The Greater Good

By Sai Infra

RG-MH-37150 · RERA P52100015361 · Last updated on MahaRERA portal: 22 Jan 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 52 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2022Possession promised52 months past this date
18 of 22Construction stages doneacross 2 buildings; furthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 38 documents Report an error

The Greater Good is a Commercial project by Sai Infra in Pune, Maharashtra, registered with MahaRERA as P52100015361 on 20 Feb 2018. Possession was promised by 30 Jun 2022 and is now 52 months past that date.

At a glance

Project

  • NameThe Greater Good
  • TypeCommercial
  • Location
    • NA
    • MOHAMMADWADI
    • Haveli
    • Pune
    • 411060
  • Pincode411060
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100015361
  • ReraGenie IDRG-MH-37150

Builder

  • NameSai Infra
  • Entity typeOthers
  • Named personsAditya Girish Gadiya, Sarvesh Gadiya, Nikhil Gadiya, Vishal Jain, Vishal Bhangire
  • Other registrations6 more →
  • Completed2 of 7
  • No longer live3 lapsed, de-registered or revoked
  • Declared earlier projects4 →

Key dates

52 months past promisethis monthRegisteredFeb 2018PromisedJun 2022

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on20 Feb 2018
  • Promised completion30 Jun 2022
  • Revised completionNone
  • Buildings2 building records
  • Documents filed38 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
The Greater Good - A WingNA50000
The Greater Good - B WingNA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 22 Jan 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 0%.

The Greater Good - A Wing82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
The Greater Good - B Wing82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 22 Jan 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes80%
Water SupplyYes80%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes60%
Storm Water DrainsYes60%
Landscaping & Tree PlantingYes70%
Street LightingYes80%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes30%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes80%
Energy managemcntYes80%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Land and ownership8

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,900 sq m
Land owned byThe promoter, with other names on the file
Named landowners8
LandownerVillageDistrict
Sai Infra (Promoter)Pune (CB)Pune
Kantabai Bhangire (Land Owner)MOHAMMADWADIPune
Tushar Bhangire (Land Owner)MOHAMMADWADIPune
Punam Bandal (Land Owner)WadachiwadiPune
Balasaheb Bhangire (Land Owner)MOHAMMADWADIPune
Maruti Bhangire (Land Owner)MOHAMMADWADIPune
Subhash Bhangire (Land Owner)MOHAMMADWADIPune
Bhagwan Bhangire (Land Owner)MOHAMMADWADIPune

Approvals and building plan

Permissible FSI2122.74
Proposed, not sanctioned2,123 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDSK ROHIT BLDG GROUND FLOOR OFF JM ROAD SHIVAJI NAGAR PUNE 411004

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectGROUP CONSULTANT
EngineerSunil Mutalik & Associates
Chartered AccountantCaYogesh Bhagat
Chartered AccountantManojAgarwal
PartnerRole in project
Sai Infra-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 4 Feb 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 4 Feb 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 4 Feb 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 4 Feb 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 30 Nov 2019

Documents filed38

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Covering Latter with Attachment.pdf22 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Covering Latter with Attachment.pdf8 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Covering Latter with Attachment.pdf28 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Sai Infra Comercial Rera from 5.pdf27 Feb 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Commercial - AR on Statement of Account.pdf30 Nov 2019
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Sai Infra Shop Completion Certificate.pdf30 Nov 2019
Details of encumbrancesFile: ENCUMBRANCES CERTIFICATE PHASE-I.pdf24 Dec 2018
OtherFile: Mortgage-deed-1.pdf15 Oct 2018
OtherFile: Mortgage-deed-2.pdf15 Oct 2018
OtherFile: Mortgage-deed-3.pdf15 Oct 2018
OtherFile: Mortgage-deed-4.pdf15 Oct 2018
Certificates of CA (Form 5)File: fORM 5 CA Certificate.pdf29 Sep 2018
Declaration in FORM BFile: Declaration Form B Promoters.pdf9 Feb 2018
Proforma of Allotment letterFile: Draft Agreement for Sale.pdf9 Feb 2018
Layout approvalFile: Layout Plan.pdf4 Feb 2018
Building plan approvalFile: Building Plan Approval 1 of 6.pdf4 Feb 2018
Building plan approvalFile: Building Plan Approval 2 of 6.pdf4 Feb 2018
Building plan approvalFile: Building Plan Approval 3 of 6.pdf4 Feb 2018
Building plan approvalFile: Building Plan Approval 4 of 6.pdf4 Feb 2018
Building plan approvalFile: Building Plan Approval 5 of 6.pdf4 Feb 2018
Building plan approvalFile: Building Plan Approval 6 of 6.pdf4 Feb 2018
PAN CardFile: PAN - Sai Infra - Promoter.pdf4 Feb 2018
Copy of the legal title reportFile: Legal Title Report.pdf4 Feb 2018
Copy of the legal title reportFile: Supplementary Legal Title Report.pdf4 Feb 2018
Details of encumbrancesFile: Details of Encumbrances.pdf4 Feb 2018
Copy of Layout Approval (in case of layout)File: Layout Plan.pdf4 Feb 2018
Building Plan Approval (IOD)File: Building Plan Approval 1 of 6.pdf4 Feb 2018
Building Plan Approval (IOD)File: Building Plan Approval 2 of 6.pdf4 Feb 2018
Building Plan Approval (IOD)File: Building Plan Approval 3 of 6.pdf4 Feb 2018
Building Plan Approval (IOD)File: Building Plan Approval 4 of 6.pdf4 Feb 2018
Building Plan Approval (IOD)File: Building Plan Approval 5 of 6.pdf4 Feb 2018
Building Plan Approval (IOD)File: Building Plan Approval 6 of 6.pdf4 Feb 2018
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate Layout.pdf4 Feb 2018
Commencement Certificates / NA Order for plotted developmentFile: Commenement Cert Bldg.pdf4 Feb 2018
Declaration in FORM BFile: Declaration - Form B - Land Owners.pdf4 Feb 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf4 Feb 2018
Certificates of CA (Form 3)File: CA Certificate.pdf4 Feb 2018
Proforma of Allotment letterFile: Allotment Letter.pdf4 Feb 2018

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Casa Familia36-1 Mohammadwadi Talluka Haveli District Pune 6032CompletedDec 2016Late, Jan 2017
Gran ExitoS No 73-2A B T Kawade Road Ghorpadi Pune 41100144CompletedSep 2012Late, Jul 2016
Venkatesh FloraS. No. 96 BCD Deccan Paper Mill Mundhawa Pune 411036161CompletedMar 2008Late, Jun 2013

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep The Greater Good on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NA13,700+ in Pune

2 kmThe Greater GoodCompleted 85Lapsed / revoked 26Other 91Dot size: filed unitsN

Filed coordinates, straight-line distance. 202 registered projects within 2 km.

Builder: Sai Infra

SAI INFRA has 7 registrations on MahaRERA, including SAI SAGAR and SAI GANESH. Its filings disclose 4 earlier MahaRERA projects: declares 1 of 4 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that The Greater Good shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if The Greater Good is delayed beyond 30 Jun 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of The Greater Good?

The registered promoter entity is Sai Infra, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in The Greater Good?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for The Greater Good?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at The Greater Good?

The professionals named in the filing: Architect: GROUP CONSULTANT; Engineer: Sunil Mutalik & Associates; Chartered Accountant: CaYogesh Bhagat; Chartered Accountant: ManojAgarwal. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in The Greater Good?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About The Greater Good. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save The Greater Good to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.