ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / TANISHQ RESIDENCY

Registration lapsed No litigation declared Others project

TANISHQ RESIDENCY

By PRATHAMESH DEVELOPERS

RG-MH-27248 · RERA P51800005734 · Last updated on MahaRERA portal: 2 Apr 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
20 of 33Construction stages doneacross 3 buildings; furthest along: Staircases, 75%
0Complaints at MahaRERAon this registration
Jump to the 108 documents Report an error

TANISHQ RESIDENCY is a Others project by PRATHAMESH DEVELOPERS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800005734 on 11 Aug 2017. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 24 months from the original filing.

At a glance

Project

  • NameTANISHQ RESIDENCY
  • TypeOthers
  • Location
    • Kurla
    • Mumbai Suburban
    • 400070
  • Pincode400070
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800005734
  • ReraGenie IDRG-MH-27248

Builder

  • NamePRATHAMESH DEVELOPERS
  • Entity typePartnership
  • PartnersPARESH KANTILAL SHAH, TUSHAR BABULAL KUVADIA, AMAR NAVIN CHHEDA, MANISH DINESH PATEL, DHARMESH BHUPAT GIRI, BHAVESH BHUPAT GIRI
  • Other registrations1 more →
  • No longer live1 lapsed, de-registered or revoked

Key dates

10 months past promisethis monthRegisteredAug 2017First promiseDec 2023Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on11 Aug 2017
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 30 Dec 2023)
  • Buildings3 building records
  • Documents filed108 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TANISHQ RESIDENCY - A WINGNA160000
TANISHQ RESIDENCY - B WINGNA160000
TANISHQ RESIDENCY - C WINGNA160000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 2 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

20 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Staircases, at 75%.

TANISHQ RESIDENCY - A WING73%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises40%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.40%
TANISHQ RESIDENCY - B WING73%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises40%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.40%
TANISHQ RESIDENCY - C WING91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 2 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes60%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed41

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots41
Closed/Covered41
BuildingClosed/CoveredTotal
TANISHQ RESIDENCY - A WING2424
TANISHQ RESIDENCY - B WING1616
TANISHQ RESIDENCY - C WING11

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,218 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on2 Apr 2026

Approvals and building plan

Sanctioning authoritySRA
Permissible FSI10517.95
Proposed, not sanctioned6,732 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShop No 2, Matunga Raj Niketan CHS Ltd, Plot No 356, Bhandarkar Road, Mumbai - 400019

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
Chartered AccountantCHIRAG PATEL
PartnerRole in project
PRATHAMESH DEVELOPERS-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800017997Dec 2023 → Dec 2024

Reason as filed by the promoterDELAY IN APPROVAL FROM THE GOVT DEPARTMENT . WE SHALL COMPLETE THE BUILDING WITHIN 1 YEAR.

EXT51800025712Dec 2023 → Dec 2025

Reason as filed by the promoterthe project is almost completed and applied for the oc of the rehab portion. as the competent authority is SRA therefore the sale building oc shall be issued after the oc of the rehab wing is issued. We are positive about obtaining OC as soon as possible. we have obtained the necessary consent for the extension therefore kindly do the needful.

Litigation declared1

CaseCourtStatus
CC/II/105/2015COOPERATIVE COURT AT MUMBAIDISPOSED

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 5 Mar 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Jul 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 23 Oct 2023

Documents filed108

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 108 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1 architect's certificate FY23-24 OCT-MAR 24.pdf2 Apr 2026
Withdrawal Update Form 1File: FORM 1 architect's certificate FY23-24 OCT-MAR 24.pdf2 Apr 2026
Withdrawal Update Form 1File: FORM 1 architect's certificate FY23-24 OCT-MAR 24.pdf2 Apr 2026
Withdrawal Update Form 2File: FORM -2 Engineer's certificate FY 23-24 Oct to Mar 24.pdf2 Apr 2026
Withdrawal Update Form 2File: FORM -2 Engineer's certificate FY 23-24 Oct to Mar 24.pdf2 Apr 2026
Withdrawal Update Form 2File: FORM -2 Engineer's certificate FY 23-24 Oct to Mar 24.pdf2 Apr 2026
Withdrawal Update Form 3File: Form - 3 Chirag Letter Head oct to mar 24 6Months Updated.pdf2 Apr 2026
Withdrawal Update Form 3File: Form - 3 Chirag Letter Head oct to mar 24 6Months Updated.pdf2 Apr 2026
Withdrawal Update Form 3File: Form - 3 Chirag Letter Head oct to mar 24 6Months Updated.pdf2 Apr 2026
Certificates of CA (Form 3)File: ilovepdf_merged (80)_compressed.pdf27 Jan 2025
Disclosure of sold/ booked inventoryFile: ilovepdf_merged (81).pdf27 Jan 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Revised Format A 23-01-25.pdf27 Jan 2025
Certificates of CA (Form 3)File: DocScanner Jan 25, 2025 12-05 PM_compressed.pdf25 Jan 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A 23-01-25.pdf25 Jan 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in other Real estate projects.pdf25 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: DocScanner Jan 25, 2025 11-49 AM.pdf25 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: DocScanner Jan 25, 2025 11-49 AM (1).pdf25 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 Architect Certificate.pdf10 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 Engineer Certificate.pdf10 Jan 2025
Certificates of CA (Form 3)File: Form - 3 Chirag Letter Head Apr to Dec 24 9Months Updated_compressed.pdf9 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 architect's certificate FY24-25 APR-DEC 24.pdf8 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM -2 Engineer's certificate FY 24-25 Apr to Dec 24.pdf8 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 Annual Report FY 2023-24.pdf4 Jan 2025
Declaration in FORM BFile: DocScanner 23-Dec-2024 3-08 pm (1).pdf23 Dec 2024
Proforma of Agreement for saleFile: GetUserDocumentFileContent (24).pdf23 Dec 2024
PAN CardFile: Prathmesh Developers New PAN.pdf10 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 architect's certificate FY23-24 OCT-MAR 24.pdf10 Jun 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM -2 Engineer's certificate FY 23-24 Oct to Mar 24.pdf10 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: GetUserDocumentFileContent.pdf10 Jun 2024
Certificates of CA (Form 3)File: Form - 3 Chirag Letter Head oct to mar 24 6Months Updated.pdf10 Jun 2024
Declaration in FORM BFile: FORM B New.pdf25 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 2A ENGINEER CERTIFICATE FOR QUALITY ASSURANCE (2).pdf25 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2A ENGINEER CERTIFICATE FOR QUALITY ASSURANCE (2).pdf25 Nov 2023
Certificates of CA (Form 3)File: FORM 3 with Sign.pdf25 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Annual Report with Sign.pdf25 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2A ENGINEER CERTIFICATE FOR QUALITY ASSURANCE.pdf21 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2A ENGINEER CERTIFICATE FOR QUALITY ASSURANCE.pdf21 Nov 2023
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD.pdf21 Nov 2023
Disclosure of sold/ booked inventoryFile: XX.pdf21 Nov 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM -2 Engineer's certificate FY 23-24 Apr to Sep 23.pdf2 Nov 2023
Certificates of CA (Form 3)File: FORM -3 CA Certificate.pdf2 Nov 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 architect's certificate FY23-24 APR-SEP 23.pdf26 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Annual Audit Report of Statutory CA (Form 5) (FY 2022-23).pdf23 Oct 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: C Wing OC.pdf23 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 architect's certificate FY22-23 JAN-MAR 23.pdf25 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM -2 Engineer's certificate FY 22-23 JAN to MAR 23.pdf25 May 2023
Certificates of CA (Form 3)File: FORM -3 CA Certificate.pdf25 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 2021 - 22.pdf24 Mar 2023
Certificates of CA (Form 3)File: FORM -3 CA July to Sep 2022.pdf31 Jan 2023
Certificates of CA (Form 3)File: FORM -3 CA Oct to Dec 2022.pdf31 Jan 2023
PAN CardFile: Prathmesh Developers New PAN.pdf24 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 Architect Certificate 2022-23 July to Sep 2022 Quarterly.pdf24 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 Architect Certificate 2022-23 Oct to Dec 2022 Quarterly.pdf24 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 Engineer Certificate 2022-23 July to Sep 2022 Quarterly.pdf24 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 Engineer Certificate 2022-23 Oct to Dec 2022 Quarterly.pdf24 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Annual Audit Report of Statutory CA (Form 5) (FY 2021-22).pdf24 Jan 2023
PAN CardFile: Prathmesh Developers New PAN.pdf8 Jul 2022
Commencement Certificates / NA Order for plotted developmentFile: CC -1.pdf8 Jul 2022
Commencement Certificates / NA Order for plotted developmentFile: New CC.pdf8 Jul 2022
Declaration about Commencement CertificateFile: Declaration about Commencement Certificate.pdf8 Jul 2022
CERSAI detailsFile: CERSAI Search Report - MAHARERA.pdf8 Jul 2022
Certificates of CA (Form 3)File: 973.pdf8 Jul 2022
Certificates of CA (Form 3)File: 964.pdf8 Jul 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 Architect Certificate 2021-22.pdf7 Jul 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 Architect Certificate 2022-23 Apr to June 2022 Quarterly.pdf7 Jul 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 Engineer Certificate 2021-22.pdf7 Jul 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 Engineer Certificate 2022-23 Apr to June 2022 Quarterly.pdf7 Jul 2022
Certificates of CA (Form 3)File: Form 3 CA Certificate FY 2017-18.pdf7 Jul 2022
Certificates of CA (Form 3)File: Form 3 CA Certificate FY 2018-19.pdf7 Jul 2022
Certificates of CA (Form 3)File: Form 3 CA Certificate FY 2019-20.pdf7 Jul 2022
Certificates of CA (Form 3)File: Form 3 CA Certificate FY 2020-21.pdf7 Jul 2022
Proforma of Allotment letterFile: Draft Sale Agreement.pdf14 Mar 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 2018-19.pdf28 Feb 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 2019-20.pdf28 Feb 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 2020-21.pdf28 Feb 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 Engineer Certificate.pdf28 Feb 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 Engineer Certificate 2020-21.pdf28 Feb 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Annual Audit Report of Statutory CA (Form 5) (FY 2018-19).pdf22 Feb 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Annual Audit Report of Statutory CA (Form 5) (FY 2019-20).pdf22 Feb 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Annual Audit Report of Statutory CA (Form 5) (FY 2019-20).pdf22 Feb 2022

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 24 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep TANISHQ RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kurla6,700+ in Mumbai Suburban

2 kmTANISHQ RESIDENCYCompleted 135Lapsed / revoked 107Other 137Dot size: filed unitsN

Filed coordinates, straight-line distance. 379 registered projects within 2 km.

Builder: PRATHAMESH DEVELOPERS

PRATHAMESH DEVELOPERS has 2 registrations on MahaRERA, including TANISHQ RESIDENCY and THE CITY SCAPE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that TANISHQ RESIDENCY shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if TANISHQ RESIDENCY is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of TANISHQ RESIDENCY?

The registered promoter entity is PRATHAMESH DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in TANISHQ RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for TANISHQ RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at TANISHQ RESIDENCY?

The professionals named in the filing: Chartered Accountant: CHIRAG PATEL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in TANISHQ RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About TANISHQ RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save TANISHQ RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.