Home / Browse projects / Mumbai Suburban, Maharashtra / Subhash Nagar Building No 14 New Jayalaxmi
Subhash Nagar Building No 14 New Jayalaxmi
RG-MH-64164 · RERA P51800046306 · Last updated on MahaRERA portal: 16 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 17 months past the filed date
- 4 complaints at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Subhash Nagar Building No 14 New Jayalaxmi is a Residential / Group Housing project by G A Builders Pvt Ltd. in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800046306 on 22 Jun 2022. Possession was promised by 31 May 2025 and is now 17 months past that date. 108 of the 120 units on this registration are recorded sold or booked, and 24 of 33 construction stages are filed complete. 4 complaints are on record with the regulator.
At a glance
Project
- NameSubhash Nagar Building No 14 New Jayalaxmi
- TypeResidential / Group Housing
- Location
- Chembur
- Kurla
- Mumbai Suburban
- 400071
- Pincode400071
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800046306
- ReraGenie IDRG-MH-64164
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on22 Jun 2022
- Promised completion31 May 2025
- Revised completionNone
- Buildings3 building records
- Documents filed81 files
Current status
Figures as on 16 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Wing A Subhash Nagar Bldg No 14 New Jayalaxmi Phase 1 | NA | 9 | 9 | 42 | 0 | 42 |
| Wing C Subhash Nagar Bldg No 14 New Jayalaxmi Phase 1 | NA | 11 | 9 | 36 | 0 | 36 |
| Wing D Subhash Nagar Bldg No 14 New Jayalaxmi Phase 1 | NA | 9 | 7 | 42 | 0 | 42 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 16 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
24 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Installation of Lifts, at 98%.
Wing A Subhash Nagar Bldg No 14 New Jayalaxmi Phase 182%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 8% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 98% |
Wing C Subhash Nagar Bldg No 14 New Jayalaxmi Phase 183%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 10% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 98% |
Wing D Subhash Nagar Bldg No 14 New Jayalaxmi Phase 182%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 8% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 98% |
Progress on shared amenities15
As on 16 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | No | Not applicable |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Jayalaxmi CHSL | Kurla | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Space Moulders |
| Engineer | Satish C Dhupelia |
| Engineer | PRAVIN NARAYAN SHINDE |
| Chartered Accountant | G S JHA & CO |
| Chartered Accountant | Anil B.Ghaisas&co. |
| Partner | Role in project |
|---|---|
| G A Builders Pvt Ltd. | - |
Complaints filed with MahaRERA4
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12603441 | G A Builders Pvt Ltd. | Smita A Salunke and Ajay Y Salunke | 04/06/2026 |
| CC12603630 | G A Builders Pvt Ltd. | ALPIKA CHOUHAN | 12/06/2026 |
| CC12603689 | G A Builders Pvt Ltd. | Dipti N Walanj | 15/06/2026 |
| CC12603690 | G A Builders Pvt Ltd. | SATISH M YADAV | 15/06/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 16 Jun 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 16 Jun 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 16 Jun 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 16 Jun 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed81
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 81 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: form 1 bldg14.pdf | 16 Jul 2026 |
| Form 2File: form 2 bldg 14.pdf | 16 Jul 2026 |
| Form 3File: form 3 bldg 14.pdf | 16 Jul 2026 |
| Disclosure of Sold and Booked InventoryFile: disclosure sold unsold bldg 14.pdf | 16 Jul 2026 |
| Form 2A (FY 2022-2023)File: 14Form2A March 23.pdf | 17 Jan 2026 |
| Form 2A (FY 2023-2024)File: 14Form2A March 24.pdf | 17 Jan 2026 |
| Form 2A (FY 2024-2025)File: 14Form2A March 25.pdf | 17 Jan 2026 |
| Form 5 (FY 2023-2024)File: 14 FORM 5 MARCH 2024 .pdf | 17 Jan 2026 |
| Form 5 (FY 2024-2025)File: 14 FORM 5 MARCH 2025.pdf | 17 Jan 2026 |
| Form 5 (FY 2022-2023)File: 14 FORM 5 MARCH 2023.pdf | 13 Jan 2026 |
| Form 1File: FORM1 Sep 2022 14.pdf | 11 Jan 2026 |
| Form 2File: FORM2 30 Sep2214.pdf | 11 Jan 2026 |
| Form 3File: 15 FORM 3 Sep22.pdf | 11 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLDUNSOLD3009202214.pdf | 11 Jan 2026 |
| Form 2File: FORM2 31 Dec2214.pdf | 11 Jan 2026 |
| Form 1File: FORM1DEC2214.pdf | 11 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLDUNSOLD3112202214.pdf | 11 Jan 2026 |
| Form 3File: 14 FORM 3 Dec 22.pdf | 11 Jan 2026 |
| Form 1File: FORM1March 2023 14.pdf | 11 Jan 2026 |
| Form 2File: FORM2 31 Mar2314.pdf | 11 Jan 2026 |
| Form 3File: 14 FORM 3 March 23.pdf | 11 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLDUNSOLD3103202314.pdf | 11 Jan 2026 |
| OthersFile: 14 FORM 3 sep 22.pdf | 11 Jan 2026 |
| Form 1File: FORM1June202314.pdf | 11 Jan 2026 |
| Form 2File: FORM2 30 Jun2314.pdf | 11 Jan 2026 |
| Form 3File: 14 FORM 3 june 23.pdf | 11 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLDUNSOLD3006202314.pdf | 11 Jan 2026 |
| Form 1File: FORM1Sep 2023 14.pdf | 11 Jan 2026 |
| Form 2File: FORM2 30 Sep2314.pdf | 11 Jan 2026 |
| Form 3File: 14 FORM 3 sep23.pdf | 11 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLDUNSOLD3009202314.pdf | 11 Jan 2026 |
| Form 1File: FORM1 Dec202314.pdf | 11 Jan 2026 |
| Form 2File: FORM2 31 Dec2314.pdf | 11 Jan 2026 |
| Form 3File: 14 FORM 3 Dec23.pdf | 11 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLDUNSOLD3112202314.pdf | 11 Jan 2026 |
| Form 1File: FORM1March 2024 14.pdf | 11 Jan 2026 |
| Form 2File: FORM2 31 Mar2414.pdf | 11 Jan 2026 |
| Form 3File: 14 FORM 3 March24.pdf | 11 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLDUNSOLD3103202414.pdf | 11 Jan 2026 |
| Form 1File: FORM1June202414.pdf | 11 Jan 2026 |
| Form 2File: FORM2 30 Jun2414.pdf | 11 Jan 2026 |
| Form 3File: 14 FORM 3 June24.pdf | 11 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLDUNSOLD3006202414.pdf | 11 Jan 2026 |
| Form 1File: FORM1Sep 202414.pdf | 11 Jan 2026 |
| Form 2File: FORM2 30 Sep2414.pdf | 11 Jan 2026 |
| Form 3File: 14 FORM 3 Sep 24.pdf | 11 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLDUNSOLD3009202414.pdf | 11 Jan 2026 |
| Form 1File: FORM1Dec202414.pdf | 11 Jan 2026 |
| Form 2File: FORM2 31 Dec2414.pdf | 11 Jan 2026 |
| Form 3File: 14 FORM 3 Dec24.pdf | 11 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLDUNSOLD3112202414.pdf | 11 Jan 2026 |
| Form 1File: FORM1March 2025 14.pdf | 11 Jan 2026 |
| Form 2File: FORM2 31 Mar2514.pdf | 11 Jan 2026 |
| Form 3File: 14 FORM 3 March 25.pdf | 11 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLDUNSOLD3103202514.pdf | 11 Jan 2026 |
| Form 1File: FORM1June 2025 14.pdf | 11 Jan 2026 |
| Form 2File: FORM2 30 Jun2514.pdf | 11 Jan 2026 |
| Form 3File: 14 FORM 3 June 25.pdf | 11 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLDUNSOLD3006202514.pdf | 11 Jan 2026 |
| Layout approvalFile: 3 (2) block plan (1).pdf | 16 Jun 2022 |
| Layout approvalFile: 3 (3) ground floor plan.pdf | 16 Jun 2022 |
| Building plan approvalFile: 3 (4 ) 1st to 7th floor plan.pdf | 16 Jun 2022 |
| Building plan approvalFile: 3 (5) 8th,9th and terrace floor.pdf | 16 Jun 2022 |
| Building plan approvalFile: 3 (6) section.pdf | 16 Jun 2022 |
| PAN CardFile: PAN CARD G A Builders.pdf | 16 Jun 2022 |
| Copy of the legal title reportFile: legal titel certificate bldg no-14.pdf | 16 Jun 2022 |
| Details of encumbrancesFile: ENCUMBRANCE 14.pdf | 16 Jun 2022 |
| Copy of Layout Approval (in case of layout)File: 3 (2) block plan (1).pdf | 16 Jun 2022 |
| Copy of Layout Approval (in case of layout)File: 3 (3) ground floor plan.pdf | 16 Jun 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: 3 (4 ) 1st to 7th floor plan.pdf | 16 Jun 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: 3 (5) 8th,9th and terrace floor.pdf | 16 Jun 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: 3 (6) section.pdf | 16 Jun 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: 4) bldg no 14 CC.pdf | 16 Jun 2022 |
| Declaration about Commencement CertificateFile: DECLARATION ABOUT CC.pdf | 16 Jun 2022 |
| Declaration in FORM BFile: form (B)affdavit cum declartion PROMOTER (1)-compressed.pdf | 16 Jun 2022 |
| CERSAI detailsFile: Cersai.pdf | 16 Jun 2022 |
| CERSAI detailsFile: Cersai Report.pdf | 16 Jun 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: New Jayalaxmi CA Certificate.pdf | 16 Jun 2022 |
| Proforma of Allotment letterFile: Jayalaxmi Letter of Allotment.pdf | 16 Jun 2022 |
| Proforma of Allotment letterFile: Sale agreement Draft Jayalaxmi.pdf | 16 Jun 2022 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| Subhash Nagar Building No 15 Mrug Vihar Phase 1P51800046368 | chembur, Mumbai Suburban | 78 | Jun 2022 | Ongoing | May 2025 | Not delivered |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 3 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 81 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Subhash Nagar Building No 14 New Jayalaxmi on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Chembur6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 451 registered projects within 2 km.
Hiranandani Maitri Park Phase 1
SHODEN DEVELOPERS PRIVATE LIMITED
Premiere by Panache
Panache Developers Pvt Ltd.
Sai Shrushti
Shree Sai Realtors
MASS METROPOLIS
GRACE URBAN DEVELOPMENT CORPORATION
ELEVIA
VIDA INFRAHUB LLP
PODDAR HARMONY
PODDAR CREATORS LLP
See every Mumbai Suburban project, with the district possession charts
Builder: G A Builders Pvt Ltd.
G A Builders Pvt Ltd. has 4 registrations on MahaRERA, including Subhash Nagar Building No 22 and Building on Plot bearing CTS No 833 pt at MHADA layout as RNA Continental Subhash Nagar Mumbai 71. Its filings disclose 2 earlier MahaRERA projects, none completed yet. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that Subhash Nagar Building No 14 New Jayalaxmi shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Subhash Nagar Building No 14 New Jayalaxmi is delayed beyond 31 May 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Subhash Nagar Building No 14 New Jayalaxmi?
The registered promoter entity is G A Builders Pvt Ltd., a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Subhash Nagar Building No 14 New Jayalaxmi?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Subhash Nagar Building No 14 New Jayalaxmi?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Subhash Nagar Building No 14 New Jayalaxmi?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Subhash Nagar Building No 14 New Jayalaxmi?
The professionals named in the filing: Architect: Space Moulders; Engineer: Satish C Dhupelia; Engineer: PRAVIN NARAYAN SHINDE; Chartered Accountant: G S JHA & CO; Chartered Accountant: Anil B.Ghaisas&co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Subhash Nagar Building No 14 New Jayalaxmi?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback