Home / Browse projects / Pune, Maharashtra / STATE BANK OF INDIA SNEHDEEP CHSL

Registered No litigation declared Residential / Group Housing project

STATE BANK OF INDIA SNEHDEEP CHSL

By Kotibhaskar Infrastructures &Developers Pvt.Ltd.

RG-MH-61414 · RERA P52100051137 · Last updated on MahaRERA portal: 23 Jul 2026

Source: official MahaRERA filing

Red flags

  • Possession 1 months past the filed date
  • Completion date moved by 6 months
  • 1 extension taken
  • Rs 15.00 crore secured on the land, in favour of HDFC BANK LIMITED

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Sep 2026Possession promised1 month past this date
9 of 11Construction stages donefurthest along: Podiums (if any), 0%
31 of 56Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 185 documents Report an error

STATE BANK OF INDIA SNEHDEEP CHSL is a Residential / Group Housing project by Kotibhaskar Infrastructures &Developers Pvt.Ltd. in Pune, Maharashtra, registered with MahaRERA as P52100051137 on 30 May 2023. Possession was promised by 30 Sep 2026 and is now 1 months past that date. The completion date has moved by 6 months from the original filing. 25 of the 56 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete.

At a glance

Project

  • NameSTATE BANK OF INDIA SNEHDEEP CHSL
  • TypeResidential / Group Housing
  • Location
    • Kothrud
    • Pune
    • Haveli
    • 411038
  • Pincode411038
  • RERA no.P52100051137
  • ReraGenie IDRG-MH-61414

Builder

  • NameKotibhaskar Infrastructures &Developers Pvt.Ltd.
  • Entity typeCompany
  • CINU45209PN2011PTC140254
  • GSTIN27AAQCS2145B1ZG
  • CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
  • Managing DirectorDilip Shivanand Kotibhaskar
  • ChairpersonChidambar Shivanand kotibhaskar
  • Other registrations27 more →
  • Completed15 of 28
  • No longer live1 lapsed, de-registered or revoked
  • Past their filed date2
  • Declared earlier projects11 →

Key dates

1 months past promisethis monthRegisteredMay 2023First promiseMar 2026Revised toSep 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on30 May 2023
  • Promised completion30 Sep 2026
  • Revised completionRevised to 30 Sep 2026 (originally 4 Mar 2026)
  • Buildings1 building record
  • Documents filed185 files

Current status

45%25 of 56 units booked
88.3%Work done, per cost certificate

Figures as on 23 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
STATE BANK OF INDIA SNEHDEEP CHSLNA151456056

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 23 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

STATE BANK OF INDIA SNEHDEEP CHSL: 82% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 23 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed187

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots187
Closed/Covered187

Land and ownership1

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area2,317 sq m
Land owned byNot the promoter
Named landowners1
Encumbrance on the landDeclared present
Charge in favour ofHDFC BANK LIMITED
Secured amountRs 15.00 crore
Declared on21 Jul 2025
LandownerVillageDistrict
STATE BANK OF INNDIA SNEHDEEP CHSLKothrudPune

Approvals and building plan

Sanctioning authorityPune Municipal Corportaion
Permissible FSI9381.36
Proposed, not sanctioned9,379 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchLAUKIK APARTMENT GROUND FLOOR PLOT NO 3 CTS NO 870 BHANDARKAR ROAD PUNE PUNE 411004
Estimated costRs 40.62 cr
Cost incurredRs 35.87 cr
Work done88.31%
BuildingWingEstimatedIncurred
STATE BANK OF INDIA SNEHDEEP CHSLNARs 40.62 crRs 35.87 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectARCHLAND ARCHITECTS
EngineerSHRIDHAR M SHET
EngineerVIRENDRA SHRIMANT DAINGADE
Chartered AccountantOMKAR CHANDAK
Chartered AccountantAMIT ANIL SHENDE
PartnerRole in project
Kotibhaskar Infrastructures &Developers Pvt.Ltd.-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA10032620165Mar 2026 → Sep 2026

Reason as filed by the promoterThe Finishing work of the project is remaining. We will require additional time to complete the Finishing Work and obtain the Completion Certificate from Pune Municipal Corporation of the said project.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 19 Apr 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 18 Apr 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 2 Aug 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 22 Jul 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed185

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 185 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Snehdeep Form 1 30062026_0001.pdf23 Jul 2026
Withdrawal Update Form 2File: Snehdeep Form 2 30062026_0001.pdf23 Jul 2026
Withdrawal Update Form 3File: Snehdeep Form3 30062026_0001_11zon.pdf23 Jul 2026
Withdrawal Update Form 1File: SBI Snehdeep Form-1 31032026.pdf21 Jul 2026
Withdrawal Update Form 1File: SBI Snehdeep Form-1 31032026.pdf21 Jul 2026
Withdrawal Update Form 2File: Snehdeep Form 2 30062026_0001.pdf21 Jul 2026
Withdrawal Update Form 2File: Snehdeep Form 2 30062026_0001.pdf21 Jul 2026
Withdrawal Update Form 3File: Snehdeep Form3 30062026_0001_11zon.pdf21 Jul 2026
Withdrawal Update Form 3File: Snehdeep Form3 30062026_0001_11zon.pdf21 Jul 2026
Withdrawal Update Form 1File: SBI Snehdeep Form-1 31032026.pdf29 Apr 2026
Withdrawal Update Form 2File: SBI Snehdeep Form-2-30032026.pdf29 Apr 2026
Withdrawal Update Form 3File: Snehdeep- Form-3-30032026.pdf29 Apr 2026
Withdrawal Update Form 1File: Snehdeep Form-1-15-01-2026.pdf20 Jan 2026
Withdrawal Update Form 2File: Snehdeep Form-2 31-12-2025_0001.pdf20 Jan 2026
Withdrawal Update Form 3File: Snehdeep Form-3 31-12-2025_0001.pdf20 Jan 2026
Form 5 (FY 2024-2025)File: SBI Snehdeep-Form-5-2024-25.pdf5 Nov 2025
Withdrawal Update Form 1File: Snehdeep Form-1-30092025-signed.pdf27 Oct 2025
Withdrawal Update Form 2File: SBI Snehdeep Form-2-30092025-signed.pdf27 Oct 2025
Withdrawal Update Form 3File: Snehdeep Form-3-30092025-signed.pdf27 Oct 2025
Building plan approvalFile: Scan 2025-6-18 (7,8,7)_1_11zon.pdf2 Aug 2025
Building plan approvalFile: Scan 2025-6-18 (7,9,37)_2_11zon.pdf2 Aug 2025
Building plan approvalFile: Scan 2025-6-18 (7,11,15)_3_11zon.pdf2 Aug 2025
Building plan approvalFile: Scan 2025-6-18 (7,12,12)_4_11zon.pdf2 Aug 2025
Building plan approvalFile: Scan 2025-6-18 (7,13,37)_5_11zon.pdf2 Aug 2025
Building plan approvalFile: Scan 2025-6-18 (7,15,18)_6_11zon.pdf2 Aug 2025
Withdrawal Update Form 1File: Snehdeep Form-1-30062025.pdf2 Aug 2025
Withdrawal Update Form 1File: Snehdeep Form-1-30062025.pdf2 Aug 2025
Withdrawal Update Form 2File: Snehdeep Form-2- 30-06-2025.pdf2 Aug 2025
Withdrawal Update Form 2File: Snehdeep Form-2- 30-06-2025.pdf2 Aug 2025
Withdrawal Update Form 3File: Snehdeep Form-3-15072025.pdf2 Aug 2025
Withdrawal Update Form 3File: Snehdeep Form-3-15072025.pdf2 Aug 2025
Commencement certificateFile: Snehdeep -CC-13062025.pdf22 Jul 2025
Building plan approvalFile: Scan 2025-6-18 (7,8,7)_1_11zon.pdf22 Jul 2025
Building plan approvalFile: Scan 2025-6-18 (7,9,37)_2_11zon.pdf22 Jul 2025
Building plan approvalFile: Scan 2025-6-18 (7,11,15)_3_11zon.pdf22 Jul 2025
Building plan approvalFile: Scan 2025-6-18 (7,12,12)_4_11zon.pdf22 Jul 2025
Building plan approvalFile: Scan 2025-6-18 (7,13,37)_5_11zon.pdf22 Jul 2025
Building plan approvalFile: Scan 2025-6-18 (7,15,18)_6_11zon.pdf22 Jul 2025
Building plan approvalFile: Scan 2025-6-18 (7,8,7)_1_11zon.pdf22 Jul 2025
Building plan approvalFile: Scan 2025-6-18 (7,9,37)_2_11zon.pdf22 Jul 2025
Building plan approvalFile: Scan 2025-6-18 (7,11,15)_3_11zon.pdf22 Jul 2025
Building plan approvalFile: Scan 2025-6-18 (7,12,12)_4_11zon.pdf22 Jul 2025
Building plan approvalFile: Scan 2025-6-18 (7,13,37)_5_11zon.pdf22 Jul 2025
Building plan approvalFile: Scan 2025-6-18 (7,15,18)_6_11zon.pdf22 Jul 2025
Withdrawal Update Form 1File: Snehdeep Form-1-30062025.pdf22 Jul 2025
Withdrawal Update Form 1File: Snehdeep Form-1-30062025.pdf22 Jul 2025
Withdrawal Update Form 1File: Snehdeep Form-1-30062025.pdf22 Jul 2025
Withdrawal Update Form 2File: Snehdeep Form-2- 30-06-2025.pdf22 Jul 2025
Withdrawal Update Form 2File: Snehdeep Form-2- 30-06-2025.pdf22 Jul 2025
Withdrawal Update Form 2File: Snehdeep Form-2- 30-06-2025.pdf22 Jul 2025
Withdrawal Update Form 3File: Snehdeep Form-3-15072025.pdf22 Jul 2025
Withdrawal Update Form 3File: Snehdeep Form-3-15072025.pdf22 Jul 2025
Withdrawal Update Form 3File: Snehdeep Form-3-15072025.pdf22 Jul 2025
Withdrawal Update Form 1File: Snehdeep Form-1-30062025.pdf21 Jul 2025
Withdrawal Update Form 2File: Snehdeep Form-2- 30-06-2025.pdf21 Jul 2025
Withdrawal Update Form 3File: Snehdeep Form-3-15072025.pdf21 Jul 2025
Form 2A (FY 2024-2025)File: Snehdeep Form 2A_0001.pdf12 Jun 2025
Form 2A (FY 2023-2024)File: Snehdeep Form 2A-23-24.pdf2 Jun 2025
Form 5 (FY 2023-2024)File: Snehdeep Form-5_0001.pdf2 Jun 2025
Form 1File: LG-SBI Snehdeep-Form 1-01082023.pdf16 May 2025
Form 2File: LG-Snehdeep-Form 2-10082023.pdf16 May 2025
Form 3File: LG-SBI Snehdeep-Form 3-07082023.pdf16 May 2025
Disclosure of Sold and Booked InventoryFile: LG-SBI Snehdeep-Sold Unsold Inventory-01082023.pdf16 May 2025
Form 1File: LG-SBI Snehdeep-Form 1-01082023.pdf16 May 2025
Form 2File: LG-Snehdeep-Form 2-10082023.pdf16 May 2025
Form 3File: LG-SBI Snehdeep-Sold Unsold Inventory-01082023.pdf16 May 2025
Disclosure of Sold and Booked InventoryFile: LG-SBI Snehdeep-Form 3-07082023.pdf16 May 2025
Form 1File: LG-SBI Snehdeep-Form 1-01082023.pdf16 May 2025
Form 2File: LG-SBI Snehdeep-Sold Unsold Inventory-01082023.pdf16 May 2025
Form 3File: LG-SBI Snehdeep-Form 3-07082023.pdf16 May 2025
Disclosure of Sold and Booked InventoryFile: LG-Snehdeep-Form 2-10082023.pdf16 May 2025
Form 1File: LG-SBI Snehdeep-Sold Unsold Inventory-01082023.pdf16 May 2025
Form 2File: LG-SBI Snehdeep-Form 1-01082023.pdf16 May 2025
Form 3File: LG-Snehdeep-Form 2-10082023.pdf16 May 2025
Disclosure of Sold and Booked InventoryFile: LG-SBI Snehdeep-Form 3-07082023.pdf16 May 2025
Form 1File: LG-SBI Snehdeep-Sold Unsold Inventory-01082023.pdf16 May 2025
Form 2File: LG-Snehdeep-Form 2-10082023.pdf16 May 2025
Form 3File: LG-SBI Snehdeep-Form 1-01082023.pdf16 May 2025
Disclosure of Sold and Booked InventoryFile: LG-SBI Snehdeep-Form 3-07082023.pdf16 May 2025
Form 1File: LG-SBI Snehdeep-Form 1-01082023.pdf16 May 2025

Promoter's earlier projects11

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

8 delivered on promise2 delivered late1 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
INDUKIRAN CO-OP HOUSING SOCIETY LIMITEDP52100046237KOTHRUD, Pune1Jun 2022CompletedNov 2025Oct 2024
SARITA CHSLP52100034229KOTHRUD, Pune70Mar 2022CompletedOct 2025May 2025
Purva HeightsP53100034113Warnali, Sangli36Mar 2022CompletedSep 2025Mar 2025
PRABHAKAR CHSLP52100049315Pune, Pune-Feb 2023CompletedJul 2025Apr 2025
Kajal Co operative Housing Society LtdP52100032652Kothrud, Pune67Jan 2022OngoingDec 2024Not delivered
MUKUNDP52100045860MAHARSHI KARVENAGAR, Pune-Jun 2022CompletedMay 2024Late, Jun 2024
SHUBHASHREEP52100045350PUNE, Pune-May 2022CompletedMar 2024Late, Jun 2024
AnnapurnaHingane Budruk Haveli Pune5-CompletedDec 2017Jun 2017
Ankoorshree Co-operative Housing SocietyHappy Colony Lane 3 Kothrud Pune21-CompletedOct 2017May 2017
Snehvardhan Co-operative Housing SocietyPatwardhan Co-operative Housing Society20-CompletedMay 2017Jan 2017
Chinar Co-operative Housing SocietyKothrud Pune24-CompletedMar 2014Mar 2014

How this compares with Pune

45%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 6 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep STATE BANK OF INDIA SNEHDEEP CHSL on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Pune13,700+ in Pune

Builder: Kotibhaskar Infrastructures &Developers Pvt.Ltd.

Kotibhaskar Infrastructures &Developers Pvt.Ltd. has 28 registrations on MahaRERA, including Sugam Cooperative Housing Society Limited and Vasant Vihar Co-operative Housing Society. Its filings disclose 11 earlier MahaRERA projects: declares 8 of 10 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if STATE BANK OF INDIA SNEHDEEP CHSL is delayed beyond 30 Sep 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of STATE BANK OF INDIA SNEHDEEP CHSL?

The registered promoter entity is Kotibhaskar Infrastructures &Developers Pvt.Ltd., a company as per the filing. Its CIN U45209PN2011PTC140254 and GSTIN 27AAQCS2145B1ZG can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in STATE BANK OF INDIA SNEHDEEP CHSL?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for STATE BANK OF INDIA SNEHDEEP CHSL?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at STATE BANK OF INDIA SNEHDEEP CHSL?

The professionals named in the filing: Architect: ARCHLAND ARCHITECTS; Engineer: SHRIDHAR M SHET; Engineer: VIRENDRA SHRIMANT DAINGADE; Chartered Accountant: OMKAR CHANDAK; Chartered Accountant: AMIT ANIL SHENDE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in STATE BANK OF INDIA SNEHDEEP CHSL?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About STATE BANK OF INDIA SNEHDEEP CHSL. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save STATE BANK OF INDIA SNEHDEEP CHSL to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.