Home / Browse projects / Nashik, Maharashtra / Sunrise Tower
Sunrise Tower
By Akshay Vinod Tatiya And Pratik Prakash Badgujar
RG-MH-15547 · RERA P51600045705 · Last updated on MahaRERA portal: 14 Jul 2026
Source: official MahaRERA filing
Red flags
- Completion date moved by 6 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Sunrise Tower is a Others project by Akshay Vinod Tatiya And Pratik Prakash Badgujar in Nashik, Maharashtra, registered with MahaRERA as P51600045705 on 6 Jun 2022. The registration is recorded completed; possession was promised by 30 Jun 2026. The completion date has moved by 6 months from the original filing. 10 of the 22 units on this registration are recorded sold or booked, and 8 of 9 construction stages are filed complete.
At a glance
Project
- NameSunrise Tower
- TypeOthers
- Location
- Nashik Shiwar
- Nashik
- 422010
- Pincode422010
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51600045705
- ReraGenie IDRG-MH-15547
Builder
- NameAkshay Vinod Tatiya And Pratik Prakash Badgujar
- Entity typeOthers
- PartnersPratik Prakash Badgujar -, Akshay Vinod Tatiya -
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on6 Jun 2022
- Promised completion30 Jun 2026
- Revised completionRevised to 30 Jun 2026 (originally 31 Dec 2025)
- Buildings1 building record
- Documents filed108 files
Current status
Figures as on 14 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Sunrise Tower | NA | 9 | 8 | 21 | 1 | 22 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 14 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
8 of 9 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 0%.
Sunrise Tower: 89% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 14 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed78
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Sunrise Tower | NA | Rs 2.36 cr | Rs 1.80 cr |
Certifying professionals and partners8
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Lakshmi Manthan Shewale |
| Engineer | Prakash Shankar Badgujar |
| Engineer | Vishal Sitaram Bagul |
| Chartered Accountant | CA Paresh Sabadra |
| Chartered Accountant | RSPH & Associates |
| Chartered Accountant | Rahul P Mundada and Associates LLP |
| Chartered Accountant | P N Sabadra and Associates |
| Chartered Accountant | Milan C Lunawat & CO |
| Partner | Role in project |
|---|---|
| Akshay Vinod Tatiya And Pratik Prakash Badgujar | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoter1) The excavation work took more than expected as there was hard rock and we were forced to do manual work along with small machines with due care in such a way that there should not be vibrations in the residential area around the site which takes considerably more time than the conventional methods. 2) While excavation and lowering of water level we were supposed to take care since the project land is already surrounded by residential premises and therefore this activity went slowly and took time. 3) The area is which project is to be constructed and completed is entirely a residential area,
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 25 May 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 25 May 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 27 Jun 2026 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 27 Apr 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed108
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 108 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupational CertificateFile: FULL OCCUPANCY CERTIFICATE.pdf | 14 Jul 2026 |
| Occupational CertificateFile: Highlighted Plan.pdf | 14 Jul 2026 |
| Occupational CertificateFile: Form 1.pdf | 14 Jul 2026 |
| Occupational CertificateFile: Form 2.pdf | 14 Jul 2026 |
| Occupational CertificateFile: Form 3.pdf | 14 Jul 2026 |
| Occupational CertificateFile: Form 5.pdf | 14 Jul 2026 |
| Occupational CertificateFile: Form 2A.pdf | 14 Jul 2026 |
| Occupational CertificateFile: Disclosure of sold booked inventory.pdf | 14 Jul 2026 |
| Building plan approvalFile: Highlighted Plan.pdf | 27 Jun 2026 |
| Form 2A (FY 2025-2026)File: Form-2A-March-2026.pdf | 27 Jun 2026 |
| Withdrawal Update Form 1File: AR - March 26.pdf | 26 Jun 2026 |
| Withdrawal Update Form 2File: ER-March-26.pdf | 26 Jun 2026 |
| Withdrawal Update Form 3File: CA-March-26-Pratik -Akshay.pdf | 26 Jun 2026 |
| Form 2A (FY 2022-2023)File: Form 2A - March 23.pdf | 21 Mar 2026 |
| Form 2A (FY 2023-2024)File: Form 2A - March 24 .pdf | 21 Mar 2026 |
| Form 2A (FY 2024-2025)File: Form 2A - March 25.pdf | 21 Mar 2026 |
| Form 5 (FY 2022-2023)File: Pratik Badgujar RA 22-23 Final.pdf | 5 Feb 2026 |
| Form 5 (FY 2023-2024)File: RERA Audit 2023-24.pdf | 5 Feb 2026 |
| Withdrawal Update Form 1File: AR - Dec 25 Pratik badgujar .pdf | 28 Jan 2026 |
| Withdrawal Update Form 2File: ER PB DEC 25 (2).pdf | 28 Jan 2026 |
| Withdrawal Update Form 3File: CA Certificates Dec 25 (2).pdf | 28 Jan 2026 |
| Form 5 (FY 2024-2025)File: RERA Audit Report 24-25 Final.pdf | 24 Jan 2026 |
| Withdrawal Update Form 1File: AR JUNE 2025.pdf | 1 Jan 2026 |
| Withdrawal Update Form 1File: AR JUNE 2025.pdf | 1 Jan 2026 |
| Withdrawal Update Form 1File: AR CERT SEPT 25.pdf | 1 Jan 2026 |
| Withdrawal Update Form 2File: ER JUNE 2025.pdf | 1 Jan 2026 |
| Withdrawal Update Form 2File: ER JUNE 2025.pdf | 1 Jan 2026 |
| Withdrawal Update Form 2File: ER CERT SEPT 25.pdf | 1 Jan 2026 |
| Withdrawal Update Form 3File: CA JUNE 2025 .pdf | 1 Jan 2026 |
| Withdrawal Update Form 3File: CA JUNE 2025 .pdf | 1 Jan 2026 |
| Withdrawal Update Form 3File: CA CERT SEPT 25 .pdf | 1 Jan 2026 |
| Form 1File: AC AT DEC 24.pdf | 31 Jul 2025 |
| Form 2File: Akshay EC AT Dec 2024.pdf | 31 Jul 2025 |
| Form 3File: CA AT DEC24.pdf | 31 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Dec 24.pdf | 31 Jul 2025 |
| Form 1File: AR March 2025.pdf | 31 Jul 2025 |
| Form 2File: ER March 25.pdf | 31 Jul 2025 |
| Form 3File: CA March 2025.pdf | 31 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure.pdf | 31 Jul 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AC PB Jun24.pdf | 8 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AC PB sep24.pdf | 8 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final CA Cert June 24.pdf | 8 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final CA Cert Sept 24.pdf | 8 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EC PB JUNe24.pdf | 8 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EC PB Sep24.pdf | 8 May 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure - June 24.pdf | 12 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure - Sep 24.pdf | 12 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR PB September 2023.pdf | 20 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR PB Dec 2023.pdf | 20 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR PB March 2024.pdf | 20 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: AR PB June 2023.pdf | 20 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FINAL CA June 23.pdf | 20 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F CA sept 23.pdf | 20 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F CA Dec 23.pdf | 20 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F CA Mar 24.pdf | 20 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate sep23.pdf | 20 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Mar 24.pdf | 20 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: EC PB Dec 23.pdf | 20 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate june 23.pdf | 20 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure June23.pdf | 10 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure Sept 23.pdf | 10 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure March 24.pdf | 10 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure Dec 23.pdf | 10 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf | 10 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: RERA Audit 2023-24.pdf | 23 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Pratik Badgujar RA 22-23 Final.pdf | 8 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A.pdf | 25 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: UNSOLD 30-9-2022.pdf | 25 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: UNSOLD 31-12-2022.pdf | 25 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: UNSOLD 31-03-2023.pdf | 25 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 ARC C AT SEP22.pdf | 15 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2 ARC C AT DEC22.pdf | 15 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3 ARC C AT MAR23.pdf | 15 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4 ER Sep 22 AT.pdf | 15 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 5 ER Dec 22 AT.pdf | 15 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 6 ER Mar 23 AT.pdf | 15 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Arc Pb sep 22.pdf | 14 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2 Arc PB DEC22.pdf | 14 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3 Arc Pb March23.pdf | 14 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4 ER Cert Sep 22.pdf | 14 Jun 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nashik
Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.
Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 108 filed documents as one ZIP, foldered, with a manifest
Keep Sunrise Tower on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Nashik4,100+ in Nashik
Filed coordinates, straight-line distance. 104 registered projects within 2 km.
SHREE SATYANARAYAN ROONGTA FORUM
ROONGTA HOMES LLP
LIFE 360
VELOCITY INFRA PROJECTS
ARYAN'S LIFEONE
SHREE ARYAN BUILDERS AND DEVELOPERS
SUNFLOWER CITY
DEEPAK KALYANJI CHANDE
Laxminarayan Heaven
Sahajanand Builders And Developers
SWASTIK MANGAL APARTMENT
SHREEMANGAL CONSTRUCTION
See every Nashik project, with the district possession charts
Builder: Akshay Vinod Tatiya And Pratik Prakash Badgujar
Akshay Vinod Tatiya And Pratik Prakash Badgujar has 1 registration on MahaRERA, including Sunrise Tower. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nashik district page.
Frequently asked questions
What are my rights if Sunrise Tower is delayed beyond 30 Jun 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Sunrise Tower?
The registered promoter entity is Akshay Vinod Tatiya And Pratik Prakash Badgujar, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Sunrise Tower?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Sunrise Tower?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Sunrise Tower?
The professionals named in the filing: Architect: Lakshmi Manthan Shewale; Engineer: Prakash Shankar Badgujar; Engineer: Vishal Sitaram Bagul; Chartered Accountant: CA Paresh Sabadra; Chartered Accountant: RSPH & Associates; Chartered Accountant: Rahul P Mundada and Associates LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Sunrise Tower?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.