pdf29 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form 5 21-22 tcc.pdf27 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect .pdf9 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 (2).pdf9 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: DocScanner 9 Feb 2023 18-29.pdf9 Feb 2023
Certificates of CA (Form 5)File: AUDIT.pdf9 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: AUDIT.pdf9 Feb 2023
Disclosure of sold/ booked inventoryFile: disclosure of inventory.pdf15 Jun 2022
Declaration about Commencement CertificateFile: CC Covering Letter.pdf14 Jun 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer form 2 sep 2021.pdf14 Jun 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer form 2 dec 2021.pdf14 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: engineer form 2A 19-20.pdf14 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: engineer form 2A 20-21.pdf14 Jun 2022
CERSAI detailsFile: CERSAI DECLARATION.pdf14 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 TCC 19-20.pdf9 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Annual Report March 21.pdf31 May 2022
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf30 May 2022
Certificates of CA (Form 3)File: CA FORM 3 MARCH 2021.pdf27 May 2022
Certificates of CA (Form 3)File: CA FORM 3 SEPTERMBER 2021.pdf27 May 2022
Certificates of CA (Form 3)File: CA FORM 3 DECEMBER 2021.pdf27 May 2022
Certificates of CA (Form 3)File: CA FORM 3 MARCH 2022.pdf27 May 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT FORM 1 MARCH 2021.pdf25 May 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT FORM 1 JUNE 2021.pdf25 May 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT FORM 1 MARCH 2022.pdf25 May 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER FORM 2.pdf25 May 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 202003_Ar-1.pdf28 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 202009_Ar-1.pdf28 Oct 2021
Certificates of CA (Form 3)File: 202003_CA-1.pdf28 Oct 2021
Certificates of CA (Form 3)File: 202009_CA-1.pdf28 Oct 2021
Certificates of CA (Form 3)File: CA_202001.pdf21 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form-5_201903.pdf21 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ar_201909.pdf10 Mar 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ar_202001.pdf10 Mar 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Er_201903.pdf10 Mar 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Er_201909.pdf10 Mar 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Er_202001.pdf10 Mar 2020
Certificates of CA (Form 3)File: CA_201903.pdf10 Mar 2020
Certificates of CA (Form 3)File: CA_201909.pdf10 Mar 2020
Certificates of CA (Form 5)File: Form-5_201903.pdf10 Mar 2020
Certificates of CA (Form 5)File: TCC_Form5_17-18.pdf14 Nov 2018
Proforma of Allotment letterFile: TCC_Draft Agreement-1.pdf3 Mar 2018
Declaration in FORM BFile: FROM B.pdf8 Aug 2017
Layout approvalFile: LAYOUT PLAN.pdf29 Jul 2017
Building plan approvalFile: 2-4 na order 2.pdf29 Jul 2017
PAN CardFile: pan card.pdf29 Jul 2017
Copy of the legal title reportFile: title page no 1.pdf29 Jul 2017
Copy of the legal title reportFile: title page no 2.pdf29 Jul 2017
Copy of the legal title reportFile: title page no 3.pdf29 Jul 2017
Details of encumbrancesFile: title page no 1.pdf29 Jul 2017
Details of encumbrancesFile: title page no 2.pdf29 Jul 2017

How this compares with Palghar

100%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one moved by 75 months
26%of Palghar registrations have lapsed or been cancelledthis one is among them

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep THE SCENIC RESIDENCY PHASE I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MOR, VASAI3,200+ in Palghar

2 kmTHE SCENIC RESIDENCY PHAOther 3Dot size: filed unitsN

Filed coordinates, straight-line distance. 3 registered projects within 2 km.

Builder: Virendra Ramesh Mehta

Virendra Ramesh Mehta has 1 registration on MahaRERA, including THE SCENIC RESIDENCY PHASE I. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What does it mean that THE SCENIC RESIDENCY PHASE I shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if THE SCENIC RESIDENCY PHASE I is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of THE SCENIC RESIDENCY PHASE I?

The registered promoter entity is Virendra Ramesh Mehta, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in THE SCENIC RESIDENCY PHASE I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against THE SCENIC RESIDENCY PHASE I?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for THE SCENIC RESIDENCY PHASE I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at THE SCENIC RESIDENCY PHASE I?

The professionals named in the filing: Architect: Ajay Wade & Associates; Engineer: PARESH UNNARKAR; Chartered Accountant: MANISH B RANPARIYA & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in THE SCENIC RESIDENCY PHASE I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About THE SCENIC RESIDENCY PHASE I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save THE SCENIC RESIDENCY PHASE I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.