Home / Browse projects / Nashik, Maharashtra / SUYOJIT VIRIDIAN VALLIS PHASE-III SECTOR B

Registered No litigation declared Commercial project

SUYOJIT VIRIDIAN VALLIS PHASE-III SECTOR B

By SUN INFRASTRUCTURES PVT LTD

RG-MH-14937 · RERA P51600033475 · Last updated on MahaRERA portal: 14 Apr 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 39 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Oct 2027Possession promisedmoved 39 months from the original
1 of 11Construction stages donefurthest along: Basement (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 37 documents Report an error

SUYOJIT VIRIDIAN VALLIS PHASE-III SECTOR B is a Commercial project by SUN INFRASTRUCTURES PVT LTD in Nashik, Maharashtra, registered with MahaRERA as P51600033475 on 22 Feb 2022. Possession is promised by 31 Oct 2027. The completion date has moved by 39 months from the original filing.

At a glance

Project

  • NameSUYOJIT VIRIDIAN VALLIS PHASE-III SECTOR B
  • TypeCommercial
  • Location
    • UPPER SAVARKAR NAGAR
    • GANGAPUR ROAD
    • NASHIK
    • Nashik (M Corp.)
    • Nashik
    • 422013
  • Pincode422013
  • RERA no.P51600033475
  • ReraGenie IDRG-MH-14937

Builder

  • NameSUN INFRASTRUCTURES PVT LTD
  • Entity typeCompany
  • CINU45200MH1996PTC099201
  • CIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • DirectorsANANT KESHAV RAJEGAONKAR, ANIL BHAVARLAL JAIN
  • Other registrations23 more →
  • Completed3 of 24
  • No longer live17 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

this monthRegisteredFeb 2022First promiseJul 2024Revised toOct 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on22 Feb 2022
  • Promised completion31 Oct 2027
  • Revised completionRevised to 31 Oct 2027 (originally 31 Jul 2024)
  • Buildings1 building record
  • Documents filed37 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
B1 SUYOJIT RIVER SQUARENA40000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 14 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.

B1 SUYOJIT RIVER SQUARE: 9% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 14 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes10%
Water SupplyNoNot applicable
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsYes10%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes10%
Aggregate area of recreational Open SpaceYes10%
Open ParkingYes10%

Parking filed152

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots152
Closed/Covered1
Open Space151

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area8,600 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI8729.0
Proposed, not sanctioned8,729 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchL-3G-3, SUYOJIT TRADE CENTER, SHARANPUR ROAD, NASHIK

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectANANT TECHNOCRATS PVT LTD
EngineerSHNGHVI AND ASSOCIATES CONSULTANTS PVT LTD
Chartered AccountantDESHMUKH JAIN AND ASSOCIATES
PartnerRole in project
SUN INFRASTRUCTURES PVT LTD-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51600025467Jul 2024 → Oct 2027

Reason as filed by the promoterRespected Sir, We, Sun Infrastructures Pvt Ltd., as Promoter of Suyojit Viridian Vallis Phase-III B1- Sector registered under MahaRera at Registration No. P51600033475. As regards delayed status of Construction it is submitted that we have given priority to repayment of construction loans of banks to avoid attachment from them. Since we have repaid a significant part of such loans we are now giving priority to complete remaining completion of the project speedily and will be able to complete the same within the extended period to be granted by MahaRera. We request you to kindly grant us extens

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jan 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Jan 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 9 Feb 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Jan 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Oct 2027

Documents filed37

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: ANNUAL REPORT CA REG NO RIVER VISTA.pdf14 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5B1.pdf14 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24).pdf13 Apr 2025
Declaration in FORM BFile: AFFIDAVIT B SECTOR.pdf13 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architects certificate sector B1001.pdf13 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineers certificate sector B1001.pdf13 Mar 2025
Disclosure of sold/ booked inventoryFile: SECTOR B1001.pdf13 Mar 2025
Other - TechnicalFile: BALANCE WORK.pdf13 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 B SECROR.pdf13 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM-2 ENGINEER CERTIFICATE SUYOJIT V V SECTOR B.pdf7 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITCT B1.pdf11 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA B1_compressed.pdf11 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER B1.pdf11 Feb 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD B1.pdf11 Feb 2025
Declaration in FORM BFile: FORMB B SECTOR.pdf10 Dec 2024
Disclosure of sold/ booked inventoryFile: SUYOJIT RIVER SQUARE S V V SECTOR B1001.pdf6 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: SVV-PHASW-3- SECTOR- B001.pdf23 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM S V V PHASE -III SECTOR B.pdf11 Feb 2023
Declaration about Commencement CertificateFile: Declaration about Commencement.pdf16 Feb 2022
Declaration about Commencement CertificateFile: BUILDING B_compressed.pdf11 Feb 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_11zon.pdf11 Feb 2022
Building plan approvalFile: BUILDING B_compressed.pdf9 Feb 2022
Building Plan Approval / NA Order for plotted developmentFile: BUILDING B_compressed.pdf9 Feb 2022
Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf5 Feb 2022
Building plan approvalFile: B1compressed.pdf28 Jan 2022
Layout approvalFile: B1compressed.pdf28 Jan 2022
PAN CardFile: PAN SUNG.pdf28 Jan 2022
Copy of the legal title reportFile: legal title report.pdf28 Jan 2022
Details of encumbrancesFile: Document 55 (1).pdf28 Jan 2022
Copy of Layout Approval (in case of layout)File: B1compressed.pdf28 Jan 2022
Building Plan Approval / NA Order for plotted developmentFile: B1compressed.pdf28 Jan 2022
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf28 Jan 2022
Declaration in FORM BFile: dECLARATION FORM B.pdf28 Jan 2022
CERSAI detailsFile: CERSAI_Search_Report_200225408532_For_Asset_Based_Search_07_12_2021_10_41_53_355.pdf28 Jan 2022
CERSAI detailsFile: CERSAI_Search_Report_200225408557_For_Asset_Based_Search_07_12_2021_10_42_12_173.pdf28 Jan 2022
CERSAI detailsFile: CERSAI_Search_Report_200225408616_For_Asset_Based_Search_07_12_2021_10_42_49_273.pdf28 Jan 2022
Proforma of Allotment letterFile: AGREEMTNT DRAFT B1.pdf28 Jan 2022

How this compares with Nashik

10%of Nashik projects moved their completion datethis one moved by 39 months
19%of Nashik registrations have lapsed or been cancelledthis one is on the register

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SUYOJIT VIRIDIAN VALLIS PHASE-III SECTOR B on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near UPPER SAVARKAR NAGAR, GANGAPUR ROAD, NASHIK4,100+ in Nashik

Builder: SUN INFRASTRUCTURES PVT LTD

SUN INFRASTRUCTURES PVT. LTD has 24 registrations on MahaRERA, including SUYOJIT ONE WORLD PHASE-I, RESIDENTIAL SECTOR and SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What are my rights if SUYOJIT VIRIDIAN VALLIS PHASE-III SECTOR B is delayed beyond 31 Oct 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SUYOJIT VIRIDIAN VALLIS PHASE-III SECTOR B?

The registered promoter entity is SUN INFRASTRUCTURES PVT LTD, a company as per the filing. Its CIN U45200MH1996PTC099201 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SUYOJIT VIRIDIAN VALLIS PHASE-III SECTOR B?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SUYOJIT VIRIDIAN VALLIS PHASE-III SECTOR B?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SUYOJIT VIRIDIAN VALLIS PHASE-III SECTOR B?

The professionals named in the filing: Architect: ANANT TECHNOCRATS PVT LTD; Engineer: SHNGHVI AND ASSOCIATES CONSULTANTS PVT LTD; Chartered Accountant: DESHMUKH JAIN AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SUYOJIT VIRIDIAN VALLIS PHASE-III SECTOR B?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SUYOJIT VIRIDIAN VALLIS PHASE-III SECTOR B. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SUYOJIT VIRIDIAN VALLIS PHASE-III SECTOR B to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.