Registration lapsed Litigation declared Commercial project

The Arcade

By CCI PROJECTS PRIVATE LIMITED

RG-MH-96852 · RERA P51800018662 · Last updated on MahaRERA portal: 5 Mar 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 16 months past the filed date
  • Litigation declared, 2 cases
  • Completion date moved by 42 months
  • 4 extensions taken

Clear

  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2025Possession promised16 months past this date
6 of 11Construction stages donefurthest along: Internal walls, 90%
0 of 5Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 104 documents Report an error

The Arcade is a Commercial project by CCI PROJECTS PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800018662 on 22 Nov 2018. Possession was promised by 30 Jun 2025 and is now 16 months past that date. The completion date has moved by 42 months from the original filing. 5 of the 5 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete.

At a glance

Project

  • NameThe Arcade
  • TypeCommercial
  • Location
    • Near Kanakia Samarpan
    • Western Express Highway
    • Magathane Telephone Exchange
    • Borivali
    • Mumbai Suburban
    • 400066
  • Pincode400066
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800018662
  • ReraGenie IDRG-MH-96852

Builder

  • NameCCI PROJECTS PRIVATE LIMITED
  • Entity typeCompany
  • CINU70102MH2000PTC128732
  • GSTIN27AABCT4694B1ZC
  • CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
  • DirectorsHiten A Khatau, Rohan Hiten Khatau
  • Other registrations7 more →
  • Completed2 of 8
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects6 →

Key dates

16 months past promisethis monthRegisteredNov 2018First promiseDec 2021Revised toJun 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on22 Nov 2018
  • Promised completion30 Jun 2025
  • Revised completionRevised to 30 Jun 2025 (originally 30 Dec 2021)
  • Buildings1 building record
  • Documents filed104 files

Current status

100%5 of 5 units booked

Figures as on 5 Mar 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
The ArcadeNA21055

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 5 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 90%.

The Arcade: 78% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 5 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes90%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,052 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
CCI PROJECTS PVT LTDBorivaliMumbai Suburban

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI870.08
Proposed, not sanctioned870 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchHdfc Bank Ltd Ground Floor Jehangir Building M G Road Fort Mumbai Maharashtra 400001

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectR DESIGN ARCHITECTS
ArchitectVipul Mistry & Associates
EngineerShanghvi and Associates Consultants Private Limited
EngineerMILIND NAIK
EngineerMadhu Sudhanan M P V
EngineerSubrat Kumar Bansidhar Pradhan
Chartered AccountantS A Sangani & Associates LLP
Chartered AccountantH Paurana and Associates
PartnerRole in project
CCI PROJECTS PRIVATE LIMITED-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800011169Dec 2021 → Dec 2022

Reason as filed by the promoterNo Sale. Hence Extension.

EXT51800017023Dec 2021 → Jun 2024

Reason as filed by the promoterThe above named project is a commercial project. We had completed the construction and we are in process of obtaining Occupancy Certificate. We haven’t sold / booked any inventory till date in the said project.

EXT51800013917Dec 2021 → Jun 2023

Reason as filed by the promoterThe above named project is a commercial project and we had completed the construction and we are in process of Occupancy Certificate. We haven’t sold / booked any inventory till date.

EXT51800024103Dec 2021 → Jun 2025

Reason as filed by the promoterThe real estate project " The Arcade" is a commercial project consisting of only 5 units in total. The construction of the said project is completed in all respect and we are in process of applying for occupancy certificate (O.C.) only recently we sold the said units and informed the allottees about the extension. Hence, we humbly request Ld. Authority to grant extension at the earliest.

Litigation declared2

CaseCourtStatus
WP/1685/2017Bombay High CourtOngoing
ULP No 18/2017Before the Member of the Industrial Court at Mumbai Court at MumbaiClosed

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 Nov 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Oct 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 6 Nov 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 Feb 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 5 Mar 2025

Documents filed104

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 104 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: ARCade_OC plan.pdf5 Mar 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupancy Certi_Arcade_170225.pdf26 Feb 2025
Proforma of Agreement for saleFile: Arcade AFS to upload.pdf22 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Certi_Form 1_Arcade_Dec 24.pdf20 Jan 2025
Certificates of CA (Form 3)File: CACerti_Form 3_Arcade_Dec 24.PDF20 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Certi_Form 2_Arcade_Dec 24.pdf20 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5_Arcade_23-24.pdf19 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Certi_Form 1_Arcade_Sep 24.pdf17 Oct 2024
Certificates of CA (Form 3)File: CA Certi_Form 3_Arcade_Sept 24_compressed.pdf17 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Certi_Form2_ARCADE_OCT 24.pdf17 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1-Architect Certi_Arcade_300624.pdf6 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2-Engg Certi_Arcade_300624.pdf6 Aug 2024
Certificates of CA (Form 3)File: Form 3-CA Certi_Arcade_300624_c.pdf6 Aug 2024
Declaration in FORM BFile: Form B_compressed.pdf27 Jun 2024
Disclosure of sold/ booked inventoryFile: sold booked_Arcade Ext June 25.pdf27 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Quality Assurance_Arcade_23-24.pdf11 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate_Arcade_March 2024.pdf7 Jun 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate_Arcade_March 2024.pdf7 Jun 2024
Certificates of CA (Form 3)File: CA Certificate_Arcade_March 2024.pdf7 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate Arcade- 31 Dec 2023.pdf31 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate Arcade -31 Dec 2023.pdf31 Jan 2024
Certificates of CA (Form 3)File: CA Certificate Arcade- 31 Dec 2023.pdf31 Jan 2024
Copy of the legal title reportFile: Legal Title Report 290923 Part 1_Rvs.pdf24 Nov 2023
Copy of the legal title reportFile: Legal Title Report 290923 Part 2.pdf24 Nov 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Arcade_300923.pdf2 Nov 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate Arcade_300923.pdf2 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Annual CA Certi Form 5 CCIPL Final.pdf2 Nov 2023
Certificates of CA (Form 3)File: Form 3-CA Certificate-Arcade_compressed.pdf26 Sep 2023
Declaration in FORM BFile: Affidavit Cum Declartion-Form B.pdf29 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A_Engg Quality Assurance.pdf29 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Arcade Form 5 March 2022 Signed.pdf29 Aug 2023
Disclosure of sold/ booked inventoryFile: Arcade Sold-Booked-060223.pdf6 Feb 2023
Disclosure of sold/ booked inventoryFile: Final_ARCADE Sold_Booked Inventory_211222.pdf28 Dec 2022
Disclosure of sold/ booked inventoryFile: ARCADE Sold_Booked Inventory.pdf7 Mar 2022
CERSAI detailsFile: CERSAI_Search_Report_200231801955_For_Asset_Based_Search_07_03_2022_16_31_21_107.pdf7 Mar 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate - Arcade.pdf9 Feb 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate - Arcade.pdf9 Feb 2022
Certificates of CA (Form 3)File: CA Certificate - Arcade.pdf9 Feb 2022
Commencement Certificates / NA Order for plotted developmentFile: Further CC revalidation.pdf7 Feb 2022
Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMENT CERTIFICATE.pdf7 Feb 2022
CERSAI detailsFile: undertaking CRESAI.pdf7 Feb 2022
Disclosure of sold/ booked inventoryFile: Sold_Booked Inventory.pdf7 Feb 2022
OtherFile: Declaration of allottees consent.pdf7 Feb 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Arcade - Form 5.pdf31 Dec 2021
Certificates of CA (Form 3)File: CA certificate - Arcade_compressed.pdf12 Nov 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arcade - Architect Certificate.pdf30 Oct 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Arcade - Engineer Certificate.pdf30 Oct 2021
Certificates of CA (Form 3)File: CA certificate - Arcade - June 2021.pdf4 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate - Arcade - June 2021.pdf3 Aug 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate - Arcade - June 2021.pdf3 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - THE ARCADE_RETAIL_31-03-2021.pdf25 Apr 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering certificate - Arcade-compressed.pdf25 Apr 2021
Certificates of CA (Form 3)File: Form 3 Arcade-22-04-2021_compressed.pdf25 Apr 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate - THE ARCADE-min-compressed.pdf28 Jan 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA ENGINEER CERTIFICATE DECEMBER 2020 RETAIL-min.pdf28 Jan 2021
Certificates of CA (Form 3)File: CA - THE ARCADE-min.pdf28 Jan 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate - Arcade.pdf29 Oct 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer certificate - The Arcade.pdf29 Oct 2020
Certificates of CA (Form 3)File: FORM-3 THE ARCADE.pdf29 Oct 2020
Annual Audit Report of Statutory CA (Form 5)File: CCIPL Form 5 Arcade March 2020.pdf30 Sep 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: CCIPL Form 5 Arcade March 2020.pdf30 Sep 2020
Certificates of CA (Form 3)File: CA Certificate June 2020 Arcade.pdf9 Sep 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate Arcade June2020.pdf12 Aug 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer certificate Retail June 2020 Comp.pdf12 Aug 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate - Arcade - Mar2020.pdf30 Jun 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer certificate - Arcade - March 2020_compressed.pdf30 Jun 2020
Certificates of CA (Form 3)File: CA Certificate Arcade.pdf30 Jun 2020
Certificates of CA (Form 3)File: CA Certificate The Arcade.pdf22 Jan 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Arcade.pdf21 Jan 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate Arcade.pdf21 Jan 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate Arcade sept19.pdf25 Oct 2019
Engineers Certificate on Quality Assurance (Form 2A)File: Engineer certificate Arcade sept19.pdf25 Oct 2019
Certificates of CA (Form 3)File: FORM 3A ARCADE compressed.pdf25 Oct 2019
OtherFile: Affidavit.pdf3 Oct 2019
Annual Audit Report of Statutory CA (Form 5)File: Form 5 The Arcade.pdf30 Sep 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate of The arcade June 2019.pdf22 Jul 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA ENGINEER CERTIFICATE The Arcade 2019.pdf22 Jul 2019
Certificates of CA (Form 3)File: The Arcade CA Certificate June 2019.pdf22 Jul 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Arcade Apr 2019.pdf23 Apr 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Arcade Retail.pdf23 Apr 2019

Promoter's earlier projects5

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late4 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Rivali Park - SkyleapPR1183032501382Magathane, Mumbai Suburban178Nov 2025OngoingJul 2032Not due yet
Rivali Park - MoonriseP51800055489CCI Compound, Mumbai Suburban354Apr 2024OngoingJun 2030Not due yet
Rivali Park - StargazeP51800053578CCI Compound, Mumbai Suburban198Nov 2023OngoingOct 2029Not due yet
Rivali Park - SunburstP51800050351CCI Compound, Mumbai Suburban277Apr 2023OngoingAug 2028Not due yet
WintergreenRivali Park Western Express Highway Borivali East Mumbai 400066708-CompletedDec 2019Late, Apr 2021

How this compares with Mumbai Suburban

100%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 42 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep The Arcade on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Magathane Telephone Exchange6,700+ in Mumbai Suburban

2 kmThe ArcadeCompleted 73Lapsed / revoked 50Other 120Dot size: filed unitsN

Filed coordinates, straight-line distance. 243 registered projects within 2 km.

Builder: CCI PROJECTS PRIVATE LIMITED

CCI PROJECTS PRIVATE LIMITED has 8 registrations on MahaRERA, including Whitespring and Wintergreen. Its filings disclose 6 earlier MahaRERA projects: declares 1 of 2 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that The Arcade shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if The Arcade is delayed beyond 30 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of The Arcade?

The registered promoter entity is CCI PROJECTS PRIVATE LIMITED, a company as per the filing. Its CIN U70102MH2000PTC128732 and GSTIN 27AABCT4694B1ZC can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in The Arcade?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for The Arcade?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at The Arcade?

The professionals named in the filing: Architect: R DESIGN ARCHITECTS; Architect: Vipul Mistry & Associates; Engineer: Shanghvi and Associates Consultants Private Limited; Engineer: MILIND NAIK; Engineer: Madhu Sudhanan M P V; Engineer: Subrat Kumar Bansidhar Pradhan. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in The Arcade?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About The Arcade. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save The Arcade to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.