Home / Browse projects / Mumbai Suburban, Maharashtra / THE SANCTUARY - TOWER 5

Registered Litigation declared Residential / Group Housing project

THE SANCTUARY - TOWER 5

By Runwal Construction Private Limited

RG-MH-29570 · RERA P51800029440 · Last updated on MahaRERA portal: 17 Jul 2026

Source: official MahaRERA filing

Red flags

  • Possession 1 months past the filed date
  • Litigation declared, 6 cases
  • 1 complaint at MahaRERA
  • Completion date moved by 6 months
  • 1 extension taken

Clear

  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Sep 2026Possession promised1 month past this date
5 of 11Construction stages donefurthest along: Slabs of Super Structure, 96%
36 of 264Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 149 documents Report an error

THE SANCTUARY - TOWER 5 is a Residential / Group Housing project by Runwal Construction Private Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800029440 on 29 May 2021. Possession was promised by 30 Sep 2026 and is now 1 months past that date. The completion date has moved by 6 months from the original filing. 228 of the 264 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameTHE SANCTUARY - TOWER 5
  • TypeResidential / Group Housing
  • Location
    • LBS Road
    • Mulund
    • Kurla
    • Mumbai Suburban
    • 400080
  • Pincode400080
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800029440
  • ReraGenie IDRG-MH-29570

Builder

  • NameRunwal Construction Private Limited
  • Entity typeCompany
  • CINU41001MH2023PTC406024
  • GSTIN27AAMCR8126K1ZT
  • DirectorsSunil Satvilkar, Sujata Rao
  • Other registrations9 more →
  • Completed3 of 10
  • Past their filed date2
  • Declared earlier projects12 →

Key dates

1 months past promisethis monthRegisteredMay 2021First promiseMar 2026Revised toSep 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on29 May 2021
  • Promised completion30 Sep 2026
  • Revised completionRevised to 30 Sep 2026 (originally 31 Mar 2026)
  • Buildings1 building record
  • Documents filed149 files

Current status

86%228 of 264 units booked

Figures as on 17 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ASPENNA52462640264

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 17 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 96%.

ASPEN: 65% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure96%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises61%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks61%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 17 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes25%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes30%
Storm Water DrainsYes15%
Landscaping & Tree PlantingYes5%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes10%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes20%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed374

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots374
Closed/Covered374

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area742 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on29 Jul 2026

Approvals and building plan

Sanctioning authorityBRIHANMUMBAI MUNICIPAL CORPORATION
Permissible FSI22200.0
Proposed, not sanctioned14,320 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGround Floor Jehangir Bldg M G Road Fort Mumbai 400 001

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNinad Dinkar Mhaskar
ArchitectPallavi Matkari
EngineerSanjay Singh
Chartered AccountantS P Gunjal & Associates
Chartered AccountantM B Agrawal & Co
Chartered AccountantS M GUPTA CO
PartnerRole in project
Runwal Construction Private Limited-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA31072621955Mar 2026 → Sep 2026

Reason as filed by the promoterWe, Runwal Construction Private Limited, the Promoter of the Project namely “The Sanctuary- Tower 5” bearing Registration No. P51800029440, are applying for extension of the Project Completion Date. The current project completion date is 30th March 2026 and we are applying for 6 months extension for completion of the Project i.e. till 30th September 2026. we have received the Part OC bearing No. CHE/ES/5937/T/337(NEW)/OCC/1/NEW of 14th October 2025 upto 45th floor except Fitness Centre. We have also handed over the possession of units to the allottees in the said Project. We further say that w

Litigation declared6

CaseCourtStatus
962/2014High Court of BombayPending
3441/2014Bombay City Civil CourtPending
299/2015Bombay City Civil CourtWithdrawn
2319/2013Bombay City Civil CourtPending
2784/2016Bombay City Civil CourtDisposed of
1399/2017Bombay City Civil CourtWithdrawn

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12605555SAVICHAN THOMASRunwal Construction Private Limited28/08/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 May 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 Mar 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 Mar 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Dec 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed149

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 149 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: From 2A.pdf17 Jul 2026
Form 1File: Form 1.pdf29 Apr 2026
Form 2File: Form 2.pdf29 Apr 2026
Form 3File: Form 3.pdf29 Apr 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory.pdf29 Apr 2026
Form 1File: Form 1.pdf28 Jan 2026
Form 2File: Form 2.pdf28 Jan 2026
Form 3File: Form 3.pdf28 Jan 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory.pdf28 Jan 2026
Form 2A (FY 2024-2025)File: Form 2A.pdf12 Dec 2025
Form 5 (FY 2024-2025)File: Form 5.pdf9 Dec 2025
Form 1File: Form 1.pdf28 Oct 2025
Form 2File: Form 2.pdf28 Oct 2025
Form 3File: Form 3.pdf28 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory.pdf28 Oct 2025
Form 1File: Form 1.pdf30 Jul 2025
Form 2File: Form 2.pdf30 Jul 2025
Form 3File: Form 3 June 2025.pdf30 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory.pdf30 Jul 2025
Disclosure of sold/ booked inventoryFile: Sold unsold Inventory.pdf3 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf2 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf19 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf18 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Dec 2024 Tower 5.pdf27 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dec 24.pdf27 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Dec 2024.pdf27 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Dec 2024.pdf20 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf12 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Tower 5.pdf6 Dec 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B Tower 5.pdf3 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Sep 2024.pdf25 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Sep 2024.pdf22 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sep 2024.pdf22 Oct 2024
Details of encumbrancesFile: Encumbrance Certificate The Sanctuary Tower 5.pdf21 Oct 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory Sep 2024.pdf21 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: From 3 June 2024.pdf12 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: From 1 June 2024.pdf22 Jul 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory June 2024.pdf22 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 June 2024.pdf19 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 March 2024.pdf29 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: From 1 March 2024.pdf22 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 March 2024.pdf22 Apr 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory March 2024.pdf22 Apr 2024
Declaration about Commencement CertificateFile: Declaration about CC-Form D.pdf6 Mar 2024
Proforma of Agreement for saleFile: 1 AFS Tower 5 The Sancturay Revised with Full CC dtd 05 02 2024 Pgs 1 to 96.pdf17 Feb 2024
Proforma of Agreement for saleFile: 2 AFS Tower 5 The Sancturay Revised with Full CC dtd 05 02 2024 Pgs 97 to 112.pdf17 Feb 2024
Proforma of Agreement for saleFile: 3 AFS Tower 5 The Sancturay Revised with Full CC dtd 05 02 2024 Pgs 113 to 138.pdf17 Feb 2024
Proforma of Agreement for saleFile: 4 AFS Tower 5 The Sancturay Revised with Full CC dtd 05 02 2024 139 to 152.pdf17 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: The Sanctuary Tower 5 Form 3.pdf24 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf23 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf19 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A.pdf19 Jan 2024
Disclosure of sold/ booked inventoryFile: sold Unsold Inventory compressed.pdf19 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf17 Jan 2024
Commencement Certificates / NA Order for plotted developmentFile: 08 12 2023 5937 CC certificate Bldg 5.pdf13 Dec 2023
Commencement Certificates / NA Order for plotted developmentFile: 11 10 2023 5937 CC certificate Bldg 5.pdf13 Dec 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold Tower 5 30 09 2023.pdf26 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Tower 5 30 9 2023.pdf23 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Tower 5 30 09 2023.pdf23 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sanctuary Tower 5 30 Sept 2023.pdf20 Oct 2023
Home Buyer /Allottee Grievance Redressal CellFile: Declaration The Sanctuary Tower 5.pdf20 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 for Sanctuary Tower 5.pdf17 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Eng Certificate Sanctuary Tower 5.pdf20 Jul 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold list of Sanctuary Tower 5 as on 30 June 2023.pdf20 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sanctuary T5 as on 30 June 2023.pdf20 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 ARCHITECT CERTIFICATE TOWER 5 30 06 2023.pdf17 Jul 2023
Commencement Certificates / NA Order for plotted developmentFile: FCC 05 01 07 2022.pdf6 Jun 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory Sanctuary Tower 5 31 03 2023.pdf21 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Sanctuary Tower 5 31 03 2023.pdf20 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate Sanctuary 5 31 3 2023.pdf20 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sanctuary Tower 5 31 03 2023.pdf20 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SANCTUARY TOWER 5_31-12-2022_FORM 1.pdf20 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sanctuary Tower 5 Engineers Certificate.pdf20 Jan 2023
Disclosure of sold/ booked inventoryFile: Sanctuary Tower 5 Sold Unsold.pdf20 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sanctuary Tower 5.pdf16 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 The Sanctuary T 5 Sep 2022.pdf19 Oct 2022
Disclosure of sold/ booked inventoryFile: sold unsold The Sanctuary Tower 5.pdf19 Oct 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 The Sanctuary T 5 Sep 2022.pdf19 Oct 2022
Commencement Certificates / NA Order for plotted developmentFile: CC Bldg No 5 11822 Sanctuary.pdf10 Oct 2022
Declaration about Commencement CertificateFile: SANCTUARY_T5_Declaration about CC_RC_30092022.pdf10 Oct 2022

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Runwal Pearl Tower Shell Coral and Oystervillage Chitalsar Manpada Thane288CompletedJun 2012Late, Nov 2013

How this compares with Mumbai Suburban

86%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 6 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep THE SANCTUARY - TOWER 5 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mulund6,700+ in Mumbai Suburban

2 kmTHE SANCTUARY - TOWER 5Completed 43Lapsed / revoked 14Other 16Dot size: filed unitsN

Filed coordinates, straight-line distance. 73 registered projects within 2 km.

Builder: Runwal Construction Private Limited

Runwal Construction Private Limited has 10 registrations on MahaRERA, including RUNWAL SERENE and RUNWAL PEARL. Its filings disclose 12 earlier MahaRERA projects: declares 4 of 5 past projects completed on time. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if THE SANCTUARY - TOWER 5 is delayed beyond 30 Sep 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of THE SANCTUARY - TOWER 5?

The registered promoter entity is Runwal Construction Private Limited, a company as per the filing. Its CIN U41001MH2023PTC406024 and GSTIN 27AAMCR8126K1ZT can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in THE SANCTUARY - TOWER 5?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against THE SANCTUARY - TOWER 5?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for THE SANCTUARY - TOWER 5?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at THE SANCTUARY - TOWER 5?

The professionals named in the filing: Architect: Ninad Dinkar Mhaskar; Architect: Pallavi Matkari; Engineer: Sanjay Singh; Chartered Accountant: S P Gunjal & Associates; Chartered Accountant: M B Agrawal & Co; Chartered Accountant: S M GUPTA CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in THE SANCTUARY - TOWER 5?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About THE SANCTUARY - TOWER 5. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save THE SANCTUARY - TOWER 5 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.