ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / SPLENDID HOMES

Registered No litigation declared Residential / Group Housing project

SPLENDID HOMES

By PANDURANG MARUTI KALOKHE

RG-MH-21526 · RERA P52100029779 · Last updated on MahaRERA portal: 8 Sep 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 35 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Nov 2026Possession promisedmoved 35 months from the original
9 of 11Construction stages donefurthest along: Basement (if any), 0%
7 of 20Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 42 documents Report an error

SPLENDID HOMES is a Residential / Group Housing project by PANDURANG MARUTI KALOKHE in Pune, Maharashtra, registered with MahaRERA as P52100029779 on 29 Jun 2021. Possession is promised by 30 Nov 2026. The completion date has moved by 35 months from the original filing. 13 of the 20 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete.

At a glance

Project

  • NameSPLENDID HOMES
  • TypeResidential / Group Housing
  • Location
    • MUMBAI PUNE EXPRESSWAY SERVICE ROAD
    • NEAR SYMBIOSIS COLLEGE KIWALE
    • Pimpri Chinchawad (M Corp.)
    • Haveli
    • Pune
    • 412101
  • Pincode412101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100029779
  • ReraGenie IDRG-MH-21526

Builder

  • NamePANDURANG MARUTI KALOKHE
  • Entity typeIndividual
  • GSTIN27ABJPK9464E1ZC
  • Other registrations1 more →
  • Completed1 of 2

Key dates

this monthRegisteredJun 2021First promiseDec 2023Revised toNov 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on29 Jun 2021
  • Promised completion30 Nov 2026
  • Revised completionRevised to 30 Nov 2026 (originally 30 Dec 2023)
  • Buildings1 building record
  • Documents filed42 files

Current status

65%13 of 20 units booked
100.0%Work done, per cost certificate

Figures as on 8 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SPLENDID HOMESNA5520020

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 8 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.

SPLENDID HOMES: 82% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 8 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed20

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots20
Closed/Covered20

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area616 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on15 Aug 2026

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Apar Tahsildar
Permissible FSI1621.35
Proposed, not sanctioned1,297 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPCNT-411044
Estimated costRs 4.26 cr
Cost incurredRs 4.26 cr
Work done100.0%
BuildingWingEstimatedIncurred
SPLENDID HOMESNARs 4.26 crRs 4.26 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSANDEEP DANGE
EngineerGirish Desai
Chartered AccountantKAJAL KAMBLE
Chartered AccountantR J LAHOTI & CO
PartnerRole in project
PANDURANG MARUTI KALOKHE-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA20082622262Dec 2023 → Nov 2026

Reason as filed by the promoterOC is received for the project applying for an extension to complete the project procedures

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 22 Jun 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 1 Jan 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 1 Jan 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 1 Jan 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 16 Sep 2023

Documents filed42

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: kalokhe form1.pdf8 Sep 2026
Withdrawal Update Form 1File: kalokhe form1.pdf8 Sep 2026
Withdrawal Update Form 1File: kalokhe form1.pdf8 Sep 2026
Withdrawal Update Form 1File: kalokhe form1.pdf8 Sep 2026
Withdrawal Update Form 1File: kalokhe form1.pdf8 Sep 2026
Withdrawal Update Form 2File: form2kalokhe.pdf8 Sep 2026
Withdrawal Update Form 2File: form2kalokhe.pdf8 Sep 2026
Withdrawal Update Form 2File: form2kalokhe.pdf8 Sep 2026
Withdrawal Update Form 2File: form2kalokhe.pdf8 Sep 2026
Withdrawal Update Form 2File: form2kalokhe.pdf8 Sep 2026
Withdrawal Update Form 3File: form3kalokhe.pdf8 Sep 2026
Withdrawal Update Form 3File: form3kalokhe.pdf8 Sep 2026
Withdrawal Update Form 3File: form3kalokhe.pdf8 Sep 2026
Withdrawal Update Form 3File: form3kalokhe.pdf8 Sep 2026
Withdrawal Update Form 3File: form3kalokhe.pdf8 Sep 2026
Form 2A (FY 2025-2026)File: Form 2A.pdf8 Sep 2026
Withdrawal Update Form 1File: kalokhe form1.pdf20 Aug 2026
Withdrawal Update Form 2File: form2kalokhe.pdf20 Aug 2026
Withdrawal Update Form 3File: form3kalokhe.pdf20 Aug 2026
Architect’s Certificate on Completion of Project (Form 4)File: form4_splendid homes.pdf12 Nov 2024
Architect’s Certificate on Completion of Project (Form 4)File: form4_splendid homes.pdf12 Nov 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: COMPLETION.pdf16 Sep 2023
Layout approvalFile: MYSCAN_20211020_0001_compressed.pdf1 Jan 2022
Building plan approvalFile: MYSCAN_20211020_0001_compressed.pdf1 Jan 2022
Copy of Layout Approval (in case of layout)File: MYSCAN_20211020_0001_compressed.pdf1 Jan 2022
Building Plan Approval / NA Order for plotted developmentFile: MYSCAN_20211020_0001_compressed.pdf1 Jan 2022
Commencement Certificates / NA Order for plotted developmentFile: Scanned Documents.pdf1 Jan 2022
Declaration about Commencement CertificateFile: d_compressed_compressed.pdf23 Jun 2021
PAN CardFile: Pan.pdf22 Jun 2021
Copy of the legal title reportFile: FORMATA_compressed.pdf22 Jun 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect_compressed_compressed.pdf22 Jun 2021
Details of encumbrancesFile: ENC.pdf13 Jun 2021
Declaration in FORM BFile: Formb_compressed.pdf13 Jun 2021
Proforma of Allotment letterFile: Splendid Home Kalokhe kiwale Rera era draft-converted.pdf13 Jun 2021
Layout approvalFile: scan0066_compressed.pdf9 Jun 2021
Building plan approvalFile: scan0066_compressed.pdf9 Jun 2021
Copy of Layout Approval (in case of layout)File: scan0066_compressed.pdf9 Jun 2021
Building Plan Approval / NA Order for plotted developmentFile: scan0066_compressed.pdf9 Jun 2021
Commencement Certificates / NA Order for plotted developmentFile: naorder.pdf9 Jun 2021
Commencement Certificates / NA Order for plotted developmentFile: commencement _compressed.pdf9 Jun 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: cacert_compressed.pdf9 Jun 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: cacert_compressed.pdf9 Jun 2021

How this compares with Pune

65%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 35 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SPLENDID HOMES on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near NEAR SYMBIOSIS COLLEGE KIWALE13,700+ in Pune

2 kmSPLENDID HOMESCompleted 81Lapsed / revoked 48Other 111Dot size: filed unitsN

Filed coordinates, straight-line distance. 240 registered projects within 2 km.

Builder: PANDURANG MARUTI KALOKHE

PANDURANG MARUTI KALOKHE has 2 registrations on MahaRERA, including KRISHNA CLASSIC and SPLENDID HOMES. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if SPLENDID HOMES is delayed beyond 30 Nov 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SPLENDID HOMES?

The registered promoter entity is PANDURANG MARUTI KALOKHE, an individual as per the filing. Its GSTIN 27ABJPK9464E1ZC can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SPLENDID HOMES?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SPLENDID HOMES?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SPLENDID HOMES?

The professionals named in the filing: Architect: SANDEEP DANGE; Engineer: Girish Desai; Chartered Accountant: KAJAL KAMBLE; Chartered Accountant: R J LAHOTI & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SPLENDID HOMES?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SPLENDID HOMES. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SPLENDID HOMES to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.