ReraGenieLog inGet a buyer report

Home / Browse projects / Nashik, Maharashtra / SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO

Registered No litigation declared Residential / Group Housing project

SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO

By SUN INFRASTRUCTURES PVT LTD

RG-MH-01223 · RERA P51600003685 · Last updated on MahaRERA portal: 6 Mar 2025

Source: official MahaRERA filing

Red flags

  • 6 complaints at MahaRERA
  • Completion date moved by 69 months
  • 3 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 69 months from the original
8 of 22Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 27%
6Complaints at MahaRERAon this registration
Jump to the 64 documents Report an error

SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO is a Residential / Group Housing project by SUN INFRASTRUCTURES PVT LTD in Nashik, Maharashtra, registered with MahaRERA as P51600003685 on 6 Aug 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 69 months from the original filing. 6 complaints are on record with the regulator.

At a glance

Project

  • NameSUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO
  • TypeResidential / Group Housing
  • Location
    • Maharashtra
    • Upper Savarkar Nagar
    • Gangapur Road
    • Nashik
    • Nashik
    • 422013
  • Pincode422013
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51600003685
  • ReraGenie IDRG-MH-01223

Builder

  • NameSUN INFRASTRUCTURES PVT LTD
  • Entity typeCompany
  • Managing DirectorsANANT KESHAV RAJEGAONKAR, ANIL BHAVARLAL JAIN
  • DirectorBITTAL MANGILAL SINGHI
  • Other registrations23 more →
  • Completed3 of 24
  • No longer live17 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2017First promiseMar 2021Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on6 Aug 2017
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Mar 2021)
  • Buildings2 building records
  • Documents filed64 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AMARANTH 1 to 7 and 9 to 12 FloorsNA150000
AMARANTH 8th FloorNA10000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 6 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 27%.

AMARANTH 1 to 7 and 9 to 12 Floors42%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure27%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises5%
Sanitary Fittings within the flats / premises10%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks16%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
AMARANTH 8th Floor36%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 6 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes70%
Water SupplyYes20%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes40%
Street LightingYes40%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes10%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceYes50%
Open ParkingYes0%

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,467 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI17421.54
Proposed, not sanctioned15,943 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShop No 13 /14 Viraj Complex, Sharanpur Road, Canada Corner Nashik 422002

Certifying professionals and partners

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

PartnerRole in project
SUN INFRASTRUCTURES PVT LTD-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51600010028Mar 2021 → Mar 2022

Reason as filed by the promoterDue to continuous onslaught of the 1st & 2nd wave of Covid-19 Pandemic, the supply chain of Construction material is badly affected. In addition, the 3rd wave of Covid-19 is apprehended very soon as per global anticipation. This has frightened the labor force resulting in lockdown, non-availability of construction labor who have already migrated to their native place & have not returned as yet. Non-availability of transport, conveyance & logistics are other hurdles in completion of our subject projects by stipulated dates. These difficulties have already been put forth by SRO Members, before t

EXT51600012635Mar 2021 → Mar 2024

Reason as filed by the promoterDear Sir/ Ma'am, We hereby apply for extension u/s 7 (3) of the registered project bearing vide no. P51600003685. As prescribed under circular no. 0717019 dated 8 Feb 2019. the consent of 51% allottees is enclosed herewith. Kindly request to grant extension for this project. Thanking you, Yours faithfully, For Sun Infrastructures Pvt. Ltd.

EXT51600024266Mar 2021 → Dec 2026

Reason as filed by the promoterTo, MahaRera, Subject - Extension to the proejct bearing Registration No. P51600003685. Respected Sir, We, hereby apply for extension u/s 7(3) of the registered project bearing vide No. P51600003685, As prescribed under circular No. 0717019, dt. 8/02/2019, the consent of the 51% allottes is enclosed herewith. The project is not completed within time specified in registration due to banking issues, financial crunch and low booking response in the project as projected, We need addional time to complete the pending development work in the project Thanking you, Yours faithfully For Sun Infrastruct

Complaints filed with MahaRERA6

Case no.ComplainantRespondentFiled
CC001000000000027AMIT YESHWANT GOVILKARANANT KESHAV RAJEGAONKAR21/11/2017
CC001000000000049Amit GovilkarAnant Rajegaonkar12/04/2018
CC001000000000034Rajendra M SonarAnant Keshav Rajegaonkar25/12/2017
CC001000000000071Ramesh Uttamchand RamchandaniSun Infrastructure Private Limited26/11/2018
CC001000000020192Deepak Bhaiyaji MalewarSUN INFRASTRUCTURES PVT LTD03/08/2021
CC001000000040283JAYSHREE JITENDRA KADAMSUN INFRASTRUCTURES PVT LTD19/09/2022

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 1 Oct 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 1 Oct 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed64

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM-2 ENGINEER CERTIFICATE SUYOJIT D1.pdf6 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: ANNUAL REPORT CA REG D1.pdf6 Mar 2025
Form 2AFile: FORM-2A S V V PHASE-1 D1.pdf9 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: D1_compressed.pdf25 Dec 2023
Disclosure of sold/ booked inventoryFile: BOOKED INVENORY D1.pdf12 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: fORM 2 D1.pdf23 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: S V V PHASE-1 D1-OTIO001.pdf11 Feb 2023
Form 2AFile: SVV -Phase-1- D1 OTIO001.pdf7 Dec 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects certificate.pdf17 Nov 2022
Disclosure of sold/ booked inventoryFile: D1.pdf8 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: CA CERTIFICATE S V V- D1 R NO-3685001.pdf4 Oct 2022
Form 2AFile: FORM -2A S V V PHASE-1, D1 -OTIO001.pdf9 Aug 2022
Form 2AFile: S V V PHASE-1 D1 OTIO.pdf28 May 2022
Form 2AFile: FORM -2A SUYOJIT V V PHASE-II, D-1, AMARANTH.pdf29 Jan 2022
Form 2AFile: Quality Certificate suyojit v v Phase-1, D1-compressed.pdf8 Nov 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: SUN INFRA BY SUYOJIT V V RERA CARIFICATE PHASE-1 D-1.pdf30 Sep 2021
Form 2AFile: d1.pdf5 Aug 2021
Declaration about Commencement CertificateFile: D1.pdf8 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM- 5 SUYOJIT V V PHASE-I D1 OTIO001.pdf8 Jul 2021
Disclosure of sold/ booked inventoryFile: D1 SOLD UNSOLD.pdf3 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FROM 2A SUYOJIT INFRA LTD SUYOJIT VIRIDIAN V PHASE-1 D-1 AMARANT.pdf30 Jun 2021
Form 2AFile: D1.pdf1 Jun 2021
Form 2AFile: D1.pdf31 Mar 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: d1.pdf27 Mar 2021
Form 2AFile: D1.pdf30 Nov 2020
Form 2AFile: D2 AND D7 BUILDING001.pdf26 Jun 2020
Form 2AFile: D1.pdf23 Jan 2020
Form 2AFile: D-1.pdf25 Oct 2019
Building plan approvalFile: D-1_compressed.pdf1 Oct 2019
Building Plan Approval (IOD)File: D-1_compressed.pdf1 Oct 2019
Commencement Certificates / NA Order for plotted developmentFile: commencement.pdf1 Oct 2019
Form 2AFile: D-107172019164912.pdf19 Jul 2019
Form 2AFile: D-1.pdf2 Apr 2019
Form 2AFile: FORM 2A- D-1 f.pdf15 Jan 2019
Certificates of CA (Form 5)File: CA Certificate Form 5 D1.pdf2 Oct 2018
Layout approvalFile: D-1-Building Plan-R.pdf29 Jul 2017
Building plan approvalFile: D1.pdf29 Jul 2017
Copy of the legal title reportFile: VV Title Report- 27-07-2017.pdf29 Jul 2017
Details of encumbrancesFile: ENCUMBRANCES DETAILS D-1.pdf29 Jul 2017
Details of encumbrancesFile: Index-II- canara bank.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: D-1-Building Plan-R.pdf29 Jul 2017
Building Plan Approval (IOD)File: D1.pdf29 Jul 2017
Declaration in FORM BFile: FORM B.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Engineer Certificate.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf29 Jul 2017
Certificates of CA (Form 3)File: CA Certificate-final d1.pdf29 Jul 2017
Proforma of Allotment letterFile: DECLARATION AGREEMENT AND ALLOTMENT.pdf29 Jul 2017
OtherFile: plinth completion certificate-NMC.pdf29 Jul 2017
OtherFile: 6821.pdf29 Jul 2017
OtherFile: 6822.pdf29 Jul 2017
OtherFile: 8125.pdf29 Jul 2017
OtherFile: 8126.pdf29 Jul 2017
OtherFile: 8127.pdf29 Jul 2017
OtherFile: Index-II 10868 sun.pdf29 Jul 2017
OtherFile: Index-II 10869 sun - suyojit.pdf29 Jul 2017
OtherFile: SUYOJIT VIRIDIAN VALLIS AMENITIES- D1.pdf29 Jul 2017
OtherFile: VVAminity.pdf29 Jul 2017
Building plan approvalFile: D-1-Building Plan-R.pdf24 Jul 2017
Building plan approvalFile: d-1-parkingR.pdf24 Jul 2017
Building Plan Approval (IOD)File: D-1-Building Plan-R.pdf24 Jul 2017
Building Plan Approval (IOD)File: d-1-parkingR.pdf24 Jul 2017
PAN CardFile: PAN Sun Infrastructures Pvt Ltd.pdf23 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate VV.pdf23 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Renewal of Commencement Cert- NMC-28-10-16.pdf23 Jul 2017

How this compares with Nashik

10%of Nashik projects moved their completion datethis one moved by 69 months
19%of Nashik registrations have lapsed or been cancelledthis one is on the register

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OT on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Upper Savarkar Nagar, Gangapur Road, Nashik4,100+ in Nashik

2 kmSUYOJIT VIRIDIAN VALLIS-Completed 28Lapsed / revoked 18Other 36Dot size: filed unitsN

Filed coordinates, straight-line distance. 82 registered projects within 2 km.

Builder: SUN INFRASTRUCTURES PVT LTD

SUN INFRASTRUCTURES PVT. LTD has 24 registrations on MahaRERA, including SUYOJIT ONE WORLD PHASE-I, RESIDENTIAL SECTOR and SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What are my rights if SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO?

The registered promoter entity is SUN INFRASTRUCTURES PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

What should I check before booking in SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OTIO. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SUYOJIT VIRIDIAN VALLIS-PHASE 1-D1 SECTOR OT to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.