Red flags

  • Registration lapsed
  • Possession 52 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2022Possession promised52 months past this date
0 of 11Construction stages donefurthest along: Excavation, 85%
0Complaints at MahaRERAon this registration
Jump to the 49 documents Report an error

THE GOLF BOULEVARD BUILDING - 1 is a Residential / Group Housing project by EMPRESS & ADISHAKTI JV in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800002734 on 4 Aug 2017. Possession was promised by 30 Jun 2022 and is now 52 months past that date.

At a glance

Project

  • NameTHE GOLF BOULEVARD BUILDING - 1
  • TypeResidential / Group Housing
  • Location
    • Chembur
    • Kurla
    • Mumbai Suburban
    • 400071
  • Pincode400071
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800002734
  • ReraGenie IDRG-MH-24289

Builder

  • NameEMPRESS & ADISHAKTI JV
  • Entity typeOthers
  • Named personEMPRESS HAMMER REALTY LLP
  • Other registrations1 more →
  • No longer live2 lapsed, de-registered or revoked

Key dates

52 months past promisethis monthRegisteredAug 2017PromisedJun 2022

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on4 Aug 2017
  • Promised completion30 Jun 2022
  • Revised completionNone
  • Buildings1 building record
  • Documents filed49 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building Number - 1NA170000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 16 Jul 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 85%.

Building Number - 1: 23% average across the applicable activities

ActivityProgress
Excavation85%
Basement (if any)85%
Podiums (if any)0%
Plinth85%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 16 Jul 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed56

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots56
Closed/Covered56

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,718 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
M/s. Augusta Homes Real Estate Pvt Ltd.-Mumbai City

Approvals and building plan

Permissible FSI12350.0
Proposed, not sanctioned8,369 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch5C II, MITAL COURT 224 NARIMAN POINT

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectACE Consultants
EngineerOptimal Consultancy Services Pvt Ltd
PartnerRole in project
EMPRESS & ADISHAKTI JV-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 16 Jul 2021

Documents filed49

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: DECLARATION THE GOLF BLDG 1.pdf16 Jul 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: DECLARATION THE GOLF BLDG 1.pdf16 Jul 2021
OtherFile: Declaration_Golf_Boulevard_Phase_1.pdf24 May 2021
OtherFile: The Boulevard 1_compressed.pdf14 Feb 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 - Chembur Phase 1- 2019.pdf28 Jan 2020
Certificates of CA (Form 5)File: Form 5 - RERA Audit 18-19.pdf14 May 2019
Certificates of CA (Form 5)File: FORM 5.pdf17 Apr 2019
PAN CardFile: JV PAN 001.pdf28 Jul 2017
Details of encumbrancesFile: No encumbrances certificate.pdf28 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Empress Adishakti JV.pdf28 Jul 2017
Certificates of CA (Form 3)File: silsila.pdf28 Jul 2017
OtherFile: Empress Adishakti JV LOI Chembur1 (1).pdf28 Jul 2017
Layout approvalFile: LAYOUT area.PDF27 Jul 2017
Building plan approvalFile: 1 floor plan.PDF27 Jul 2017
Building plan approvalFile: 7th refuge floor plan.PDF27 Jul 2017
Building plan approvalFile: car parking.PDF27 Jul 2017
Building plan approvalFile: fungible area 2 to 12.PDF27 Jul 2017
Building plan approvalFile: Builtup area diagram.PDF27 Jul 2017
Building plan approvalFile: 13 FLOOR PLAN.pdf27 Jul 2017
Building plan approvalFile: refuge floor plan.PDF27 Jul 2017
Building plan approvalFile: TERRACE FLOOR PLAN.PDF27 Jul 2017
Building plan approvalFile: typical floor plan 1st to 6th and 8th.PDF27 Jul 2017
Building plan approvalFile: typical floor plan 2 4 6.PDF27 Jul 2017
Building plan approvalFile: parking plan.pdf27 Jul 2017
Building plan approvalFile: Fungible area plan.PDF27 Jul 2017
Building plan approvalFile: ground floor plan.PDF27 Jul 2017
Building plan approvalFile: Empress Adishakti JV LOI Chembur.pdf27 Jul 2017
Copy of the legal title reportFile: Empress Adishakti JV Chembur Title Report regarding company letter.pdf27 Jul 2017
Copy of Layout Approval (in case of layout)File: LAYOUT area.PDF27 Jul 2017
Building Plan Approval (IOD)File: 1 floor plan.PDF27 Jul 2017
Building Plan Approval (IOD)File: 7th refuge floor plan.PDF27 Jul 2017
Building Plan Approval (IOD)File: 13 FLOOR PLAN.pdf27 Jul 2017
Building Plan Approval (IOD)File: Builtup area diagram.PDF27 Jul 2017
Building Plan Approval (IOD)File: car parking.PDF27 Jul 2017
Building Plan Approval (IOD)File: fungible area 2 to 12.PDF27 Jul 2017
Building Plan Approval (IOD)File: Fungible area plan.PDF27 Jul 2017
Building Plan Approval (IOD)File: ground floor plan.PDF27 Jul 2017
Building Plan Approval (IOD)File: parking plan.pdf27 Jul 2017
Building Plan Approval (IOD)File: refuge floor plan.PDF27 Jul 2017
Building Plan Approval (IOD)File: TERRACE FLOOR PLAN.PDF27 Jul 2017
Building Plan Approval (IOD)File: typical floor plan 1st to 6th and 8th.PDF27 Jul 2017
Building Plan Approval (IOD)File: typical floor plan 2 4 6.PDF27 Jul 2017
Building Plan Approval (IOD)File: Empress Adishakti JV LOI Chembur.pdf27 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Empress Adishakti JV Composite BldgCC 13042017Chembur.pdf27 Jul 2017
Declaration in FORM BFile: form_b_empress_adishakti.pdf27 Jul 2017
Declaration in FORM BFile: download (1).pdf27 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: empress_adishakti_jv.pdf27 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: B3Ecertificate.pdf27 Jul 2017
Proforma of Allotment letterFile: AFS Empress Adishakti.pdf27 Jul 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep THE GOLF BOULEVARD BUILDING - 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Chembur6,700+ in Mumbai Suburban

2 kmTHE GOLF BOULEVARD BUILDCompleted 139Lapsed / revoked 110Other 134Dot size: filed unitsN

Filed coordinates, straight-line distance. 383 registered projects within 2 km.

Builder: EMPRESS & ADISHAKTI JV

EMPRESS & ADISHAKTI JV has 2 registrations on MahaRERA, including THE GOLF BOULEVARD BUILDING - 1 and THE GOLF BOULEVARD BUILDING 2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that THE GOLF BOULEVARD BUILDING - 1 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if THE GOLF BOULEVARD BUILDING - 1 is delayed beyond 30 Jun 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of THE GOLF BOULEVARD BUILDING - 1?

The registered promoter entity is EMPRESS & ADISHAKTI JV, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in THE GOLF BOULEVARD BUILDING - 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for THE GOLF BOULEVARD BUILDING - 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at THE GOLF BOULEVARD BUILDING - 1?

The professionals named in the filing: Architect: ACE Consultants; Engineer: Optimal Consultancy Services Pvt Ltd. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in THE GOLF BOULEVARD BUILDING - 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About THE GOLF BOULEVARD BUILDING - 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save THE GOLF BOULEVARD BUILDING - 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.