ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / SOLITAIRE BUSINESS HUB KALYANINAGAR

Completed Litigation declared Commercial project

SOLITAIRE BUSINESS HUB KALYANINAGAR

By CLASSIC PROMOTERS & BUILDERS PVT LTD

RG-MH-62958 · RERA P52100014846 · Last updated on MahaRERA portal: 28 Jan 2025

Source: official MahaRERA filing

Red flags

  • Litigation declared, 2 cases
  • 6 complaints at MahaRERA
  • Completion date moved by 18 months
  • 1 extension taken

Clear

  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 1 earlier projects delivered on promise

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2024Possession promisedregistration recorded completed
15 of 33Construction stages doneacross 3 buildings; furthest along: Internal walls, 80%
6Complaints at MahaRERAon this registration
Jump to the 190 documents Report an error

SOLITAIRE BUSINESS HUB KALYANINAGAR is a Commercial project by CLASSIC PROMOTERS & BUILDERS PVT LTD in Pune, Maharashtra, registered with MahaRERA as P52100014846 on 8 Jan 2018. The registration is recorded completed; possession was promised by 29 Dec 2024. The completion date has moved by 18 months from the original filing. 6 complaints are on record with the regulator.

At a glance

Project

  • NameSOLITAIRE BUSINESS HUB KALYANINAGAR
  • TypeCommercial
  • Location
    • KALYANI NAGAR
    • YERWADA
    • Ghorpadi
    • Haveli
    • Pune
    • 411014
  • Pincode411014
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100014846
  • ReraGenie IDRG-MH-62958

Builder

  • NameCLASSIC PROMOTERS & BUILDERS PVT LTD
  • Entity typeCompany
  • CINU70101MH1988PTC047131
  • GSTIN27AABCC1200C1ZN
  • Managing DirectorASHOK DHANRAJ CHORDIA
  • Declared earlier projects1 →

Key dates

this monthRegisteredJan 2018First promiseJun 2023Revised toDec 2024Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on8 Jan 2018
  • Promised completion29 Dec 2024
  • Revised completionRevised to 29 Dec 2024 (originally 30 Jun 2023)
  • Buildings3 building records
  • Documents filed190 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building - 1 - Upper Gr Floor To 4th FloorNA90000
Building - 2 - 5th Floor To 10th FloorNA60000
Building ThreeNA00000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 28 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

15 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Internal walls, at 80%.

Building - 1 - Upper Gr Floor To 4th Floor68%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises5%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.59%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.34%
Building - 2 - 5th Floor To 10th Floor68%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises5%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.59%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.34%
Building Three68%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises5%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.59%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.34%

Progress on shared amenities15

As on 28 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes25%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes35%
Storm Water DrainsYes35%
Landscaping & Tree PlantingYes20%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes30%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes50%
Energy managemcntYes5%
Fire protection and fire safety requirementsYes86%
Electrical meter room, sub-station, receiving stationYes20%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed202

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots202
Closed/Covered202
BuildingClosed/CoveredTotal
Building - 1 - Upper Gr Floor To 4th Floor102102
Building - 2 - 5th Floor To 10th Floor100100

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,162 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI8697.0
Proposed, not sanctioned8,697 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBHANDARKAR ROAD BRANCH

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAmit Ghate
EngineerG.A. Bhilare Consultants Private Limited
Chartered AccountantS P A K & Co
Chartered AccountantRSVA & Co
PartnerRole in project
CLASSIC PROMOTERS & BUILDERS PVT LTD-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100017944Jun 2023 → Dec 2024

Reason as filed by the promoterWe, Classic Promoters And Builders Private Limited, are developing a Commercial project named Solitaire Business Hub Kalyaninagar. The project was registered with MahaRERA and was due to be completed on 30-12-2023. However, due to the COVID-19 pandemic, we faced several challenges that adversely affected the construction activities and the sales of the project. Some of these challenges were: • Lack of availability of labour contractors as many of them migrated back to their native places during the lockdown. • Disruption of supply chain of essential construction materials such as cement, steel

Litigation declared2

CaseCourtStatus
OMP I COMM 154/2017/2017HIGH COURT DELHICASE DISMISSED
OMP I COMM 154/2017/2017HIGH COURT DELHIClosed

Complaints filed with MahaRERA6

Case no.ComplainantRespondentFiled
CC005000000106391Amit Kumar GandhiClassic Promoters and Builders Private Limited20/12/2021
CC005000000116942Classic Promoters & Builders Pvt. Ltd.Dinesh Vasudev Chhutani23/04/2022
CC12502148Abhiraaj Sanjeev KulkarniCLASSIC PROMOTERS & BUILDERS PVT LTD29/06/2025
CC12502245DSIJ PRIVATE LIMITEDCLASSIC PROMOTERS & BUILDERS PVT LTD05/07/2025
CC12503496CLASSIC PROMOTERS & BUILDERS PVT LTDNVM AGRO PRIVATE LIMITED30/09/2025
CC12601562DSIJ PRIVATE LIMITEDCLASSIC PROMOTERS & BUILDERS PVT LTD21/03/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 19 Oct 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Mar 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Mar 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Mar 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 31 Dec 2024

Documents filed190

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 190 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - SBH Kalyaninagar - Dec 24.pdf28 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - SBH Kalyaninagar - Dec 24.pdf25 Jan 2025
Certificates of CA (Form 3)File: Form 3_CA KN_Dec 2024.pdf23 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 Engineer certificate _Kalyani Nagar_DEC-24.pdf23 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold Disclosure - SBH KN - Dec 24.pdf20 Jan 2025
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 - SBH Kalyaninagar.pdf15 Jan 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: SBH - Kalyaninagar - PMC OC Verification.pdf31 Dec 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: SBH KN Full Completion.pdf26 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: SBH KN - Form 5 - FY 23-24.pdf24 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - SBH KN - Sept 24.pdf21 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 7 Form 1 - SBH KN - Sept 2024 - Bldg 2.pdf19 Oct 2024
Disclosure of sold/ booked inventoryFile: 8 Sold Discloure - SBH KN - Sept 2024.pdf19 Oct 2024
Disclosure of sold/ booked inventoryFile: Sold Disclosure - SBH KN - Mar 2024.pdf8 Aug 2024
Disclosure of sold/ booked inventoryFile: SBH Kalyaninagar Merged.pdf31 Jul 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: SBH Kalyani Nagar Part Completion.pdf19 Jul 2024
Disclosure of sold/ booked inventoryFile: SBH KN Dec 23 Sold Disclosure.pdf20 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: From 2A - SBH KN - Dec 23.pdf8 Jan 2024
Declaration in FORM BFile: SBH KN - from B - RERA Extension (1).pdf21 Nov 2023
Declaration in FORM BFile: P52100014846_FileName_2.pdf20 Nov 2023
Disclosure of sold/ booked inventoryFile: SBH KN - Sept 23 Sold Disclosure.pdf20 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 SBH KN - Sept 23.pdf18 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - SBH KN FY 22-23.pdf13 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A - SBH KN Sept 2023.pdf6 Oct 2023
Disclosure of sold/ booked inventoryFile: SBH KN - Bldg 1.pdf20 Sep 2023
Disclosure of sold/ booked inventoryFile: SBH KN - Bldg 2.pdf20 Sep 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 SBH KN.pdf11 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A SBH KN.pdf11 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 SBH KN March-2023.pdf11 May 2023
Disclosure of sold/ booked inventoryFile: SBH Kalaninagar_March23.pdf11 May 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: KN.pdf21 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A SBH KN March 2023.pdf12 Apr 2023
Layout approvalFile: 1.pdf28 Mar 2023
Layout approvalFile: 2.pdf28 Mar 2023
Layout approvalFile: 3.pdf28 Mar 2023
Building plan approvalFile: 2.pdf28 Mar 2023
Building plan approvalFile: 2.pdf28 Mar 2023
Building plan approvalFile: 3.pdf28 Mar 2023
Building plan approvalFile: 4.pdf28 Mar 2023
Building plan approvalFile: 5.pdf28 Mar 2023
Building plan approvalFile: 6.pdf28 Mar 2023
Building plan approvalFile: 7.pdf28 Mar 2023
Building plan approvalFile: 8.pdf28 Mar 2023
Building plan approvalFile: 9.pdf28 Mar 2023
Building plan approvalFile: 10.pdf28 Mar 2023
Building plan approvalFile: 11.pdf28 Mar 2023
Building plan approvalFile: 12.pdf28 Mar 2023
Copy of Layout Approval (in case of layout)File: 1.pdf28 Mar 2023
Copy of Layout Approval (in case of layout)File: 2.pdf28 Mar 2023
Copy of Layout Approval (in case of layout)File: 3.pdf28 Mar 2023
Building Plan Approval (IOD)File: 2.pdf28 Mar 2023
Building Plan Approval (IOD)File: 2.pdf28 Mar 2023
Building Plan Approval (IOD)File: 3.pdf28 Mar 2023
Building Plan Approval (IOD)File: 4.pdf28 Mar 2023
Building Plan Approval (IOD)File: 5.pdf28 Mar 2023
Building Plan Approval (IOD)File: 6.pdf28 Mar 2023
Building Plan Approval (IOD)File: 7.pdf28 Mar 2023
Building Plan Approval (IOD)File: 8.pdf28 Mar 2023
Building Plan Approval (IOD)File: 9.pdf28 Mar 2023
Building Plan Approval (IOD)File: 10.pdf28 Mar 2023
Building Plan Approval (IOD)File: 11.pdf28 Mar 2023
Building Plan Approval (IOD)File: 12.pdf28 Mar 2023
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf28 Mar 2023
Declaration about Commencement CertificateFile: Declaration of CC.pdf28 Mar 2023
Disclosure of sold/ booked inventoryFile: Sold_Disclosure_SBH_KN_Dec_22.pdf27 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A SBH Kalyani Nagar Dec-22.pdf20 Jan 2023
Disclosure of sold/ booked inventoryFile: SBH_KN_PH1_Sep_22.pdf21 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)SBH Kalyani nagar.pdf30 Sep 2022
Disclosure of sold/ booked inventoryFile: SBH KN - Bldg 1.pdf11 Aug 2022
Disclosure of sold/ booked inventoryFile: SBH KN - Bldg -2.pdf11 Aug 2022
CERSAI detailsFile: CERSAI_Search_Report.pdf8 Aug 2022
Declaration about Commencement CertificateFile: SBH KN.pdf7 Apr 2022
Declaration about Commencement CertificateFile: 11 SBH KN DEC 2021.pdf8 Jan 2022
Disclosure of sold/ booked inventoryFile: SBH KN - Building 1-2 Sold Disclosure Dec 2021.pdf8 Jan 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: KN Mar 20 P1_P2_merged.pdf10 Nov 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: KN Mar 21 P1_P2_merged.pdf10 Nov 2021
Copy of the legal title reportFile: Supplemental_TSR_SBH KALYANI NAGAR_29092021_compressed.pdf19 Oct 2021
Declaration about Commencement CertificateFile: kn dd.pdf19 Oct 2021
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD SBH KN B1.pdf8 Oct 2021
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD SBH KN B2.pdf8 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: SBH KalayaniNagar.pdf30 Sep 2021

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsRegisteredStatusPromisedDelivered
AVALON CITY C-3P52100003105Pune, Pune48Aug 2017CompletedDec 2021Registered original: Dec 2019Feb 2020

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 18 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SOLITAIRE BUSINESS HUB KALYANINAGAR on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near YERWADA13,700+ in Pune

2 kmSOLITAIRE BUSINESS HUB KCompleted 13Lapsed / revoked 8Dot size: filed unitsN

Filed coordinates, straight-line distance. 21 registered projects within 2 km.

Builder: CLASSIC PROMOTERS & BUILDERS PVT LTD

CLASSIC PROMOTERS & BUILDERS PVT LTD has 1 registration on MahaRERA, including SOLITAIRE BUSINESS HUB KALYANINAGAR. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if SOLITAIRE BUSINESS HUB KALYANINAGAR is delayed beyond 29 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SOLITAIRE BUSINESS HUB KALYANINAGAR?

The registered promoter entity is CLASSIC PROMOTERS & BUILDERS PVT LTD, a company as per the filing. Its CIN U70101MH1988PTC047131 and GSTIN 27AABCC1200C1ZN can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SOLITAIRE BUSINESS HUB KALYANINAGAR?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SOLITAIRE BUSINESS HUB KALYANINAGAR?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SOLITAIRE BUSINESS HUB KALYANINAGAR?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SOLITAIRE BUSINESS HUB KALYANINAGAR?

The professionals named in the filing: Architect: Amit Ghate; Engineer: G.A. Bhilare Consultants Private Limited; Chartered Accountant: S P A K & Co; Chartered Accountant: RSVA & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SOLITAIRE BUSINESS HUB KALYANINAGAR?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SOLITAIRE BUSINESS HUB KALYANINAGAR. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SOLITAIRE BUSINESS HUB KALYANINAGAR to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.