CCI PROJECTS PRIVATE LIMITED: RERA track record
CIN U70102MH2000PTC128732 · GSTIN 27AABCT4694B1ZC · Company · attribution by exact filing name, entity resolution in progress
CCI PROJECTS PRIVATE LIMITED has 8 registrations on MahaRERA, including Whitespring and Wintergreen. Its filings disclose 6 earlier MahaRERA projects: declares 1 of 2 past projects completed on time. Litigation is declared on 1 of its registrations.
Projects by this developer
Showing all 8 projects.
Largest first, by the unit count in the filing.
| Project | Location | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| Rivali Park - MoonriseP51800055489 | CCI Compound, Mumbai Suburban, 400066 | 354 | 75% | 2 Apr 2024 | Registered |
| Rivali Park - SunburstP51800050351 | CCI Compound, Mumbai Suburban, 400066 | 277 | 94% | 5 Apr 2023 | Registered |
| Rivali Park - StargazeP51800053578 | CCI Compound, Mumbai Suburban, 400066 | 198 | 61% | 10 Nov 2023 | Registered |
| Rivali Park - SkyleapPR1183032501382 | Magathane, Mumbai Suburban, 400066 | 178 | 67% | 3 Nov 2025 | Registered |
| Rivali Park-SkyflowPR1184042502590 | Magathane, Mumbai Suburban, 400066 | 5 | 0% | 4 Mar 2026 | Registered |
| The ArcadeP51800018662 | Magathane Telephone Exchange, Mumbai Suburban, 400066 | 5 | 100% | 22 Nov 2018 | Registration lapsed |
| WhitespringP51800002287 | Borivali East, Mumbai Suburban, 400066 | - | - | 31 Jul 2017 | Completed |
| WintergreenP51800003067 | Borivali East, Mumbai Suburban, 400066 | - | - | 4 Aug 2017 | Completed |
What this promoter declares as its own experience
CCI PROJECTS PRIVATE LIMITED declares experience on 6 earlier projects. 5 of them carry a registration number we could match on MahaRERA, all under this promoter's own name.
5 of these declarations can be compared with the dates those projects' own registrations hold. On 1, the date given as the original completion date is the REVISED deadline that project carries after an extension rather than its original one. That changes the arithmetic on the one completion recorded here as on time: measured against the original deadline the register itself holds, that one was finished after it. A completion date is also recorded against 1 registration MahaRERA does not show as completed. A registration lapses when a promoter files neither a completion nor an extension, so that can mean the completion was never filed rather than that the project was not finished.
From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| Wintergreen | 31 Dec 2019 | 7 Apr 2021 | +15 months |
| The Arcade P51800018662 | 30 Jun 2025 | 17 Feb 2025 | On time |
| Rivali Park - Sunburst P51800050351 | 31 Aug 2028 | Not completed yet | Ongoing |
| Rivali Park - Stargaze P51800053578 | 31 Oct 2029 | Not completed yet | Ongoing |
| Rivali Park - Moonrise P51800055489 | 30 Jun 2030 | Not completed yet | Ongoing |
| Rivali Park - Skyleap PR1183032501382 | 31 Jul 2032 | Not completed yet | Ongoing |
Frequently asked questions
How do I verify CCI PROJECTS PRIVATE LIMITED as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its CIN U70102MH2000PTC128732 and GSTIN 27AABCT4694B1ZC on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with CCI PROJECTS PRIVATE LIMITED?
Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
Does the declared litigation make CCI PROJECTS PRIVATE LIMITED unsafe to buy from?
Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.