SKYREEN
RG-MH-16810 · RERA P52100027714 · Last updated on MahaRERA portal: 31 May 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 24 months past the filed date
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SKYREEN is a Residential / Group Housing project by NILIMA PRAFULLA BADHE in Pune, Maharashtra, registered with MahaRERA as P52100027714 on 3 Jan 2021. Possession was promised by 29 Oct 2024 and is now 24 months past that date. The completion date has moved by 12 months from the original filing.
At a glance
Project
- NameSKYREEN
- TypeResidential / Group Housing
- Location
- Survey No.94
- Plot no 10 and 17
- Near S B Patil Public School
- Ravet
- Pune 412101.
- RAVET
- Pimpri Chinchawad (M Corp.)
- Haveli
- Pune
- 412101
- Pincode412101
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100027714
- ReraGenie IDRG-MH-16810
Builder
- NameNILIMA PRAFULLA BADHE
- Entity typeIndividual
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on3 Jan 2021
- Promised completion29 Oct 2024
- Revised completionRevised to 29 Oct 2024 (originally 30 Oct 2023)
- Buildings1 building record
- Documents filed144 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SKYREEN | NA | 6 | 4 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 31 May 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 0%.
SKYREEN: 0% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 31 May 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed60
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership3
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Nalini Chandramohan Pawar | Pimpri Chinchawad (M Corp.) | Pune |
| Vinod Kumaran Nair | - | Palakkad |
| Vivek Anandeshwar Bhamodkar | Gahunje | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Ar Kaustubh Babar |
| Engineer | P S Badhe |
| Chartered Accountant | SPAK & Co |
| Partner | Role in project |
|---|---|
| NILIMA PRAFULLA BADHE | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to the Covid-19 pandemic we were not able to construct anymore because of lack of labor contractors and the poor market condition we were unable to complete the project within the due time. Hence, we request you to kindly allow us an extension till 29/10/2024.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 31 Oct 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 31 Jan 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 31 Oct 2020 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 31 Jan 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed144
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 144 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: 1 1-4-2021 Mar-21.pdf | 31 May 2025 |
| Form 2File: 1 form 2 07 04 2021 Mar-21.pdf | 31 May 2025 |
| Form 3File: 1 Skyreen Form-3 Mar-21 Done.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: 1 Mar 21.pdf | 31 May 2025 |
| Form 1File: 2 1-7-2021 Jun-21.pdf | 31 May 2025 |
| Form 2File: 2 form 2 june 2021.pdf | 31 May 2025 |
| Form 3File: 2 Skyreen Form-3 Jun-21 Done.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: 2 Jun 21.pdf | 31 May 2025 |
| Form 1File: 3 1-10-2021 Sep-21.pdf | 31 May 2025 |
| Form 2File: 3 form 2 05-12-2021 Sep-21.pdf | 31 May 2025 |
| Form 3File: 3 Skyreen Form-3 Sep-21 Done.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: 3 Sep 21.pdf | 31 May 2025 |
| Form 1File: 4 1-1-2022 Dec-21.pdf | 31 May 2025 |
| Form 2File: 4 form 2 07-01-2022 Dec-21.pdf | 31 May 2025 |
| Form 3File: 4 Skyreen Form-3 Dec-21 Done.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: 4 Dec 21.pdf | 31 May 2025 |
| Form 1File: 5 1-4-2022 Mar-22.pdf | 31 May 2025 |
| Form 2File: 5 form 2 09-4-2022 Mar-22.pdf | 31 May 2025 |
| Form 3File: 5 Skyreen Form-3 Mar-22.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: 5 Mar 22.pdf | 31 May 2025 |
| Form 1File: 6 1-7-2022 Jun-22.pdf | 31 May 2025 |
| Form 2File: 6 form 3 04-07-2022 Jun-22.pdf | 31 May 2025 |
| Form 3File: 6 Skyreen Form-3 Jun-22.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: 6 Jun 22.pdf | 31 May 2025 |
| Form 1File: 7 1-10-2022 Sep-22.pdf | 31 May 2025 |
| Form 2File: 7 form 2 07-10-2022 sep-22.pdf | 31 May 2025 |
| Form 3File: 7 Skyreen Form-3 Sep-22.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: 7 Sep 22.pdf | 31 May 2025 |
| Form 1File: 8 1-1-2023 Dec-22.pdf | 31 May 2025 |
| Form 2File: 8 form 2 07-01-2023 Dec-22.pdf | 31 May 2025 |
| Form 3File: 8 Skyreen Form-3 Dec-22 Done.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: 8 Dec 22.pdf | 31 May 2025 |
| Form 1File: 9 1-4-2023 Mar-23.pdf | 31 May 2025 |
| Form 2File: 9 form 3 06-04-2023 Mar-23.pdf | 31 May 2025 |
| Form 3File: 9 Skyreen Form-3 Mar-23.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: 9 Mar 23.pdf | 31 May 2025 |
| Form 1File: 10 1-7-2023 Jun-23.pdf | 31 May 2025 |
| Form 2File: 10 form 2 04-07-2023 Jun-23.pdf | 31 May 2025 |
| Form 3File: 10 Skyreen Form-3 Jun-23 Done.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: 10 Jun 23.pdf | 31 May 2025 |
| Form 1File: 11 1-10-2023 Sep-23.pdf | 31 May 2025 |
| Form 2File: 11 form 2 oct 2023 Sep-23.pdf | 31 May 2025 |
| Form 3File: 11 Skyreen Form-3 Sep-23 Done.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: 11 Sep 23.pdf | 31 May 2025 |
| Form 1File: 12 1-1-2024 Dec-23.pdf | 31 May 2025 |
| Form 2File: 12 form 2 05-01-2024 Dec-23.pdf | 31 May 2025 |
| Form 3File: 12 Skyreen Form-3 Dec-23 Done.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: 12 Dec 23.pdf | 31 May 2025 |
| Form 1File: 13 1-4-2024 Mar-24.pdf | 31 May 2025 |
| Form 2File: 13 form 2 08-04-2024 Mar-24.pdf | 31 May 2025 |
| Form 3File: 13 Skyreen Form-3 Mar-24 Done.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: 16 Dec 24.pdf | 31 May 2025 |
| Form 1File: 13 1-4-2024 Mar-24.pdf | 31 May 2025 |
| Form 2File: 13 form 2 08-04-2024 Mar-24.pdf | 31 May 2025 |
| Form 3File: 13 Skyreen Form-3 Mar-24 Done.pdf | 31 May 2025 |
| Disclosure of Sold and Booked InventoryFile: 16 Dec 24.pdf | 31 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 1 Skyreen Form-3 Mar-21.pdf | 29 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 2 Skyreen Form-3 Jun-21.pdf | 29 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 Skyreen Form-3 Sep-21.pdf | 29 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 4 Skyreen Form-3 Dec-21.pdf | 29 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 8 Skyreen Form-3 Dec-22.pdf | 29 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 10 Skyreen Form-3 Jun-23.pdf | 29 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 11 Skyreen Form-3 Sep-23.pdf | 29 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 12 Skyreen Form-3 Dec-23.pdf | 29 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 13 Skyreen Form-3 Mar-24.pdf | 29 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 5 Skyreen Form-3 Mar-22_compressed.pdf | 29 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 6 Skyreen Form-3 Jun-22_compressed.pdf | 29 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 7 Skyreen Form-3 Sep-22_compressed.pdf | 29 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 9 Skyreen Form-3 Mar-23_compressed (1).pdf | 29 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2 1-7-2021 Jun-21.pdf | 28 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 1-4-2021 Mar-21.pdf | 28 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 17 1-4-2025 Mar-25.pdf | 28 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 16 1-1-2025 Dec-24.pdf | 28 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 15 1-10-2024 Sep-24.pdf | 28 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 14 1-7-2024 Jun-24.pdf | 28 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 13 1-4-2024 Mar-24.pdf | 28 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 12 1-1-2024 Dec-23.pdf | 28 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 11 1-10-2023 Sep-23.pdf | 28 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 10 1-7-2023 Jun-23.pdf | 28 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 9 1-4-2023 Mar-23.pdf | 28 Apr 2025 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 144 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep SKYREEN on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near RAVET13,700+ in Pune
Filed coordinates, straight-line distance. 251 registered projects within 2 km.
Godrej Park Greens
Godrej Skyline Developers Limited
FOREST GROVE AT GODREJ PARK GREENS
Godrej Skyline Developers Limited
Om Mangalam Samruddhi
NDG Homes LLP
PCMC EWS KIWALE
Pimpri Chinchwad Municipal Corporation
Godrej Nurture
Godrej Skyline Developers Limited
My Home Sanctuary Phase I
MAMURDI DEVELOPERS LLP
Builder: NILIMA PRAFULLA BADHE
NILIMA PRAFULLA BADHE has 1 registration on MahaRERA, including SKYREEN. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that SKYREEN shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if SKYREEN is delayed beyond 29 Oct 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SKYREEN?
The registered promoter entity is NILIMA PRAFULLA BADHE, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SKYREEN?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SKYREEN?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SKYREEN?
The professionals named in the filing: Architect: Ar Kaustubh Babar; Engineer: P S Badhe; Chartered Accountant: SPAK & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SKYREEN?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback