Home / Browse projects / Palghar, Maharashtra / Skyline Towers

Registration lapsed No litigation declared Residential / Group Housing project

Skyline Towers

By K A Infra Builders and Developers

RG-MH-34880 · RERA P99000048981 · Last updated on MahaRERA portal: 29 Jan 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 7 months past the filed date
  • Completion date moved by 15 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Mar 2026Possession promised7 months past this date
0 of 22Construction stages doneacross 2 buildings; furthest along: Excavation, 40%
0Complaints at MahaRERAon this registration
Jump to the 48 documents Report an error

Skyline Towers is a Residential / Group Housing project by K A Infra Builders and Developers in Palghar, Maharashtra, registered with MahaRERA as P99000048981 on 24 Jan 2023. Possession was promised by 31 Mar 2026 and is now 7 months past that date. The completion date has moved by 15 months from the original filing.

At a glance

Project

  • NameSkyline Towers
  • TypeResidential / Group Housing
  • Location
    • Mauje Vevoor
    • Vevoor
    • Palghar
    • 401404
  • Pincode401404
  • RERA no.P99000048981
  • ReraGenie IDRG-MH-34880

Builder

  • NameK A Infra Builders and Developers
  • Entity typePartnership
  • PartnersKamruddin Abbasali Khan, Ahmedali Kamruddin Khan, Mudassir Kamruddin Khan, MUZAMMIL KAMRUDDIN KHAN, MUBASSIR KAMRUDDIN KHAN

Key dates

7 months past promisethis monthRegisteredJan 2023First promiseDec 2024Revised toMar 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on24 Jan 2023
  • Promised completion31 Mar 2026
  • Revised completionRevised to 31 Mar 2026 (originally 31 Dec 2024)
  • Buildings2 building records
  • Documents filed48 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Skyline Towers- Wing ANA130000
Skyline Towers- Wing BNA00000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 29 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Excavation, at 40%.

Skyline Towers- Wing A5%
ActivityProgress
Excavation40%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor20%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Skyline Towers- Wing B0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 29 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed106

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots106
Closed/Covered2
Open Space104

Land and ownership4

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,281 sq m
Land owned byThe promoter, with other names on the file
Named landowners4
LandownerVillageDistrict
Ahmed Ali KhanKurlaMumbai Suburban
Kamruddin Haji Abbas Ali KhanKurlaMumbai Suburban
Mohammed Yaqub Haji Abbas Ali KhanKurlaMumbai Suburban
Riyazuddin Sadruddin KhanKurlaMumbai Suburban

Approvals and building plan

Permissible FSI9123.2
Proposed, not sanctioned4,636 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNew Dwarkapuri LBS Marg Near Sheetal Cinema Kurla West Mumbai 400070

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSiddhivinayak Associates
EngineerM P Prime Structures Pvt Ld
Chartered AccountantKapure and Kapure Chartered Accountants
PartnerRole in project
K A Infra Builders and Developers-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000025997Dec 2024 → Mar 2026

Reason as filed by the promoterThe new approval full commencement certificate of the project has received in Nov 2023 and due to which the project work is delayed. further accordingly all estimates and timelines of project has changed.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 13 Oct 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 12 Jan 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 4 Jan 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 4 Jan 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed48

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: april to june 2023.pdf29 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: july to sept 2023.pdf29 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Dec 23.pdf29 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Jan - March 24.pdf29 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: April - June 24.pdf29 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: July - Sept 24.pdf29 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Oct - Dec 24.pdf29 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: jan to march 2023.pdf29 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 9 OCT TO DEC 24.pdf29 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 8 JULY TO SEPT 24.pdf29 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1 JAN TO MARCH 23.pdf29 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form 5 2022-23.pdf29 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 2023-24.pdf29 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A 22-23.pdf9 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A 23-24.pdf9 Jan 2025
Building plan approvalFile: SANCTIONED PLAN 3 mb.pdf4 Jan 2025
Building plan approvalFile: SANCTIONED PLAN 3 mb.pdf4 Jan 2025
Commencement Certificates / NA Order for plotted developmentFile: REVISED CC.pdf4 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: SANCTIONED PLAN 3 mb.pdf4 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: SANCTIONED PLAN 3 mb.pdf4 Jan 2025
Layout approvalFile: Revised KA INFRA BPMS PLAN -1.pdf12 Jan 2023
Layout approvalFile: Revised KA INFRA BPMS PLAN - 2.pdf12 Jan 2023
Building plan approvalFile: Revised KA INFRA BPMS PLAN -1.pdf12 Jan 2023
Building plan approvalFile: Revised KA INFRA BPMS PLAN - 2.pdf12 Jan 2023
Copy of Layout Approval (in case of layout)File: Revised KA INFRA BPMS PLAN -1.pdf12 Jan 2023
Copy of Layout Approval (in case of layout)File: Revised KA INFRA BPMS PLAN - 2.pdf12 Jan 2023
Building Plan Approval / NA Order for plotted developmentFile: Revised KA INFRA BPMS PLAN -1.pdf12 Jan 2023
Building Plan Approval / NA Order for plotted developmentFile: Revised KA INFRA BPMS PLAN - 2.pdf12 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organizations.pdf10 Jan 2023
Other - LegalFile: Declaration about Survey No.pdf29 Nov 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: KA Infra Form 3 for Registration-6-10.pdf15 Nov 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: KA Infra Form 3 for Registration-6-10.pdf15 Nov 2022
Proforma of Agreement for saleFile: AGREEMENT FOR SALE.pdf15 Nov 2022
Copy of the legal title reportFile: legal tittle.pdf13 Oct 2022
CERSAI detailsFile: CERSAI_Search_Report_200249587332_For_Asset_Based_Search_13_10_2022_18_39_43_225.pdf13 Oct 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: KA Infra Form 3 for Registration-1-5.pdf13 Oct 2022
Proforma of Allotment letterFile: Allotment letter.pdf13 Oct 2022
Declaration in FORM BFile: Form B Affidavit Cum declaration.pdf12 Oct 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Final architects Certificate for registration.pdf12 Oct 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Final Engineer certificate for registration.pdf12 Oct 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: separate Bank account.pdf12 Oct 2022
Deviation Report with respect to Allotment letterFile: Deviation for AL.pdf12 Oct 2022
Deviation Report with respect to model copy of AgreementFile: Deviation for ATS.pdf12 Oct 2022
PAN CardFile: K A Infra Pan Card.pdf4 Oct 2022
Details of encumbrances concerned to FinanceFile: Concerned to Finance.pdf4 Oct 2022
Details of encumbrances concerned to LegalFile: Concerned to legal.pdf4 Oct 2022
Commencement Certificates / NA Order for plotted developmentFile: cc.pdf4 Oct 2022
Declaration about Commencement CertificateFile: Declaration About CC.pdf4 Oct 2022

How this compares with Palghar

31%of Palghar projects moved their completion datethis one moved by 15 months
26%of Palghar registrations have lapsed or been cancelledthis one is among them

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Skyline Towers on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Vevoor3,200+ in Palghar

Builder: K A Infra Builders and Developers

K A Infra Builders and Developers has 1 registration on MahaRERA, including Skyline Towers. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What does it mean that Skyline Towers shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Skyline Towers is delayed beyond 31 Mar 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Skyline Towers?

The registered promoter entity is K A Infra Builders and Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Skyline Towers?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Skyline Towers?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Skyline Towers?

The professionals named in the filing: Architect: Siddhivinayak Associates; Engineer: M P Prime Structures Pvt Ld; Chartered Accountant: Kapure and Kapure Chartered Accountants. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Skyline Towers?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Skyline Towers. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Skyline Towers to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.