CCI PROJECTS PRIVATE LIMITED: RERA track record

CIN U70102MH2000PTC128732 · GSTIN 27AABCT4694B1ZC · Company · attribution by exact filing name, entity resolution in progress

CCI PROJECTS PRIVATE LIMITED has 8 registrations on MahaRERA, including Whitespring and Wintergreen. Its filings disclose 6 earlier MahaRERA projects: declares 1 of 2 past projects completed on time. Litigation is declared on 1 of its registrations.

8RERA registrations
6Past projects disclosed
+6 monthsMedian delivery slip
1Registrations with litigation
Follow this developer. An email when CCI PROJECTS PRIVATE LIMITED registers a new project on MahaRERA, and when the filings of their existing projects change: new sales, moved possession dates, extensions, complaints. Runs 12 months, no auto-renew. Follow · Rs 999 / 12 months

Projects by this developer

Showing all 8 projects.

Largest first, by the unit count in the filing.

ProjectLocationUnitsBookedRegisteredStatus
Rivali Park - MoonriseP51800055489CCI Compound, Mumbai Suburban, 40006635475%2 Apr 2024Registered
Rivali Park - SunburstP51800050351CCI Compound, Mumbai Suburban, 40006627794%5 Apr 2023Registered
Rivali Park - StargazeP51800053578CCI Compound, Mumbai Suburban, 40006619861%10 Nov 2023Registered
Rivali Park - SkyleapPR1183032501382Magathane, Mumbai Suburban, 40006617867%3 Nov 2025Registered
Rivali Park-SkyflowPR1184042502590Magathane, Mumbai Suburban, 40006650%4 Mar 2026Registered
The ArcadeP51800018662Magathane Telephone Exchange, Mumbai Suburban, 4000665100%22 Nov 2018Registration lapsed
WhitespringP51800002287Borivali East, Mumbai Suburban, 400066--31 Jul 2017Completed
WintergreenP51800003067Borivali East, Mumbai Suburban, 400066--4 Aug 2017Completed

What this promoter declares as its own experience

CCI PROJECTS PRIVATE LIMITED declares experience on 6 earlier projects. 5 of them carry a registration number we could match on MahaRERA, all under this promoter's own name.

5 of these declarations can be compared with the dates those projects' own registrations hold. On 1, the date given as the original completion date is the REVISED deadline that project carries after an extension rather than its original one. That changes the arithmetic on the one completion recorded here as on time: measured against the original deadline the register itself holds, that one was finished after it. A completion date is also recorded against 1 registration MahaRERA does not show as completed. A registration lapses when a promoter files neither a completion nor an extension, so that can mean the completion was never filed rather than that the project was not finished.

From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
Wintergreen
31 Dec 20197 Apr 2021+15 months
The Arcade
P51800018662
30 Jun 202517 Feb 2025On time
Rivali Park - Sunburst
P51800050351
31 Aug 2028Not completed yetOngoing
Rivali Park - Stargaze
P51800053578
31 Oct 2029Not completed yetOngoing
Rivali Park - Moonrise
P51800055489
30 Jun 2030Not completed yetOngoing
Rivali Park - Skyleap
PR1183032501382
31 Jul 2032Not completed yetOngoing

Frequently asked questions

How do I verify CCI PROJECTS PRIVATE LIMITED as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its CIN U70102MH2000PTC128732 and GSTIN 27AABCT4694B1ZC on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with CCI PROJECTS PRIVATE LIMITED?

Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

Does the declared litigation make CCI PROJECTS PRIVATE LIMITED unsafe to buy from?

Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.

Spotted a project attributed to the wrong developer, or something else wrong on this page? Projects are grouped by the promoter name as filed, so a firm that registers under two spellings can split across two pages. Tell us and we will check it against the filings.

Report an errorShare feedback

Data from official MahaRERA filings. How we handle corrections is on the about page.