Home / Browse projects / Nashik, Maharashtra / SUYOJIT VIRIDIAN VALLIS - PULSATION PHASE - I

Registration lapsed No litigation declared Commercial project

SUYOJIT VIRIDIAN VALLIS - PULSATION PHASE - I

By SUN INFRASTRUCTURES PVT LTD

RG-MH-13564 · RERA P51600026037 · Last updated on MahaRERA portal: 7 Mar 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 28 months past the filed date
  • 3 complaints at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Jun 2024Possession promised28 months past this date
1 of 11Construction stages donefurthest along: Basement (if any), 25%
3Complaints at MahaRERAon this registration
Jump to the 28 documents Report an error

SUYOJIT VIRIDIAN VALLIS - PULSATION PHASE - I is a Commercial project by SUN INFRASTRUCTURES PVT LTD in Nashik, Maharashtra, registered with MahaRERA as P51600026037 on 11 Aug 2020. Possession was promised by 29 Jun 2024 and is now 28 months past that date. The completion date has moved by 12 months from the original filing. 3 complaints are on record with the regulator.

At a glance

Project

  • NameSUYOJIT VIRIDIAN VALLIS - PULSATION PHASE - I
  • TypeCommercial
  • Location
    • Upper Savarkar Nagar
    • Adjoining to Goda Park
    • Gangapur Road
    • Nashik
    • Gangapur Road
    • Nashik (M Corp.)
    • Nashik
    • 422013
  • Pincode422013
  • RERA no.P51600026037
  • ReraGenie IDRG-MH-13564

Builder

  • NameSUN INFRASTRUCTURES PVT LTD
  • Entity typeCompany
  • DirectorsANANT KESHAV RAJEGAONKAR, BITTAL MANGILAL SINGHI
  • Other registrations23 more →
  • Completed3 of 24
  • No longer live17 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

28 months past promisethis monthRegisteredAug 2020First promiseJun 2023Revised toJun 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on11 Aug 2020
  • Promised completion29 Jun 2024
  • Revised completionRevised to 29 Jun 2024 (originally 30 Jun 2023)
  • Buildings1 building record
  • Documents filed28 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PULSATION PHASE-INA51000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 7 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 25%.

PULSATION PHASE-I: 14% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)25%
Podiums (if any)0%
Plinth25%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 7 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,607 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityNashik Municipal Corporation
Permissible FSI2200.0
Proposed, not sanctioned2,200 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchVIRAJ CORNER, CANADA CORNER, NASHIK

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAnant Technocrats Pvt Ltd
ArchitectAnant Rajegaokar
EngineerShnghvi and Associates consultants Pvt Ltd
EngineerRajendra Patil
Chartered AccountantDeshmukh Jan and Associates
Chartered AccountantDeshamukh Jain & Associates
PartnerRole in project
SUN INFRASTRUCTURES PVT LTD-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51600017319Jun 2023 → Jun 2024

Reason as filed by the promoterDear Sir, With reference to above mentioned project, due to certain difficulties encountered by the contactors engaged for the construction of subject project the construction could not be completed within the period stipulated in MahaRera i.e. JUNE-2023. Hence we have changed the contactor who has taken up the remaining construction work in hand. However due to sharp rise in construction costs delayed the progress of the project and heavy rains in Nashik the progress of said work is presently slow. Hence extension for project completion is hereby requested which may kindly be granted. Thankin

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC12502597Dhiraj Jayvantrao DeshmukhDhiraj Jayvantrao Deshmukh28/07/2025
CC12601685RUPESH PRAKASHCHANDRA GUJRATHISUN INFRASTRUCTURES PVT LTD24/03/2026
CC12600677Dhiraj Jayvantrao DeshmukhSUN INFRASTRUCTURES PVT LTD05/02/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 8 Aug 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Aug 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Aug 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Aug 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed28

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM-2 ENGINEER CERTIFICATE SUYOJIT V V PULSATION.pdf7 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: ANNUAL REPORT CA REG PUL.pdf7 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTS CERTIFICATE PULSATION.pdf5 Oct 2023
Disclosure of sold/ booked inventoryFile: BOOKED INVENORY S V V PULSATION PHASE.pdf5 Oct 2023
Disclosure of sold/ booked inventoryFile: DISCORLSURE OF SOLD PULSATION PHASE.pdf7 Sep 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: ANNUAL REPORT PULSATION.pdf10 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: S V V PULSATION001.pdf11 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: SVV -Pulsation001.pdf30 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM -2A S V V PALSATION001.pdf9 Aug 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: S V V PULSATION.pdf28 May 2022
OtherFile: FORM -2A SUYOJIT V V PULSATION-compressed.pdf22 Feb 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM -2A SUYOJIT V V PULSATION-compressed.pdf29 Jan 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5-compressed.pdf1 Dec 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality Certificate suyojit v v PULASATION.pdf15 Nov 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: pulsation_compressed.pdf5 Aug 2021
Disclosure of sold/ booked inventoryFile: Pulsation - compressed.pdf3 Aug 2021
Layout approvalFile: PLAN.pdf8 Aug 2020
Building plan approvalFile: PLAN.pdf8 Aug 2020
Copy of the legal title reportFile: VV Title Report- 27-07-2017.pdf8 Aug 2020
Details of encumbrancesFile: ENCUBRANCE DETAILS PULSATION.pdf8 Aug 2020
Copy of Layout Approval (in case of layout)File: PLAN.pdf8 Aug 2020
Building Plan Approval / NA Order for plotted developmentFile: PLAN.pdf8 Aug 2020
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT.pdf8 Aug 2020
Declaration in FORM BFile: Form B_compressed.pdf8 Aug 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_compressed.pdf8 Aug 2020
Proforma of Allotment letterFile: AGREEMTN Draft - 2020 - Pulsation.pdf8 Aug 2020
Status of ConveyanceFile: 7 12 EXTRACT.pdf8 Aug 2020
PAN CardFile: PAN- SUN.pdf6 Aug 2020

How this compares with Nashik

10%of Nashik projects moved their completion datethis one moved by 12 months
19%of Nashik registrations have lapsed or been cancelledthis one is among them

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SUYOJIT VIRIDIAN VALLIS - PULSATION PHASE - on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Gangapur Road4,100+ in Nashik

Builder: SUN INFRASTRUCTURES PVT LTD

SUN INFRASTRUCTURES PVT. LTD has 24 registrations on MahaRERA, including SUYOJIT ONE WORLD PHASE-I, RESIDENTIAL SECTOR and SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What does it mean that SUYOJIT VIRIDIAN VALLIS - PULSATION PHASE - I shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SUYOJIT VIRIDIAN VALLIS - PULSATION PHASE - I is delayed beyond 29 Jun 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SUYOJIT VIRIDIAN VALLIS - PULSATION PHASE - I?

The registered promoter entity is SUN INFRASTRUCTURES PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SUYOJIT VIRIDIAN VALLIS - PULSATION PHASE - I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SUYOJIT VIRIDIAN VALLIS - PULSATION PHASE - I?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SUYOJIT VIRIDIAN VALLIS - PULSATION PHASE - I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SUYOJIT VIRIDIAN VALLIS - PULSATION PHASE - I?

The professionals named in the filing: Architect: Anant Technocrats Pvt Ltd; Architect: Anant Rajegaokar; Engineer: Shnghvi and Associates consultants Pvt Ltd; Engineer: Rajendra Patil; Chartered Accountant: Deshmukh Jan and Associates; Chartered Accountant: Deshamukh Jain & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SUYOJIT VIRIDIAN VALLIS - PULSATION PHASE - I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SUYOJIT VIRIDIAN VALLIS - PULSATION PHASE - I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SUYOJIT VIRIDIAN VALLIS - PULSATION PHASE - to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.