Home / Browse projects / Thane, Maharashtra / Suman Arcade
Suman Arcade
RG-MH-73066 · RERA P51700031345 · Last updated on MahaRERA portal: 21 Dec 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 24 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Suman Arcade is a Others project by Shreekrupa Construction in Thane, Maharashtra, registered with MahaRERA as P51700031345 on 23 Oct 2021. Possession is promised by 31 Dec 2026. The completion date has moved by 24 months from the original filing.
At a glance
Project
- NameSuman Arcade
- TypeOthers
- Location
- Manpada Road
- Sagaon
- nandivli tarfe panchnand
- Kalyan
- Thane
- 421204
- Pincode421204
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700031345
- ReraGenie IDRG-MH-73066
Builder
- NameShreekrupa Construction
- Entity typePartnership
- PartnersMahendra Vasudeo Mhatre, Umesh Ananta Madhavi, Gangaram Sudam Thange
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on23 Oct 2021
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2024)
- Buildings1 building record
- Documents filed25 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Suman Arcade | NA | 14 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 21 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
1 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.
Suman Arcade: 9% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities16
As on 21 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
| Society Office Common entrance lobby common toilet and refuge area at 8th floor | Yes | 0% |
Land and ownership8
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| SUMAN ATMARAM MHATRE | nandivli tarfe panchnand | Thane |
| Indra Nana Bhoir | Kalyan-Dombivali (M Corp.) | Thane |
| Chandra Vaman Bangar | Sagaon | Thane |
| Ranjana Sunil Sante | nelje | Thane |
| Meena Vasudev Mhatre | Sagaon | Thane |
| Paresh Vasudev Mhatre | Sagaon | Thane |
| Purushottam Vasudev Mhatre | Sagaon | Thane |
| Haresh Vasudev Mhatre | Sagaon | Thane |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | TIBIN TONSON THOMAS |
| Engineer | MANOHAR VISHNU PATIL |
| Chartered Accountant | SWAPNIL SURESH VARDAM |
| Chartered Accountant | SONALI SUNIL MHATRE |
| Partner | Role in project |
|---|---|
| Shreekrupa Construction | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterProject could not be completed in stipulated time due to Market conditions, delay from the contractor's side and scarcity of certain raw materials needed for civil work on site, which further delayed the construction process. Due to aforementioned circumstances, we are request to you goodself to grant Extension for date of completion upto 31.12.2026.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 4 Oct 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 4 Oct 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 4 Oct 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 4 Oct 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed25
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Shreekrupa.pdf | 21 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Shreekrupa 30092024.pdf | 4 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Shreekrupa 30092024.pdf | 4 Dec 2024 |
| Declaration in FORM BFile: Form B Firm Shreekrupa Construction.pdf | 29 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3 Shreekrupa Sept 2024.pdf | 29 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Inventory Sept 2024.pdf | 29 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Shreekrupa Construction Form 5 202324.pdf | 29 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form No 5 202223.pdf | 15 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Shreekrupa Construction Form No 5.pdf | 14 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate_compressed.pdf | 18 Oct 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate in Form3_compressed.pdf | 18 Oct 2021 |
| Layout approvalFile: scan0015 copy.pdf | 4 Oct 2021 |
| Building plan approvalFile: scan0016 copy.pdf | 4 Oct 2021 |
| PAN CardFile: Pan Card Copy.pdf | 4 Oct 2021 |
| Copy of the legal title reportFile: Title Report_compressed.pdf | 4 Oct 2021 |
| Details of encumbrancesFile: No Encumbrances Certificate.pdf | 4 Oct 2021 |
| Copy of Layout Approval (in case of layout)File: scan0015 copy.pdf | 4 Oct 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: scan0016 copy.pdf | 4 Oct 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: CC 1_compressed.pdf | 4 Oct 2021 |
| Declaration about Commencement CertificateFile: CC Declaration.pdf | 4 Oct 2021 |
| Declaration in FORM BFile: Mahendra Vasudev Mhatre_compressed.pdf | 4 Oct 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate_compressed.pdf | 4 Oct 2021 |
| Disclosure of sold/ booked inventoryFile: Inventory Declaration 30092021.pdf | 4 Oct 2021 |
| Proforma of Allotment letterFile: DRAFT AGREEMENT FOR SALE_Sanjay Patil.pdf | 4 Oct 2021 |
| Proforma of Allotment letterFile: Shreekrupa Construction Allotment Letter.pdf | 4 Oct 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 25 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Suman Arcade on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Sagaon7,600+ in Thane
Filed coordinates, straight-line distance. 190 registered projects within 2 km.
Constrcution of 2557 EWS tenements at S.No.157
ARUN SHANKARRAO BORGAVE
Runwal Gardens Phase I
Runwal Residency Private Limited
Runwal Garden City Cluster 6 Tower 6 to 9
HORIZON PROJECTS PVT LTD
Runwal Gardens Phase 6A Bldg No. 53-54
Runwal Residency Private Limited
RGC Runwal My City EWS - LIG Building
HORIZON PROJECTS PVT LTD
BALAJI ESTATE PHASE 2
M/S SAI BALAJI BUILDCON
See every Thane project, with the district possession charts
Builder: Shreekrupa Construction
Shreekrupa Construction has 1 registration on MahaRERA, including Suman Arcade. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What are my rights if Suman Arcade is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Suman Arcade?
The registered promoter entity is Shreekrupa Construction, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Suman Arcade?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Suman Arcade?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Suman Arcade?
The professionals named in the filing: Architect: TIBIN TONSON THOMAS; Engineer: MANOHAR VISHNU PATIL; Chartered Accountant: SWAPNIL SURESH VARDAM; Chartered Accountant: SONALI SUNIL MHATRE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Suman Arcade?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback