Home / Browse projects / Nashik, Maharashtra / SUYOJIT VIRIDIAN VALLIS-PHASE 1 F AND G SECTOR VIRENS

Registration lapsed No litigation declared Residential / Group Housing project

SUYOJIT VIRIDIAN VALLIS-PHASE 1 F AND G SECTOR VIRENS

By SUN INFRASTRUCTURES PVT LTD

RG-MH-01240 · RERA P51600003674 · Last updated on MahaRERA portal: 6 Mar 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 25 months past the filed date
  • Completion date moved by 54 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Sep 2024Possession promised25 months past this date
8 of 33Construction stages doneacross 3 buildings; furthest along: Slabs of Super Structure, 90%
3 of 21Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 65 documents Report an error

SUYOJIT VIRIDIAN VALLIS-PHASE 1 F AND G SECTOR VIRENS is a Residential / Group Housing project by SUN INFRASTRUCTURES PVT LTD in Nashik, Maharashtra, registered with MahaRERA as P51600003674 on 6 Aug 2017. Possession was promised by 30 Sep 2024 and is now 25 months past that date. The completion date has moved by 54 months from the original filing. 18 of the 21 units on this registration are recorded sold or booked, and 8 of 33 construction stages are filed complete.

At a glance

Project

  • NameSUYOJIT VIRIDIAN VALLIS-PHASE 1 F AND G SECTOR VIRENS
  • TypeResidential / Group Housing
  • Location
    • GANGAPUR ROAD
    • Suyojit Viridian Vallis
    • Upper Savarkar Nagar
    • Adjoining to Goda Park
    • Off Gangapur Road
    • Nashik
    • Nashik
    • 422013
  • Pincode422013
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51600003674
  • ReraGenie IDRG-MH-01240

Builder

  • NameSUN INFRASTRUCTURES PVT LTD
  • Entity typeCompany
  • Managing DirectorsAnant Keshav Rajegaonkar, ANIL BHAVARLAL JAIN
  • Other registrations23 more →
  • Completed3 of 24
  • No longer live17 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

25 months past promisethis monthRegisteredAug 2017First promiseMar 2020Revised toSep 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on6 Aug 2017
  • Promised completion30 Sep 2024
  • Revised completionRevised to 30 Sep 2024 (originally 31 Mar 2020)
  • Buildings3 building records
  • Documents filed65 files

Current status

86%18 of 21 units booked

Figures as on 6 Mar 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Villas F Sector R1 to R7NA55707
Villas G Sector R8 to R13NA55606
Villas G Sector R14 to R21NA55808

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 6 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Slabs of Super Structure, at 90%.

Villas F Sector R1 to R754%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure90%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks86%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.15%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villas G Sector R8 to R1357%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises15%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Villas G Sector R14 to R2141%
ActivityProgress
Excavation100%
Basement (if any)90%
Podiums (if any)0%
Plinth90%
Stilt Floor0%
Slabs of Super Structure85%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises30%
Sanitary Fittings within the flats / premises10%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks25%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.25%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 6 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes40%
Water SupplyYes20%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes40%
Street LightingYes40%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes10%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes10%
Aggregate area of recreational Open SpaceYes50%
Open ParkingYes0%

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area12,333 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on1 Jun 2026

Approvals and building plan

Sanctioning authorityNASHIK MUNICIPAL CORPORATION
Permissible FSI8250.8
Proposed, not sanctioned8,106 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShop No 13/14, Viraj Corner Complex, Sharanpur Road, Canada Corner Nashik 422002

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAnant Technocrats Pvt Ltd
EngineerShanghvi and Associates Consultants Private Limited
Chartered Accountant112958
Chartered AccountantCA Ashok S Lohade
PartnerRole in project
SUN INFRASTRUCTURES PVT LTD-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51600006003Mar 2020 → Mar 2021

Reason as filed by the promoterIn this connection, we have to state that we have not yet received permission form MSEB, Nashik Municipal Authority for water supply, drainage system, Fire System for completion of project within time. Hence we could not complete the project as per schedule and the same is delayed for the reasons beyond over control. In this connection kindly refer to GR of Government of India, Ministry of Finance, dt 19/02/2020 wherein it is stated that the ground on which we are seeking extension are considered as Force Majeure grounds and hence extension may kindly granted. Since the outbreak of pendemic ‘C

EXT51600011659Mar 2020 → Jun 2023

Reason as filed by the promoterRespected Sir, We, hereby apply for extension u/s 7(3) of the registered project bearing vide no P51600003674 As prescribed under circular no 0717019 dated 8 Feb 2019, the consent of the 63.63% allottees is enclosed herewith. Hence, you are kindly requested to grant project extension. Thanking you, Yours faithfully, Suyojit Infrastructures Pvt. Ltd

EXT51600017531Mar 2020 → Sep 2024

Reason as filed by the promoterTo The MahaRERA. Sub: Extension to the project bearing Registration No. P51600003674 We, hereby apply for extension u/s 7(3) of the registered project bearing vide no P51600003674 As prescribed under circular no 0717019 dated 8 Feb 2019, the consent of the 51% allottees is enclosed herewith. Thanking you, For Sun Infrastructures Pvt. Ltd,

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 1 Oct 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed65

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM-2 ENGINEER CERTIFICATE SUYOJIT VILLA.pdf6 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM-2 ENGINEER CERTIFICATE SUYOJIT VILLA.pdf6 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS CERTIFICATE S V V PHASE VILLA.pdf5 Oct 2023
Disclosure of sold/ booked inventoryFile: BOOKED INVENORY VILLA.pdf5 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: ANNUAL REPORT VILLA.pdf10 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: S V V PHASE -1 VILLA.pdf11 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: SVV -Phase-1- F AND G VIRENS001.pdf7 Dec 2022
Form 2AFile: FORM -2A S V V PHASE-3 SECTOR G-4001.pdf9 Aug 2022
Form 2AFile: S V V PHASE 1 F G VIRENS.pdf28 May 2022
CERSAI detailsFile: CERSAI_Search_Report_200225408616_For_Asset_Based_Search_07_12_2021_10_42_49_273.pdf29 Mar 2022
CERSAI detailsFile: CERSAI_Search_Report_200225408557_For_Asset_Based_Search_07_12_2021_10_42_12_173.pdf29 Mar 2022
CERSAI detailsFile: CERSAI_Search_Report_200225408532_For_Asset_Based_Search_07_12_2021_10_41_53_355.pdf29 Mar 2022
Disclosure of sold/ booked inventoryFile: Booked invenory Valla.pdf29 Mar 2022
Form 2AFile: Quality Certificate suyojit v v Phase-1, VILLA.pdf8 Nov 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: SUN INFRA BY SUYOJIT V V RERA CARIFICATE PHASE-1 F VIRENS.pdf19 Oct 2021
Disclosure of sold/ booked inventoryFile: Villa.pdf14 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: VILLA.pdf9 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: VILLA.pdf7 Aug 2021
Declaration about Commencement CertificateFile: Villla.pdf8 Jul 2021
Form 2AFile: VILLA.pdf2 Jun 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: VILLA.pdf2 Jun 2021
Form 2AFile: VILLA.pdf3 Apr 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Villa.pdf27 Mar 2021
Form 2AFile: SVV PHASE 1F G VIRENS001.pdf26 Jun 2020
Form 2AFile: VALLIS PHASE 1F.pdf23 Jan 2020
Form 2AFile: suyojit varridian vallis phase 1F G VIRENS.pdf25 Oct 2019
Commencement Certificates / NA Order for plotted developmentFile: commencement.pdf1 Oct 2019
Form 2AFile: VILLA07172019163326.pdf19 Jul 2019
Form 2AFile: vILLAS.pdf2 Apr 2019
Form 2AFile: FORM 2A VILLAS.pdf15 Jan 2019
Certificates of CA (Form 5)File: CA Certificate Form 5 Villas.pdf2 Oct 2018
Layout approvalFile: 3 Row villa 1 to 6R.pdf30 Jul 2017
Building plan approvalFile: 4 Row Villa 8 to 11 and 14 to 21R.pdf30 Jul 2017
Building plan approvalFile: 1- Row villa-12 and 13R.pdf30 Jul 2017
Building plan approvalFile: ROW_HOUSE_NO_7.pdf30 Jul 2017
Building plan approvalFile: ROW_HOUSE_NO_12_13.pdf30 Jul 2017
Copy of the legal title reportFile: VV Title Report- 27-07-2017.pdf30 Jul 2017
Details of encumbrancesFile: ENCUMBRANCES DETAILS.pdf30 Jul 2017
Details of encumbrancesFile: Index-II- canara bank.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: 3 Row villa 1 to 6R.pdf30 Jul 2017
Building Plan Approval (IOD)File: 4 Row Villa 8 to 11 and 14 to 21R.pdf30 Jul 2017
Building Plan Approval (IOD)File: 1- Row villa-12 and 13R.pdf30 Jul 2017
Building Plan Approval (IOD)File: ROW_HOUSE_NO_7.pdf30 Jul 2017
Building Plan Approval (IOD)File: ROW_HOUSE_NO_12_13.pdf30 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: plinth completion certificate-NMC.pdf30 Jul 2017
Declaration in FORM BFile: FORM B.pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Villa Certificate-30-07.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certiciate -villas.pdf30 Jul 2017
Certificates of CA (Form 3)File: CA Certificate- 29-07-2017.pdf30 Jul 2017
Proforma of Allotment letterFile: DECLARATION AGREEMENT AND ALLOTMENT.pdf30 Jul 2017
OtherFile: 6821.pdf30 Jul 2017
OtherFile: 6822.pdf30 Jul 2017
OtherFile: 8125.pdf30 Jul 2017
OtherFile: 8126.pdf30 Jul 2017
OtherFile: 8127.pdf30 Jul 2017
OtherFile: Index-II 10868 sun.pdf30 Jul 2017
OtherFile: FINAL ALL AMINITIES.pdf30 Jul 2017
OtherFile: VILLAS AMINITY.pdf30 Jul 2017
Building plan approvalFile: 3 Row villa 1 to 6R.pdf24 Jul 2017
Building plan approvalFile: 2 Row Villa 7R.pdf24 Jul 2017
PAN CardFile: PAN Sun Infrastructures Pvt Ltd.pdf24 Jul 2017
Building Plan Approval (IOD)File: 3 Row villa 1 to 6R.pdf24 Jul 2017
Building Plan Approval (IOD)File: 2 Row Villa 7R.pdf24 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate VV.pdf24 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Renewal of Commencement Cert- NMC-28-10-16.pdf24 Jul 2017

How this compares with Nashik

86%of this project is bookeddistrict median 17%
10%of Nashik projects moved their completion datethis one moved by 54 months
19%of Nashik registrations have lapsed or been cancelledthis one is among them

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SUYOJIT VIRIDIAN VALLIS-PHASE 1 F AND G SECT on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Suyojit Viridian Vallis, Upper Savarkar Nagar, Adjoining to Goda Park, Off Gangapur Road, Nashik4,100+ in Nashik

2 kmSUYOJIT VIRIDIAN VALLIS-Completed 27Lapsed / revoked 16Other 37Dot size: filed unitsN

Filed coordinates, straight-line distance. 80 registered projects within 2 km.

Builder: SUN INFRASTRUCTURES PVT LTD

SUN INFRASTRUCTURES PVT. LTD has 24 registrations on MahaRERA, including SUYOJIT ONE WORLD PHASE-I, RESIDENTIAL SECTOR and SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What does it mean that SUYOJIT VIRIDIAN VALLIS-PHASE 1 F AND G SECTOR VIRENS shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SUYOJIT VIRIDIAN VALLIS-PHASE 1 F AND G SECTOR VIRENS is delayed beyond 30 Sep 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SUYOJIT VIRIDIAN VALLIS-PHASE 1 F AND G SECTOR VIRENS?

The registered promoter entity is SUN INFRASTRUCTURES PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SUYOJIT VIRIDIAN VALLIS-PHASE 1 F AND G SECTOR VIRENS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SUYOJIT VIRIDIAN VALLIS-PHASE 1 F AND G SECTOR VIRENS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SUYOJIT VIRIDIAN VALLIS-PHASE 1 F AND G SECTOR VIRENS?

The professionals named in the filing: Architect: Anant Technocrats Pvt Ltd; Engineer: Shanghvi and Associates Consultants Private Limited; Chartered Accountant: 112958; Chartered Accountant: CA Ashok S Lohade. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SUYOJIT VIRIDIAN VALLIS-PHASE 1 F AND G SECTOR VIRENS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SUYOJIT VIRIDIAN VALLIS-PHASE 1 F AND G SECTOR VIRENS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SUYOJIT VIRIDIAN VALLIS-PHASE 1 F AND G SECT to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.