Home / Developers / CCI PROJECTS PRIVATE LIMITED
CCI PROJECTS PRIVATE LIMITED: RERA track record
Company ยท attribution by exact filing name, entity resolution in progress
CCI PROJECTS PRIVATE LIMITED has 8 registrations in this build, including Whitespring and Wintergreen. Its filings disclose 6 earlier MahaRERA projects: 1 of 2 past projects completed on time. Litigation is declared on 1 of its registrations.
Projects in this build
| Project | Location | Units | Booked | Status |
|---|---|---|---|---|
| Whitespring | Mumbai Suburban, Maharashtra | - | - | Completed |
| Wintergreen | Mumbai Suburban, Maharashtra | - | - | Completed |
| The Arcade | Mumbai Suburban, Maharashtra | 5 | 100% | Registration lapsed |
| Rivali Park - Sunburst | Mumbai Suburban, Maharashtra | 277 | 94% | Registered |
| Rivali Park - Stargaze | Mumbai Suburban, Maharashtra | 198 | 61% | Registered |
| Rivali Park - Moonrise | Mumbai Suburban, Maharashtra | 354 | 75% | Registered |
| Rivali Park - Skyleap | Mumbai Suburban, Maharashtra | 178 | 67% | Registered |
| Rivali Park-Skyflow | Mumbai Suburban, Maharashtra | 5 | 0% | Registered |
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| Wintergreen | 31 Dec 2019 | 7 Apr 2021 | +15 months |
| The Arcade P51800018662 | 30 Jun 2025 | 17 Feb 2025 | On time |
| Rivali Park - Sunburst P51800050351 | 31 Aug 2028 | Not completed yet | Ongoing |
| Rivali Park - Stargaze P51800053578 | 31 Oct 2029 | Not completed yet | Ongoing |
| Rivali Park - Moonrise P51800055489 | 30 Jun 2030 | Not completed yet | Ongoing |
| Rivali Park - Skyleap PR1183032501382 | 31 Jul 2032 | Not completed yet | Ongoing |
Frequently asked questions
How do I verify CCI PROJECTS PRIVATE LIMITED as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with CCI PROJECTS PRIVATE LIMITED?
Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
Does the declared litigation make CCI PROJECTS PRIVATE LIMITED unsafe to buy from?
Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.
Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.