Home / Browse projects / Nashik, Maharashtra / LIFE 360
LIFE 360
RG-MH-57542 · RERA P51600052232 · Last updated on MahaRERA portal: 13 Sep 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 4 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
LIFE 360 is a Residential / Group Housing project by VELOCITY INFRA PROJECTS in Nashik, Maharashtra, registered with MahaRERA as P51600052232 on 31 Jul 2023. Possession is promised by 30 Apr 2028. The completion date has moved by 4 months from the original filing. 238 of the 985 units on this registration are recorded sold or booked, and 2 of 66 construction stages are filed complete.
At a glance
Project
- NameLIFE 360
- TypeResidential / Group Housing
- Location
- JUNNARE NAGAR
- PATHARDI SHIWAR
- Nashik (M Corp.)
- Nashik
- 422010
- Pincode422010
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51600052232
- ReraGenie IDRG-MH-57542
Builder
- NameVELOCITY INFRA PROJECTS
- Entity typePartnership
- PartnersSUNITA VIJAY SANAP, VIJAY KISAN SANAP, Santosh Parmanand Kothawale, Amol Vasant More
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on31 Jul 2023
- Promised completion30 Apr 2028
- Revised completionRevised to 30 Apr 2028 (originally 31 Dec 2027)
- Buildings6 building records
- Documents filed118 files
Current status
Figures as on 13 Sep 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A1, A2, A3 | NA | 17 | 16 | 180 | 0 | 180 |
| B1, B2, B3 | NA | 18 | 16 | 192 | 0 | 192 |
| C1, C2, C3 | NA | 21 | 19 | 228 | 0 | 228 |
| D1, D2, D3 | NA | 18 | 16 | 191 | 0 | 191 |
| E1, E2, E3 | NA | 18 | 16 | 193 | 0 | 193 |
| Club House | NA | 4 | 3 | 0 | 1 | 1 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building6
As on 13 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
2 of 66 construction stages are filed complete across 6 buildings. The stage furthest along is Stilt Floor, at 95%.
A1, A2, A325%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 85% |
| Podiums (if any) | 0% |
| Plinth | 80% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 10% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B1, B2, B30%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
C1, C2, C336%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 90% |
| Podiums (if any) | 0% |
| Plinth | 85% |
| Stilt Floor | 95% |
| Slabs of Super Structure | 15% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 15% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
D1, D2, D39%
| Activity | Progress |
|---|---|
| Excavation | 95% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
E1, E2, E39%
| Activity | Progress |
|---|---|
| Excavation | 95% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Club House0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 13 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed1053
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| A1, A2, A3 | 192 | 10 | 202 |
| B1, B2, B3 | 192 | 10 | 202 |
| C1, C2, C3 | 228 | 11 | 239 |
| D1, D2, D3 | 192 | 10 | 202 |
| E1, E2, E3 | 192 | 10 | 202 |
| Club House | 1 | 5 | 6 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| C1, C2, C3 | NA | Rs 26.44 cr | Rs 13.22 cr |
| E1, E2, E3 | NA | Rs 25.51 cr | - |
| A1, A2, A3 | NA | Rs 25.50 cr | Rs 5.10 cr |
| B1, B2, B3 | NA | Rs 22.29 cr | - |
| D1, D2, D3 | NA | Rs 22.27 cr | Rs 2.23 cr |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | VIJAYKUMAR SANAP |
| Engineer | VIJAY K SANAP |
| Chartered Accountant | SUDARSHAN VITTHAL KALUNGE |
| Chartered Accountant | SANKET K JAIN |
| Partner | Role in project |
|---|---|
| VELOCITY INFRA PROJECTS | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterNA
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 26 Jun 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 1 Jun 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 1 Jun 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 1 Jun 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Apr 2028
Documents filed118
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 118 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Withdrawal Application Form1_Signed.pdf | 13 Sep 2026 |
| Withdrawal Update Form 2File: Withdrawal Application Form2_Signed.pdf | 13 Sep 2026 |
| Withdrawal Update Form 3File: Withdrawal Application Form3.pdf | 13 Sep 2026 |
| Withdrawal Update Form 1File: Withdrawal Application Form1 LIFE 360.pdf | 10 Jun 2026 |
| Withdrawal Update Form 2File: Withdrawal Application Form2 LIFE 360.pdf | 10 Jun 2026 |
| Withdrawal Update Form 3File: Form 3 Q4 FY 25-26_Compressed.pdf | 10 Jun 2026 |
| Withdrawal Update Form 1File: Signed_Withdrawal Application Form1 Q1 25-26.pdf | 21 Mar 2026 |
| Withdrawal Update Form 1File: Signed_Withdrawal Application Form1 Q-2 25-26.pdf | 21 Mar 2026 |
| Withdrawal Update Form 1File: Signed_Withdrawal Application Form1 Q-2 25-26.pdf | 21 Mar 2026 |
| Withdrawal Update Form 1File: Signed_Withdrawal Application Form1 Q-3 25-26.pdf | 21 Mar 2026 |
| Withdrawal Update Form 2File: Signed_Withdrawal Application Form2 Q1 25-26.pdf | 21 Mar 2026 |
| Withdrawal Update Form 2File: Signed_Withdrawal Application Form2 Q-2 25-26.pdf | 21 Mar 2026 |
| Withdrawal Update Form 2File: Signed_Withdrawal Application Form2 Q-2 25-26.pdf | 21 Mar 2026 |
| Withdrawal Update Form 2File: Signed_Withdrawal Application Form 2 Q-3 25-26.pdf | 21 Mar 2026 |
| Withdrawal Update Form 3File: Final_ Q1_25-26_P.pdf | 21 Mar 2026 |
| Withdrawal Update Form 3File: Signed_Withdrawal Application Form2 Q-2 25-26.pdf | 21 Mar 2026 |
| Withdrawal Update Form 3File: Form 3 Final_ Q2_25-26_P.pdf | 21 Mar 2026 |
| Withdrawal Update Form 3File: Final_ Q3_25-26_P.pdf | 21 Mar 2026 |
| Form 2File: Q1_24-_25_FORM_2.pdf | 7 Mar 2026 |
| Form 1File: Q1_24-25_FORM_1.pdf | 7 Mar 2026 |
| Form 3File: FORM3_1st_Q_FY24_25 Final.pdf | 7 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: April_june_24-25.pdf | 7 Mar 2026 |
| Form 1File: Architect_Form1_Q2_24-25.pdf | 7 Mar 2026 |
| Form 2File: Engineer_Form 2_Q2_24-25.pdf | 7 Mar 2026 |
| Form 3File: FORM3_2nd_Q_FY24-25_ Final.pdf | 7 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: July_sep_24-25.pdf | 7 Mar 2026 |
| Form 1File: Form 01 Q3 24-25.pdf | 7 Mar 2026 |
| Form 2File: Form 02 Q3 24-25.pdf | 7 Mar 2026 |
| Form 3File: Q3_24-25_Signed_F.pdf | 7 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Oct_Dec_2024-25.pdf | 7 Mar 2026 |
| Form 1File: Form 1 Life 360 March 25.pdf | 7 Mar 2026 |
| Form 2File: Form 2 Life 360 March 25.pdf | 7 Mar 2026 |
| Form 3File: Q4_24-25_Signed_F.pdf | 7 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Q4_24-25_Sold_Unsold.pdf | 7 Mar 2026 |
| Form 1File: 1 Architects Certificate of Percentage of Completion of Work (Form 1).pdf | 7 Mar 2026 |
| Form 2File: 1 Engineers Certificate on Cost Incurred on Project (Form 2).pdf | 7 Mar 2026 |
| Form 3File: 1_FORM3_2nd_Q_FY23-24__Final.pdf | 7 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: 1 Disclosure of sold_ booked inventory.pdf | 7 Mar 2026 |
| Form 1File: FORM1.pdf | 7 Mar 2026 |
| Form 2File: FORM2.pdf | 7 Mar 2026 |
| Form 3File: 2_FORM3_3rd_Q_FY23_24_Final.pdf | 7 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: 2 Disclosure of sold_ booked inventory.pdf | 7 Mar 2026 |
| Form 1File: FORM1.pdf | 7 Mar 2026 |
| Form 2File: FORM2.pdf | 7 Mar 2026 |
| Form 3File: 3_FORM3_4th_Q_FY23_24 Final.pdf | 7 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold_booked inventory.pdf | 7 Mar 2026 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM3_2nd_Q_FY23-24__Final.pdf | 22 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM3_3rd_Q_FY23_24_Final.pdf | 22 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM3_4th_Q_FY23_24 Final.pdf | 22 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM3_1st_Q_FY24_25 Final.pdf | 22 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM3_2nd_Q_FY24-25_ Final.pdf | 22 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Inventory Update as on 30-09-24.pdf | 22 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Sept 24.pdf | 20 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Sept 24.pdf | 20 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Inventory June 24.pdf | 26 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 01 30 June 24.pdf | 19 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 02 30 June 24.pdf | 19 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 31 Mar 24.pdf | 26 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 31 Mar 24.pdf | 26 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Inventory Update as on 31-03-2024.pdf | 26 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Inventory Update as on 31-12-23.pdf | 7 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Velocity dec 23.pdf | 6 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Velocity dec 23.pdf | 6 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 30 Sept 23.pdf | 14 Dec 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 30 Sept 23.pdf | 14 Dec 2023 |
| Disclosure of sold/ booked inventoryFile: Inventory Update as on 30-09-23.pdf | 14 Dec 2023 |
| Details of encumbrances concerned to FinanceFile: NON ENCUMBRANCE.pdf | 21 Jul 2023 |
| Details of encumbrances concerned to LegalFile: NON ENCUMBRANCE.pdf | 21 Jul 2023 |
| Copy of the legal title reportFile: Partnership Deed_Velocity Infra Project.pdf | 26 Jun 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Report pdf.pdf | 9 Jun 2023 |
| Proforma of Agreement for saleFile: Agreement to Sale.pdf | 2 Jun 2023 |
| Layout approvalFile: 1 (1).pdf | 1 Jun 2023 |
| Building plan approvalFile: 1 (2).pdf | 1 Jun 2023 |
| Building plan approvalFile: 1 (3).pdf | 1 Jun 2023 |
| Building plan approvalFile: 1 (4).pdf | 1 Jun 2023 |
| Building plan approvalFile: 1 (5).pdf | 1 Jun 2023 |
| Building plan approvalFile: 1 (6).pdf | 1 Jun 2023 |
| Building plan approvalFile: 1 (7).pdf | 1 Jun 2023 |
| Building plan approvalFile: 1 (8).pdf | 1 Jun 2023 |
| Building plan approvalFile: 1 (9).pdf | 1 Jun 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nashik
Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.
Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 118 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep LIFE 360 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near PATHARDI SHIWAR4,100+ in Nashik
Filed coordinates, straight-line distance. 286 registered projects within 2 km.
SHREE SATYANARAYAN ROONGTA FORUM
ROONGTA HOMES LLP
ARYAN'S LIFEONE
SHREE ARYAN BUILDERS AND DEVELOPERS
SUNFLOWER CITY
DEEPAK KALYANJI CHANDE
Laxminarayan Heaven
Sahajanand Builders And Developers
SWASTIK MANGAL APARTMENT
SHREEMANGAL CONSTRUCTION
VRINDAVAN DHAM
RAJMUDRA CONSTRUCTIONS
See every Nashik project, with the district possession charts
Builder: VELOCITY INFRA PROJECTS
VELOCITY INFRA PROJECTS has 1 registration on MahaRERA, including LIFE 360. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nashik district page.
Frequently asked questions
What are my rights if LIFE 360 is delayed beyond 30 Apr 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of LIFE 360?
The registered promoter entity is VELOCITY INFRA PROJECTS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in LIFE 360?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for LIFE 360?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at LIFE 360?
The professionals named in the filing: Architect: VIJAYKUMAR SANAP; Engineer: VIJAY K SANAP; Chartered Accountant: SUDARSHAN VITTHAL KALUNGE; Chartered Accountant: SANKET K JAIN. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in LIFE 360?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback