Home / Browse projects / Pune, Maharashtra / Sukhwani Verde

Registered No litigation declared Residential / Group Housing project

Sukhwani Verde

By Sagar Gurmukh Sukhwani

RG-MH-86198 · RERA P52100050278 · Last updated on MahaRERA portal: 22 Jul 2026

Source: official MahaRERA filing

Red flags

  • 2 complaints at MahaRERA
  • Completion date moved by 12 months, 4 of them under MahaRERA's automatic 4-month extension
  • 1 extension taken
  • Rs 50.00 crore secured on the land, in favour of BAJAJ HOUSING FINANCE LIMITED

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 12 months from the original
15 of 36Construction stages doneacross 4 buildings; furthest along: Installation of Lifts, 90%
213 of 322Units unsoldnot recorded sold or booked
2Complaints at MahaRERAon this registration
Jump to the 150 documents Report an error

Sukhwani Verde is a Residential / Group Housing project by Sagar Gurmukh Sukhwani in Pune, Maharashtra, registered with MahaRERA as P52100050278 on 1 Apr 2023. Possession is promised by 30 Dec 2027. The completion date has moved by 12 months from the original filing, 4 of them under MahaRERA's automatic 4-month extension for the West Asia conflict. 109 of the 322 units on this registration are recorded sold or booked, and 15 of 36 construction stages are filed complete. 2 complaints are on record with the regulator.

At a glance

Project

  • NameSukhwani Verde
  • TypeResidential / Group Housing
  • Location
    • Katraj Fursungi Road
    • Undri
    • Undri-Ext
    • Haveli
    • Pune
    • 411060
  • Pincode411060
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100050278
  • ReraGenie IDRG-MH-86198

Builder

  • NameSagar Gurmukh Sukhwani
  • Entity typeIndividual
  • Declared earlier projects2 →

Key dates

this monthRegisteredApr 2023First promiseDec 2026Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on1 Apr 2023
  • Promised completion30 Dec 2027
  • Revised completionRevised to 30 Dec 2027 (originally 30 Dec 2026)
  • Buildings4 building records
  • Documents filed150 files

Current status

34%109 of 322 units booked
92.3%Work done, per cost certificate

Figures as on 22 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building ANA201890090
Building BNA201890090
Building CNA20181210121
Building D MhadaNA9721021

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 22 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

15 of 36 construction stages are filed complete across 4 buildings. The stage furthest along is Installation of Lifts, at 90%.

Building A32%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)Not applicable
Plinth0%
Stilt FloorNot applicable
Slabs of Super Structure40%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises7%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks25%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%
Building B71%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises30%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks88%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.24%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.40%
Building C99%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)Not applicable
Plinth100%
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
Building D Mhada32%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)Not applicable
Plinth90%
Stilt FloorNot applicable
Slabs of Super Structure56%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks35%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%

Progress on shared amenities15

As on 22 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes35%
Water SupplyYes35%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes35%
Storm Water DrainsYes35%
Landscaping & Tree PlantingYes35%
Street LightingYes0%
Community BuildingsYes35%
Treatment And Disposal Of Sewage And Sullage WaterYes35%
Solid Waste Management And DisposalYes35%
Water conservation /Rain water harvestingYes35%
Energy managemcntYes35%
Fire protection and fire safety requirementsYes35%
Electrical meter room, sub-station, receiving stationYes35%
Aggregate area of recreational Open SpaceYesNot applicable
Open ParkingNoNot applicable

Parking filed578

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots578
Closed/Covered239
Open Space339
BuildingClosed/CoveredOpen SpaceTotal
Building A6894162
Building B6894162
Building C92125217
Building D Mhada112637

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area10,950 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofBAJAJ HOUSING FINANCE LIMITED
Secured amountRs 50.00 crore
CERSAI search filedYes
Declared on3 Jul 2025

Approvals and building plan

Sanctioning authorityPune Muncipal Corporation
Permissible FSI33261.82
Proposed, not sanctioned32,106 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKAMALA CROSSROADS,UNIT NOS. 1 TO 4 and 26 TO 29, OPP.PCMC OFFICE.PUNE MAHARASHTRA 411017
Estimated costRs 80.44 cr
Cost incurredRs 74.21 cr
Work done92.26%
BuildingWingEstimatedIncurred
Building CNARs 34.92 crRs 33.85 cr
Building BNARs 28.16 crRs 27.10 cr
Building D MhadaNARs 6.79 crRs 5.26 cr
-NARs 5.91 crRs 4.75 cr
Building ANARs 4.66 crRs 3.25 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectManoj Tatooskar
EngineerShivaji Sherekar
Chartered AccountantA N J K & CO LLP
Chartered AccountantR V Nevatia and Co
PartnerRole in project
Sagar Gurmukh Sukhwani-

Extensions2

A revised date filed with the regulator does not change the possession date in your agreement for sale. Commentary on the order notes that a buyer's right to interest for delay under section 18 of RERA may still stand; that question has not been tested.

MahaRERA order of 7 Aug 2026Dec 2026 → Apr 2027

Granted by MahaRERA, not applied for by the promoterMahaRERA's order of 7 August 2026 extended the completion date of eligible registered projects by four months, treating the West Asia conflict as force majeure. Promoters did not have to apply for it.

EA30092639014Dec 2026 → Dec 2027

Reason as filed by the promoterWe are writing to request an extension for the completion timeline of our project, which includes Building A, Building B, Building C & Building D, registered under RERA in 2017. The project has been delayed primarily due to the approval of the Revised Sanctioned Plans, which were approved on 23/02/2026. The time involved in obtaining the revised approval and thereafter aligning the construction activities with the revised sanctioned plans has affected the overall project timeline. Further, the project has faced shortage of skilled labour and irregular availability of essential construction mat

Litigation declared1

CaseCourtStatus
1410/2016/2016Civil Court Senior Division PuneIssues

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC12602961Kulbhushan Shrinivas GavaliSagar Gurmukh Sukhwani19/05/2026
CC12602962Dattatray Dnyandeo AgawaneSagar Gurmukh Sukhwani19/05/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 16 May 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 Jul 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Jul 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 1 Feb 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Dec 2027

Documents filed150

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 150 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Layout approvalFile: Layout Approval_Final.pdf22 Jul 2026
Building plan approvalFile: Building Plan 1.pdf22 Jul 2026
Building plan approvalFile: Building Plan 2.pdf22 Jul 2026
Building plan approvalFile: Building Plan 3.pdf22 Jul 2026
Building plan approvalFile: Building Plan 4.pdf22 Jul 2026
Building plan approvalFile: Building Plan 5.pdf22 Jul 2026
Building plan approvalFile: Building Plan 6.pdf22 Jul 2026
Building plan approvalFile: Building Plan 7.pdf22 Jul 2026
Building plan approvalFile: Building Plan 8.pdf22 Jul 2026
Building plan approvalFile: Building Plan 9.pdf22 Jul 2026
Building plan approvalFile: Building Plan 10.pdf22 Jul 2026
Building plan approvalFile: Building Plan 11.pdf22 Jul 2026
Building plan approvalFile: Building Plan 12.pdf22 Jul 2026
Building plan approvalFile: Building Plan 13.pdf22 Jul 2026
Building plan approvalFile: Building Plan 14.pdf22 Jul 2026
Withdrawal Update Form 1File: Form 1 Architect Certificate June 2026.pdf22 Jul 2026
Withdrawal Update Form 2File: Form 2 Engineer Certificate June 2026.pdf22 Jul 2026
Withdrawal Update Form 3File: Form 3 CA Certificate June 2026.pdf22 Jul 2026
Form 2A (FY 2024-2025)File: Form 2A FY 2024-25Final.pdf22 Jul 2026
Form 2A (FY 2025-2026)File: Form 2A FY 2025-26Final.pdf22 Jul 2026
Withdrawal Update Form 1File: Form 1 Architect Certificate March 2026.pdf30 Apr 2026
Withdrawal Update Form 1File: Form 1 Architect Certificate March 2026.pdf30 Apr 2026
Withdrawal Update Form 2File: Form 2 Engineer Certificate March 2026.pdf30 Apr 2026
Withdrawal Update Form 2File: Form 2 Engineer Certificate March 2026.pdf30 Apr 2026
Withdrawal Update Form 3File: Form 3 CA Certificate - March 2026 Verde.pdf30 Apr 2026
Withdrawal Update Form 3File: Form 3 CA Certificate - March 2026 Verde.pdf30 Apr 2026
Withdrawal Update Form 1File: Form-1 Art Certificate Dec 2025.pdf22 Jan 2026
Withdrawal Update Form 2File: Form-2 Eng Certificate Dec 2025.pdf22 Jan 2026
Withdrawal Update Form 3File: Form 3 CA Certificate - Verde - December 2025.pdf22 Jan 2026
Form 5 (FY 2024-2025)File: CA Form 5_Sukhwani Verde_FY 2024-25_Signed.pdf24 Nov 2025
Withdrawal Update Form 1File: Form 1 Architect Certificate Verde - September 2025.pdf6 Nov 2025
Withdrawal Update Form 2File: Form 2 Engineer Certificate Verde - September 2025.pdf6 Nov 2025
Withdrawal Update Form 3File: Form 3 CA Certificate Verde - September 2025.pdf6 Nov 2025
Form 1File: Form 1 Architect Certificate - March 2025 - Verde.pdf15 Jul 2025
Form 2File: Form 2 Engineer certificate 31-03-2025.pdf15 Jul 2025
Form 3File: CA Certificate Sukhwani Verde - March 2025.pdf15 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Inventory March 25.pdf15 Jul 2025
Withdrawal Update Form 1File: Form 1 Architect Certificate June 2025 Signed.pdf15 Jul 2025
Withdrawal Update Form 2File: Form 2 Engineers Certificate June 2025.pdf15 Jul 2025
Withdrawal Update Form 3File: Form 3 CA Certificate Verde June 2025 Signed.pdf15 Jul 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate New Format - Sukhwani Verde - December 2024 - Sign.pdf28 Mar 2025
Declaration about Commencement CertificateFile: CC Declaration.pdf7 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Sukhwani Buildtech_Verde.pdf3 Feb 2025
Layout approvalFile: Layout Approval 1.pdf1 Feb 2025
Layout approvalFile: Layout Approval 2.pdf1 Feb 2025
Layout approvalFile: Layout Approval 3.pdf1 Feb 2025
Building plan approvalFile: Building Plan 1.pdf1 Feb 2025
Building plan approvalFile: Building Plan 2.pdf1 Feb 2025
Building plan approvalFile: Building Plan 3.pdf1 Feb 2025
Building plan approvalFile: Building Plan 4.pdf1 Feb 2025
Building plan approvalFile: Building Plan 5.pdf1 Feb 2025
Building plan approvalFile: Building Plan 6.pdf1 Feb 2025
Building plan approvalFile: Building Plan 7.pdf1 Feb 2025
Building plan approvalFile: Building Plan 8.pdf1 Feb 2025
Building plan approvalFile: Building Plan 9.pdf1 Feb 2025
Building plan approvalFile: Building Plan 10.pdf1 Feb 2025
Copy of Layout Approval (in case of layout)File: Layout Approval 2.pdf1 Feb 2025
Copy of Layout Approval (in case of layout)File: Layout Approval 3.pdf1 Feb 2025
Copy of Layout Approval (in case of layout)File: Layout Approval 1.pdf1 Feb 2025
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf1 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 3.pdf1 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 10.pdf1 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 9.pdf1 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 8.pdf1 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 7.pdf1 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 6.pdf1 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 5.pdf1 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 4.pdf1 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 2.pdf1 Feb 2025
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 1.pdf1 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf31 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate New Format - Sukhwani Verde - December 2024 - Sign.pdf31 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate.pdf31 Jan 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory-Verde - December 2024.pdf31 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate.pdf13 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf11 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate New Format - Sukhwani Verde - Sept 2024 - Sign.pdf11 Nov 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory-Verde - Sept 2024.pdf11 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate.pdf26 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate_Compressed.pdf20 Jul 2024

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise1 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Sukhwani ArtizeP52100026850Ravet, Pune131Oct 2020OngoingApr 2024Not delivered
Sukhwani EuphoriaP52100028123Near Kapil Akhila, Pune18Feb 2021CompletedJun 2023Jun 2023

How this compares with Pune

34%of this project is bookeddistrict median 29%
28%of Pune projects moved their completion datethis one moved by 12 months
25%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 14,000+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Sukhwani Verde on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Undri14,000+ in Pune

2 kmSukhwani VerdeCompleted 97Lapsed / revoked 37Other 95Dot size: filed unitsN

Filed coordinates, straight-line distance. 229 registered projects within 2 km.

Builder: Sagar Gurmukh Sukhwani

Sagar Gurmukh Sukhwani has 1 registration on MahaRERA, including Sukhwani Verde. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Sukhwani Verde is delayed beyond 30 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Sukhwani Verde?

The registered promoter entity is Sagar Gurmukh Sukhwani, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Sukhwani Verde?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Sukhwani Verde?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Sukhwani Verde?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Sukhwani Verde?

The professionals named in the filing: Architect: Manoj Tatooskar; Engineer: Shivaji Sherekar; Chartered Accountant: A N J K & CO LLP; Chartered Accountant: R V Nevatia and Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Sukhwani Verde?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sukhwani Verde. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sukhwani Verde to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.