ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / SONIGARA PRESIDENCY PHASE II

Registration lapsed No litigation declared Residential / Group Housing project

SONIGARA PRESIDENCY PHASE II

By DHANASHRI CONSTRUCTION

RG-MH-21505 · RERA P52100030017 · Last updated on MahaRERA portal: 30 Jun 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 16 months past the filed date
  • Completion date moved by 6 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2025Possession promised16 months past this date
16 of 22Construction stages doneacross 2 buildings; furthest along: Installation of Lifts, 90%
15 of 218Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 117 documents Report an error

SONIGARA PRESIDENCY PHASE II is a Residential / Group Housing project by DHANASHRI CONSTRUCTION in Pune, Maharashtra, registered with MahaRERA as P52100030017 on 26 Jul 2021. Possession was promised by 30 Jun 2025 and is now 16 months past that date. The completion date has moved by 6 months from the original filing. 203 of the 218 units on this registration are recorded sold or booked, and 16 of 22 construction stages are filed complete.

At a glance

Project

  • NameSONIGARA PRESIDENCY PHASE II
  • TypeResidential / Group Housing
  • Location
    • MASKE WASTI ROAD RAVET
    • RAVET
    • Pimpri Chinchawad (M Corp.)
    • Haveli
    • Pune
    • 412101
  • Pincode412101
  • RERA no.P52100030017
  • ReraGenie IDRG-MH-21505

Builder

  • NameDHANASHRI CONSTRUCTION
  • Entity typePartnership
  • PartnersAMRIT KESARIMAL SONIGARA, RAHUL RAMESH SONIGARA, SHAILENDRA KRISHNARAO GHORPADE
  • Other registrations1 more →
  • Completed1 of 2
  • No longer live1 lapsed, de-registered or revoked

Key dates

16 months past promisethis monthRegisteredJul 2021First promiseDec 2024Revised toJun 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on26 Jul 2021
  • Promised completion30 Jun 2025
  • Revised completionRevised to 30 Jun 2025 (originally 31 Dec 2024)
  • Buildings2 building records
  • Documents filed117 files

Current status

93%203 of 218 units booked

Figures as on 30 Jun 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
C WINGNA22181440144
D WINGNA211874074

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 30 Jun 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

16 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Installation of Lifts, at 90%.

C WING87%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises65%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
D WING87%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises65%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 30 Jun 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes0%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes50%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Parking filed2

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots2
Closed/Covered2
BuildingClosed/CoveredTotal
C WING11
D WING11

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area6,793 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on30 Jun 2025
LandownerVillageDistrict
SONIGARA AND BHOSALE ASSOCIATESPimpri Chinchawad (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPIMPRI CHINCHWAD MUNCIPAL CORPORATION
Permissible FSI20102.33
Proposed, not sanctioned13,485 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGROUND FLOOR MAKER CHAMBERS IV NARIMAN POINT

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectADITYA A PUNGAVKAR & SATYAJEET INAMDAR
ArchitectI P ASSOCIATES
EngineerMAHADEV VITTHAL HATMODE
Chartered AccountantNAVDEEP JINDAL
Chartered AccountantPRACHI S AGARWAL
PartnerRole in project
DHANASHRI CONSTRUCTION-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100027148Dec 2024 → Jun 2025

Reason as filed by the promoterCOMPLICTION PENDING AND SITE DEVELOPMENT WORK PENDING 5%

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Jun 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 17 Jul 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Oct 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Oct 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed117

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 117 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: FORM1.pdf30 Jun 2025
Form 2File: FORM2.pdf30 Jun 2025
Form 3File: FORM3 Signed.pdf30 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold-Booked Inventory Dec 24.pdf30 Jun 2025
Form 1File: Form 1 Sep 24.pdf30 Jun 2025
Form 2File: Form 2 Sep 24.pdf30 Jun 2025
Form 3File: Dhanashri Construction From-3 Signed_compressed.pdf30 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold-Booked Inventory sep 24.pdf30 Jun 2025
Form 1File: Form 1 Sep 23 ARCHI 30-09-2023.pdf30 Jun 2025
Form 2File: Form 2 Sep 23.pdf30 Jun 2025
Form 3File: FORM 3 Signed_compressed.pdf30 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of sold-Booked Inventory SEP 23.pdf30 Jun 2025
Form 5 (FY 2024-2025)File: Audit Report DHANASHRI CONSTRUCTION Signed.pdf30 Jun 2025
Form 5 (FY 2023-2024)File: form 5.pdf30 Jun 2025
Form 5 (FY 2022-2023)File: form 5_signed.pdf30 Jun 2025
Form 5 (FY 2021-2022)File: form 5.pdf30 Jun 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM5.pdf6 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1.pdf4 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM3.pdf4 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2.pdf4 Feb 2025
Disclosure of sold/ booked inventoryFile: DOF SOLD_compressed.pdf4 Feb 2025
Declaration in FORM BFile: FORM B.pdf1 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: form 2A 2020-21.pdf1 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM2A 2021-22.pdf1 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A 2022-23.pdf1 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM2A 2023-24.pdf1 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1.pdf31 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5.pdf31 Jan 2025
OtherFile: doc01162920250127191720_001.pdf27 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHI.pdf23 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA.pdf23 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2.pdf23 Nov 2024
Commencement Certificates / NA Order for plotted developmentFile: 14-10-2024 CC.pdf24 Oct 2024
Building plan approvalFile: 22 NOS.pdf13 Oct 2024
Building plan approvalFile: 23.pdf13 Oct 2024
Building plan approvalFile: 24.pdf13 Oct 2024
Building plan approvalFile: 26.pdf13 Oct 2024
Building plan approvalFile: 27.pdf13 Oct 2024
Building plan approvalFile: 1.pdf13 Oct 2024
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf13 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: 24.pdf13 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: 1.pdf13 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: 27.pdf13 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: 26.pdf13 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: 23.pdf13 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: 22 NOS.pdf13 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA SP.pdf5 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: CD ARCHI_compressed (1).pdf24 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM3_compressed.pdf24 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Audit Report DHANASHRI CONSTRUCTION.pdf25 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHI 30-09-2023_compressed.pdf12 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGI 30-09-2023.pdf12 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA 30-09-2023.pdf12 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: dhanashree form 3_compressed_compressed.pdf15 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHI_compressed.pdf4 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 2021 22 DHANASHRI.pdf4 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 2021 22 DHANASHRI.pdf2 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_compressed.pdf7 Dec 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3 Dhanashri Construction_compressed.pdf17 Sep 2022
Details of encumbrancesFile: DHANASHRI LETTER LOAN EN.pdf26 Jun 2022
Details of encumbrancesFile: MORT1.pdf26 Jun 2022
Details of encumbrancesFile: MORT2.pdf26 Jun 2022
Details of encumbrancesFile: MORT3.pdf26 Jun 2022
Details of encumbrancesFile: MORT4.pdf26 Jun 2022
Details of encumbrancesFile: MORT5.pdf26 Jun 2022
Details of encumbrancesFile: MORT6.pdf26 Jun 2022
Details of encumbrancesFile: MORT7.pdf26 Jun 2022
Details of encumbrancesFile: MORT8.pdf26 Jun 2022
Details of encumbrancesFile: MORT9.pdf26 Jun 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 31-03-2022 CA 1.pdf5 Jun 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA2.pdf5 Jun 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTS.pdf7 Jan 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE.pdf7 Jan 2022
Layout approvalFile: AMAL.pdf17 Jul 2021
Copy of Layout Approval (in case of layout)File: AMAL.pdf17 Jul 2021
Declaration in FORM BFile: DE 11.pdf17 Jul 2021
Declaration in FORM BFile: SALE1.pdf17 Jul 2021
Declaration in FORM BFile: SALE2.pdf17 Jul 2021
Declaration in FORM BFile: SALE3.pdf17 Jul 2021
Declaration in FORM BFile: SALE4.pdf17 Jul 2021

How this compares with Pune

93%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 6 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SONIGARA PRESIDENCY PHASE II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near RAVET13,700+ in Pune

Builder: DHANASHRI CONSTRUCTION

DHANASHRI CONSTRUCTION has 2 registrations on MahaRERA, including SONIGARA PRESIDENCY PHASE II and 97 SONIGARA BIZZ. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that SONIGARA PRESIDENCY PHASE II shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SONIGARA PRESIDENCY PHASE II is delayed beyond 30 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SONIGARA PRESIDENCY PHASE II?

The registered promoter entity is DHANASHRI CONSTRUCTION, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SONIGARA PRESIDENCY PHASE II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SONIGARA PRESIDENCY PHASE II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SONIGARA PRESIDENCY PHASE II?

The professionals named in the filing: Architect: ADITYA A PUNGAVKAR & SATYAJEET INAMDAR; Architect: I P ASSOCIATES; Engineer: MAHADEV VITTHAL HATMODE; Chartered Accountant: NAVDEEP JINDAL; Chartered Accountant: PRACHI S AGARWAL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SONIGARA PRESIDENCY PHASE II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SONIGARA PRESIDENCY PHASE II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SONIGARA PRESIDENCY PHASE II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.