Home / Browse projects / Palghar, Maharashtra / STERLING HEIGHTS B WING

Registration lapsed No litigation declared Others project

STERLING HEIGHTS B WING

By SHANTEE SWARG

RG-MH-77594 · RERA P99000018952 · Last updated on MahaRERA portal: 29 Apr 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 85 documents Report an error

STERLING HEIGHTS B WING is a Others project by SHANTEE SWARG in Palghar, Maharashtra, registered with MahaRERA as P99000018952 on 17 Dec 2018. Possession was promised by 30 Dec 2025 and is now 10 months past that date.

At a glance

Project

  • NameSTERLING HEIGHTS B WING
  • TypeOthers
  • Location
    • Gokhivare
    • Yashwant Smart City
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401208
  • Pincode401208
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000018952
  • ReraGenie IDRG-MH-77594

Builder

  • NameSHANTEE SWARG
  • Entity typePartnership
  • PartnersFAYAZZUDDIN YASIN KHANPADIYAR, MOHAMMED SHAMOON MOHAMMED ISHAQUE CHOUDHARY
  • Other registrations1 more →
  • Completed1 of 2
  • No longer live1 lapsed, de-registered or revoked

Key dates

10 months past promisethis monthRegisteredDec 2018PromisedDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on17 Dec 2018
  • Promised completion30 Dec 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed85 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
STERLING HEIGHTS B WINGNA200000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 29 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

STERLING HEIGHTS B WING: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 29 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed19

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots19
Closed/Covered19

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,041 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI5141.06
Proposed, not sanctioned2,041 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGOKHIWARE ROAD VASAI EAST 401208

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSANAT MEHTA & ASSOCATES
ArchitectMUFADDAL MERCHANT
EngineerJAYSHREE KRISHNA CONSULTING ENGINEER
EngineerMOHAMMED SHOEB BHATI
PartnerRole in project
SHANTEE SWARG-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Nov 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 Aug 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Nov 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 Jul 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 8 Apr 2025

Documents filed85

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 85 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 STERLING B WING MAR 25.pdf29 Apr 2025
Certificates of CA (Form 3)File: FORM-3 STERLING HEIGHTS B-WING.pdf29 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 STERLING B WING MAR 25.pdf29 Apr 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: STERLING HEIGHTS A, B AND E WING OC.pdf8 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: STERLING HEIGHT WING B FORM 1.pdf24 Jan 2025
Certificates of CA (Form 3)File: STERLING HEIGHTS B WING FORM 3 REDUCE.pdf24 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: STERLING HEIGHTS B WING FORM 2.pdf24 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 STERLING HEIGHTS B WING.pdf15 Jan 2025
Architect’s Certificate on Completion of Project (Form 4)File: FORM-4 STERLING B WING.pdf11 Jan 2025
Status of Formation of Legal Entity (Society/Co Op etc.)File: STERLING A and B WING SOC REG CERTI.pdf8 Jan 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC STERLING B WING 03122024.pdf8 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: STERLING HEIGHT B WING.pdf5 Nov 2024
Certificates of CA (Form 3)File: STERLING HEIGHTS B WING.pdf5 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: STERLING HEIGHT B WING.pdf5 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: STERLING B WING.pdf1 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: STERLING B WING.pdf26 Jul 2024
Disclosure of sold/ booked inventoryFile: STERLING B WING.pdf26 Jul 2024
Certificates of CA (Form 3)File: STERLING HEIGHT B WING.pdf26 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 STERLING HEIGHT B WING.pdf9 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 STERLING HEIGHT B-WING.pdf9 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 STERLING B WING.pdf9 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 STERLING HEIGHT B WING.pdf9 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 STERLING HIEGHT B-WING.pdf9 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 STERLING HEIGHT B WING.pdf9 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 STERLING HEIGHT B WING.pdf9 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 STERLING HEIGHT B WING.pdf9 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM-2A STERLING HEIGHT B WING 31032024.pdf9 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM-2A STERLING HEIGHT B WING 31032023.pdf9 May 2024
Certificates of CA (Form 3)File: FORM-3 STERLING HIEGHT BWING 300623.pdf9 May 2024
Certificates of CA (Form 3)File: FORM-3 STERLING HIGHT B WING.pdf9 May 2024
Certificates of CA (Form 3)File: FORM-3 STERLING HEIGHT B WING.pdf9 May 2024
Certificates of CA (Form 3)File: FORM-3 STERLING HEIGHT B WING.pdf9 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 STERLING B WING.pdf1 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 STERLING HEIGHT B WING.pdf1 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM-1 STERLING HEIGHT B-WING.pdf1 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: STERLING HEIGHT B WING.pdf1 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: STERLING HEIGHTS B WING.pdf1 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: STERLING HEIGHTS B WING.pdf1 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-2 STERLING HEIGHT B WING.pdf1 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: STERLING HEIGHTS B WING.pdf1 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: STERLING HEIGHTS B WING.pdf1 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: STERLING HEIGHTS B WING.pdf1 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: STERLING HEIGHTS B WING.pdf1 Mar 2024
Certificates of CA (Form 3)File: FORM-3 STERLING HIEGHT BWING 300623.pdf1 Mar 2024
Certificates of CA (Form 3)File: FORM-3 STERLING HIGHT B WING.pdf1 Mar 2024
Certificates of CA (Form 3)File: STERLING HEIGHTS B WING.pdf1 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM-3 STERLING HEIGHT B WING.pdf1 Mar 2024
Commencement Certificates / NA Order for plotted developmentFile: STERLING B REVISED CC.pdf6 Jul 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: STERLING HEIGHTS B WING.pdf25 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: STERLING HEIGHTS B WING.pdf24 Apr 2023
Layout approvalFile: STERLING HEIGHTS B WING LAYOUT.pdf16 Aug 2022
Copy of Layout Approval (in case of layout)File: STERLING HEIGHTS B WING LAYOUT.pdf16 Aug 2022
Form 2AFile: FORM 2A STERLING B.pdf25 Nov 2021
Form 2AFile: FORM 2A STERLING B.pdf25 Nov 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A STERLING B.pdf25 Nov 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A STERLING B.pdf25 Nov 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A STERLING B.pdf25 Nov 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A STERLING B.pdf25 Nov 2021
Disclosure of sold/ booked inventoryFile: SOLD AND UNSOLD STERLING HEIGHTS B.pdf24 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: RERA AUDIT STERLING B WING Form 5.pdf26 Feb 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: RERA AUDIT STERLING B WING Form 5.pdf26 Feb 2021
Form 2AFile: FORM-2A - STERLING B WING.pdf24 Feb 2020
Form 2AFile: FORM-2 STERLING B WING 30-09-20.pdf13 Feb 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 1819 STERLING HEIGHTS B WING-30-11-19.pdf31 Dec 2019
Commencement Certificates / NA Order for plotted developmentFile: COM CRT REVISED .pdf24 Dec 2019
Form 2AFile: FORM-2A STERLING HEIGHT B WING.pdf4 Jun 2019
Proforma of Allotment letterFile: ALLOTMENT B WING.pdf1 Dec 2018
Building plan approvalFile: Sterline Height B WING PG 1.pdf29 Nov 2018
Building plan approvalFile: Strrline Height B WING PG 2.pdf29 Nov 2018
Layout approvalFile: Sterline Height B WING PG 1.pdf29 Nov 2018
Layout approvalFile: Strrline Height B WING PG 2.pdf29 Nov 2018
PAN CardFile: SHANTEE SWARG PAN CARD.pdf29 Nov 2018
Copy of the legal title reportFile: SEARCH TITLE REPORT B WING.pdf29 Nov 2018
Details of encumbrancesFile: ENCUMBRANCE CERTIFICATE STERLING B WING.pdf29 Nov 2018
Copy of Layout Approval (in case of layout)File: Sterline Height B WING PG 1.pdf29 Nov 2018
Copy of Layout Approval (in case of layout)File: Strrline Height B WING PG 2.pdf29 Nov 2018
Building Plan Approval (IOD)File: Sterline Height B WING PG 1.pdf29 Nov 2018
Building Plan Approval (IOD)File: Strrline Height B WING PG 2.pdf29 Nov 2018
Commencement Certificates / NA Order for plotted developmentFile: COM CRT OF B WING.pdf29 Nov 2018
Declaration in FORM BFile: FORM B STERLING B WING.pdf29 Nov 2018

How this compares with Palghar

31%of Palghar projects moved their completion datethis one has not
26%of Palghar registrations have lapsed or been cancelledthis one is among them

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep STERLING HEIGHTS B WING on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Yashwant Smart City3,200+ in Palghar

2 kmSTERLING HEIGHTS B WINGCompleted 19Lapsed / revoked 17Other 57Dot size: filed unitsN

Filed coordinates, straight-line distance. 93 registered projects within 2 km.

Builder: SHANTEE SWARG

SHANTEE SWARG has 2 registrations on MahaRERA, including STERLING HEIGHTS B WING and STERLING HEIGHTS E WING. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What does it mean that STERLING HEIGHTS B WING shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if STERLING HEIGHTS B WING is delayed beyond 30 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of STERLING HEIGHTS B WING?

The registered promoter entity is SHANTEE SWARG, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in STERLING HEIGHTS B WING?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for STERLING HEIGHTS B WING?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at STERLING HEIGHTS B WING?

The professionals named in the filing: Architect: SANAT MEHTA & ASSOCATES; Architect: MUFADDAL MERCHANT; Engineer: JAYSHREE KRISHNA CONSULTING ENGINEER; Engineer: MOHAMMED SHOEB BHATI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in STERLING HEIGHTS B WING?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About STERLING HEIGHTS B WING. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save STERLING HEIGHTS B WING to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.