Home / Browse projects / Pune, Maharashtra / SONIGARA PRESIDENCY PHASE II
SONIGARA PRESIDENCY PHASE II
RG-MH-21505 · RERA P52100030017 · Last updated on MahaRERA portal: 30 Jun 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 16 months past the filed date
- Completion date moved by 6 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SONIGARA PRESIDENCY PHASE II is a Residential / Group Housing project by DHANASHRI CONSTRUCTION in Pune, Maharashtra, registered with MahaRERA as P52100030017 on 26 Jul 2021. Possession was promised by 30 Jun 2025 and is now 16 months past that date. The completion date has moved by 6 months from the original filing. 203 of the 218 units on this registration are recorded sold or booked, and 16 of 22 construction stages are filed complete.
At a glance
Project
- NameSONIGARA PRESIDENCY PHASE II
- TypeResidential / Group Housing
- Location
- MASKE WASTI ROAD RAVET
- RAVET
- Pimpri Chinchawad (M Corp.)
- Haveli
- Pune
- 412101
- Pincode412101
- RERA no.P52100030017
- ReraGenie IDRG-MH-21505
Builder
- NameDHANASHRI CONSTRUCTION
- Entity typePartnership
- PartnersAMRIT KESARIMAL SONIGARA, RAHUL RAMESH SONIGARA, SHAILENDRA KRISHNARAO GHORPADE
- Other registrations1 more →
- Completed1 of 2
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on26 Jul 2021
- Promised completion30 Jun 2025
- Revised completionRevised to 30 Jun 2025 (originally 31 Dec 2024)
- Buildings2 building records
- Documents filed117 files
Current status
Figures as on 30 Jun 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| C WING | NA | 22 | 18 | 144 | 0 | 144 |
| D WING | NA | 21 | 18 | 74 | 0 | 74 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 30 Jun 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
16 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Installation of Lifts, at 90%.
C WING87%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 65% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
D WING87%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 65% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
Progress on shared amenities15
As on 30 Jun 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 50% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | No | Not applicable |
Parking filed2
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| C WING | 1 | 1 |
| D WING | 1 | 1 |
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| SONIGARA AND BHOSALE ASSOCIATES | Pimpri Chinchawad (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ADITYA A PUNGAVKAR & SATYAJEET INAMDAR |
| Architect | I P ASSOCIATES |
| Engineer | MAHADEV VITTHAL HATMODE |
| Chartered Accountant | NAVDEEP JINDAL |
| Chartered Accountant | PRACHI S AGARWAL |
| Partner | Role in project |
|---|---|
| DHANASHRI CONSTRUCTION | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterCOMPLICTION PENDING AND SITE DEVELOPMENT WORK PENDING 5%
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 26 Jun 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 17 Jul 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 13 Oct 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 24 Oct 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed117
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 117 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: FORM1.pdf | 30 Jun 2025 |
| Form 2File: FORM2.pdf | 30 Jun 2025 |
| Form 3File: FORM3 Signed.pdf | 30 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold-Booked Inventory Dec 24.pdf | 30 Jun 2025 |
| Form 1File: Form 1 Sep 24.pdf | 30 Jun 2025 |
| Form 2File: Form 2 Sep 24.pdf | 30 Jun 2025 |
| Form 3File: Dhanashri Construction From-3 Signed_compressed.pdf | 30 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold-Booked Inventory sep 24.pdf | 30 Jun 2025 |
| Form 1File: Form 1 Sep 23 ARCHI 30-09-2023.pdf | 30 Jun 2025 |
| Form 2File: Form 2 Sep 23.pdf | 30 Jun 2025 |
| Form 3File: FORM 3 Signed_compressed.pdf | 30 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold-Booked Inventory SEP 23.pdf | 30 Jun 2025 |
| Form 5 (FY 2024-2025)File: Audit Report DHANASHRI CONSTRUCTION Signed.pdf | 30 Jun 2025 |
| Form 5 (FY 2023-2024)File: form 5.pdf | 30 Jun 2025 |
| Form 5 (FY 2022-2023)File: form 5_signed.pdf | 30 Jun 2025 |
| Form 5 (FY 2021-2022)File: form 5.pdf | 30 Jun 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM5.pdf | 6 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1.pdf | 4 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM3.pdf | 4 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2.pdf | 4 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: DOF SOLD_compressed.pdf | 4 Feb 2025 |
| Declaration in FORM BFile: FORM B.pdf | 1 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: form 2A 2020-21.pdf | 1 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM2A 2021-22.pdf | 1 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A 2022-23.pdf | 1 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM2A 2023-24.pdf | 1 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1.pdf | 31 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5.pdf | 31 Jan 2025 |
| OtherFile: doc01162920250127191720_001.pdf | 27 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHI.pdf | 23 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA.pdf | 23 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM2.pdf | 23 Nov 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: 14-10-2024 CC.pdf | 24 Oct 2024 |
| Building plan approvalFile: 22 NOS.pdf | 13 Oct 2024 |
| Building plan approvalFile: 23.pdf | 13 Oct 2024 |
| Building plan approvalFile: 24.pdf | 13 Oct 2024 |
| Building plan approvalFile: 26.pdf | 13 Oct 2024 |
| Building plan approvalFile: 27.pdf | 13 Oct 2024 |
| Building plan approvalFile: 1.pdf | 13 Oct 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: CC.pdf | 13 Oct 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 24.pdf | 13 Oct 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 1.pdf | 13 Oct 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 27.pdf | 13 Oct 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 26.pdf | 13 Oct 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 23.pdf | 13 Oct 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 22 NOS.pdf | 13 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA SP.pdf | 5 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: CD ARCHI_compressed (1).pdf | 24 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM3_compressed.pdf | 24 Apr 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Audit Report DHANASHRI CONSTRUCTION.pdf | 25 Nov 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHI 30-09-2023_compressed.pdf | 12 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGI 30-09-2023.pdf | 12 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA 30-09-2023.pdf | 12 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: dhanashree form 3_compressed_compressed.pdf | 15 May 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHI_compressed.pdf | 4 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 2021 22 DHANASHRI.pdf | 4 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 2021 22 DHANASHRI.pdf | 2 Feb 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_compressed.pdf | 7 Dec 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3 Dhanashri Construction_compressed.pdf | 17 Sep 2022 |
| Details of encumbrancesFile: DHANASHRI LETTER LOAN EN.pdf | 26 Jun 2022 |
| Details of encumbrancesFile: MORT1.pdf | 26 Jun 2022 |
| Details of encumbrancesFile: MORT2.pdf | 26 Jun 2022 |
| Details of encumbrancesFile: MORT3.pdf | 26 Jun 2022 |
| Details of encumbrancesFile: MORT4.pdf | 26 Jun 2022 |
| Details of encumbrancesFile: MORT5.pdf | 26 Jun 2022 |
| Details of encumbrancesFile: MORT6.pdf | 26 Jun 2022 |
| Details of encumbrancesFile: MORT7.pdf | 26 Jun 2022 |
| Details of encumbrancesFile: MORT8.pdf | 26 Jun 2022 |
| Details of encumbrancesFile: MORT9.pdf | 26 Jun 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 31-03-2022 CA 1.pdf | 5 Jun 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA2.pdf | 5 Jun 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTS.pdf | 7 Jan 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE.pdf | 7 Jan 2022 |
| Layout approvalFile: AMAL.pdf | 17 Jul 2021 |
| Copy of Layout Approval (in case of layout)File: AMAL.pdf | 17 Jul 2021 |
| Declaration in FORM BFile: DE 11.pdf | 17 Jul 2021 |
| Declaration in FORM BFile: SALE1.pdf | 17 Jul 2021 |
| Declaration in FORM BFile: SALE2.pdf | 17 Jul 2021 |
| Declaration in FORM BFile: SALE3.pdf | 17 Jul 2021 |
| Declaration in FORM BFile: SALE4.pdf | 17 Jul 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration, which the RERA portal never shows together
- All 117 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep SONIGARA PRESIDENCY PHASE II on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near RAVET13,700+ in Pune
Godrej Park Greens
Godrej Skyline Developers Limited
FOREST GROVE AT GODREJ PARK GREENS
Godrej Skyline Developers Limited
Om Mangalam Samruddhi
NDG Homes LLP
PCMC EWS KIWALE
Pimpri Chinchwad Municipal Corporation
Godrej Nurture
Godrej Skyline Developers Limited
My Home Sanctuary Phase I
MAMURDI DEVELOPERS LLP
Builder: DHANASHRI CONSTRUCTION
DHANASHRI CONSTRUCTION has 2 registrations on MahaRERA, including SONIGARA PRESIDENCY PHASE II and 97 SONIGARA BIZZ. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that SONIGARA PRESIDENCY PHASE II shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if SONIGARA PRESIDENCY PHASE II is delayed beyond 30 Jun 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SONIGARA PRESIDENCY PHASE II?
The registered promoter entity is DHANASHRI CONSTRUCTION, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SONIGARA PRESIDENCY PHASE II?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SONIGARA PRESIDENCY PHASE II?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SONIGARA PRESIDENCY PHASE II?
The professionals named in the filing: Architect: ADITYA A PUNGAVKAR & SATYAJEET INAMDAR; Architect: I P ASSOCIATES; Engineer: MAHADEV VITTHAL HATMODE; Chartered Accountant: NAVDEEP JINDAL; Chartered Accountant: PRACHI S AGARWAL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SONIGARA PRESIDENCY PHASE II?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback