supreme emperor
RG-MH-11905 · RERA P99000004020 · Last updated on MahaRERA portal: 11 Nov 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 60 months past the filed date
- 5 complaints at MahaRERA
- Completion date moved by 22 months
- 2 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
supreme emperor is a Residential / Group Housing project by SUPRIYA JEETEN DUTT in Palghar, Maharashtra, registered with MahaRERA as P99000004020 on 7 Aug 2017. Possession was promised by 31 Oct 2021 and is now 60 months past that date. The completion date has moved by 22 months from the original filing. 5 complaints are on record with the regulator.
At a glance
Project
- Namesupreme emperor
- TypeResidential / Group Housing
- Location
- Pereria Square
- Behind Don Bosco School
- Juchandra
- Naigaon (E)
- Thane - 401208.
- Naigaon
- Vasai-Virar City (M Corp)
- Vasai
- Palghar
- 401208
- Pincode401208
- MapView location on Google Maps (as filed on RERA)
- RERA no.P99000004020
- ReraGenie IDRG-MH-11905
Builder
- NameSUPRIYA JEETEN DUTT
- Entity typeIndividual
- Declared earlier projects2 →
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on7 Aug 2017
- Promised completion31 Oct 2021
- Revised completionRevised to 31 Oct 2021 (originally 31 Dec 2019)
- Buildings5 building records
- Documents filed34 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Supreme Emperor Bldg No H1 80 | NA | 5 | 0 | 0 | 0 | 0 |
| Supreme Emperor bldg no H1 81 | NA | 5 | 0 | 0 | 0 | 0 |
| Supreme Emperor bldg no H1 82 | NA | 5 | 0 | 0 | 0 | 0 |
| Supreme Emperor bldg no H1 83 | NA | 5 | 0 | 0 | 0 | 0 |
| Supreme Emperor bldg no H1 84 | NA | 5 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building5
As on 11 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
40 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 95%.
Supreme Emperor Bldg No H1 8081%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 95% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Supreme Emperor bldg no H1 8181%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 95% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Supreme Emperor bldg no H1 8281%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 95% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Supreme Emperor bldg no H1 8381%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 95% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Supreme Emperor bldg no H1 8481%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 95% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 11 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 60% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ENCON |
| Engineer | Sanjay S Narang |
| Partner | Role in project |
|---|---|
| SUPRIYA JEETEN DUTT | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe Reason for seeking extension in completion date is due to the reason that Final finishing work like Flooring, Plumbing, and Installation of lift in the last two buildings i.e. H1-83 and H1- 84 are still pending. Plus compliances related to Occupation Certificates will take time. Hence we request you to approve the extension of time period for completing the said project till 30th June 2020.
Reason as filed by the promoterCOVID - 19 in all over India and Lockdown declared in India. Shortage of Labour and material i.e. only 50% percent Labour were available. The Project consists of Five buildings H1 80-84 is nearly completed except the following work i.e. 1) Internal Road and pathways are partly completed 2) Tree plantation is yet to be done 3) CCTV Cameras fitting is yet to be done 4) Occupation Certificate for all the Five buildings is yet to be obtained. Since the construction work of the Project consisting of five buildings has been completed and the Promoter is seeking extension for registration of upcoming
Complaints filed with MahaRERA5
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000001611 | mohd haneef | Supreme Construction | 04/11/2017 |
| CC006000000089859 | Mohammad Haneef | Supriya Jeeten Dutt | 11/07/2019 |
| CC006000000056563 | Sarita Mishra | Supriya Dutt | 20/01/2019 |
| CC006000000078326 | ABHISHEK ARORA | SUPRIYA DUTT | 03/03/2019 |
| CC006000000078798 | Meenakshi Anand | Supreme Construction One | 07/05/2019 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 7 Jan 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 29 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 29 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 28 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 27 Sep 2023
Documents filed34
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate on Completion of Project (Form 4)File: DOC-20241008.pdf | 11 Nov 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Commencement Certificate (Supreme Emperor).pdf | 27 Sep 2023 |
| PAN CardFile: Supriya Madam - Pancard new attested.pdf | 28 Jun 2023 |
| CERSAI detailsFile: Undertaking.pdf | 28 Jun 2023 |
| Deviation Report with respect to Allotment letterFile: Deviation Allotment.pdf | 28 Jun 2023 |
| Deviation Report with respect to model copy of AgreementFile: Deviation Agreement.pdf | 28 Jun 2023 |
| Details of encumbrances concerned to FinanceFile: AFFIDAVIT.pdf | 22 Jun 2023 |
| Details of encumbrances concerned to LegalFile: AFFIDAVIT.pdf | 22 Jun 2023 |
| Declaration about Commencement CertificateFile: DECLARATION OF COMMENCEMENT CERTIFICATE.pdf | 22 Jun 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf | 22 Jun 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2N.pdf | 22 Jun 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE OF INTEREST.pdf | 22 Jun 2023 |
| Proforma of Agreement for saleFile: PROFORMA ALLOTMENT AND AGREEMENT.pdf | 22 Jun 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: SEPERATE ACC.pdf | 22 Jun 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FY 2019-20 Certificate.pdf | 8 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FY 2019-20 Certificate.pdf | 8 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FY 2020-21 Certificate.pdf | 8 Feb 2023 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Registration Certificate.pdf | 3 Nov 2022 |
| Copy of the legal title reportFile: Title Certificates.pdf | 7 Jan 2021 |
| Details of Restarting of Construction work post lockdownFile: Letter dated 24-7-2020.pdf | 27 Jul 2020 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Certificate 17-18.pdf | 26 Dec 2019 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Certificate 18-19.pdf | 26 Dec 2019 |
| Building plan approvalFile: BlDG PLAN TYPE H1.pdf | 29 Jul 2017 |
| Layout approvalFile: approved development plan rera (pereira builder).pdf | 29 Jul 2017 |
| Details of encumbrancesFile: encumbrances certificate supreme emperor.pdf | 29 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: approved development plan rera (pereira builder).pdf | 29 Jul 2017 |
| Building Plan Approval (IOD)File: BlDG PLAN TYPE H1.pdf | 29 Jul 2017 |
| Certificates of CA (Form 3)File: CA Certificate rera final.pdf | 29 Jul 2017 |
| Copy of the legal title reportFile: title certificate.pdf | 28 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: cc 2003-ilovepdf-compressed.pdf | 28 Jul 2017 |
| Declaration in FORM BFile: AFFIDVAIT RERA.pdf | 28 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ARCHITECT CERTIFICATE RERA.pdf | 28 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE FORM 2 RERA.pdf | 28 Jul 2017 |
| Proforma of Allotment letterFile: Rera upload allotment agreement.pdf | 28 Jul 2017 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Status | Promised | Delivered |
|---|---|---|---|---|
| NIL | NIL | Completed | Jul 2017 | Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Palghar
Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.
Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 34 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep supreme emperor on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Naigaon3,200+ in Palghar
Filed coordinates, straight-line distance. 62 registered projects within 2 km.
Suraksha Smart City - Phase I
Conceptual Advisory Services LLP
The Great Western Mumbai
HOABL Impactum Land Private Limited
Suraksha Smart City - Phase II
Conceptual Advisory Services LLP
Suraksha Smart City - Phase III
Conceptual Advisory Services LLP
Rashmi Star City Phase 2
Rashmi Realty Builders Pvt Ltd
Agarwal Sky Heights
Shreenath Realtors
See every Palghar project, with the district possession charts
Builder: SUPRIYA JEETEN DUTT
SUPRIYA JEETEN DUTT has 1 registration on MahaRERA, including supreme emperor. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 2 past projects completed on time. Read the full track record. See more projects on the Palghar district page.
Frequently asked questions
What does it mean that supreme emperor shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if supreme emperor is delayed beyond 31 Oct 2021?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of supreme emperor?
The registered promoter entity is SUPRIYA JEETEN DUTT, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in supreme emperor?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against supreme emperor?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for supreme emperor?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at supreme emperor?
The professionals named in the filing: Architect: ENCON; Engineer: Sanjay S Narang. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in supreme emperor?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback