Home / Browse projects / Pune, Maharashtra / SkyHigh Towers - D1D2

Registered No litigation declared Residential / Group Housing project

SkyHigh Towers - D1D2

By New World Landmark LLP

RG-MH-62945 · RERA P52100015918 · Last updated on MahaRERA portal: 11 Aug 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 51 months
  • 3 extensions taken
  • Rs 50.00 crore secured on the land, in favour of ICICI HOME FINANCE LIMITED

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Mar 2028Possession promisedmoved 51 months from the original
2 of 22Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 82%
84 of 272Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 152 documents Report an error

SkyHigh Towers - D1D2 is a Residential / Group Housing project by New World Landmark LLP in Pune, Maharashtra, registered with MahaRERA as P52100015918 on 9 Apr 2018. Possession is promised by 31 Mar 2028. The completion date has moved by 51 months from the original filing. 188 of the 272 units on this registration are recorded sold or booked, and 2 of 22 construction stages are filed complete.

At a glance

Project

  • NameSkyHigh Towers - D1D2
  • TypeResidential / Group Housing
  • Location
    • Near Hinjewadi Phase 2
    • Hinjewadi
    • Man
    • Mulshi
    • Pune
    • 411057
  • Pincode411057
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100015918
  • ReraGenie IDRG-MH-62945

Builder

  • NameNew World Landmark LLP
  • Entity typePartnership
  • PartnerSunil Mittal
  • Other registrations3 more →
  • Completed1 of 4
  • Declared earlier projects3 →

Key dates

this monthRegisteredApr 2018First promiseDec 2023Revised toMar 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on9 Apr 2018
  • Promised completion31 Mar 2028
  • Revised completionRevised to 31 Mar 2028 (originally 31 Dec 2023)
  • Buildings2 building records
  • Documents filed152 files

Current status

69%188 of 272 units booked
51.2%Work done, per cost certificate

Figures as on 11 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
D1NA43341360136
D2NA43341360136

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 11 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 82%.

D152%
ActivityProgress
Excavation100%
Basement (if any)80%
Podiums (if any)80%
Plinth80%
Stilt Floor80%
Slabs of Super Structure82%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises25%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks47%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
D252%
ActivityProgress
Excavation100%
Basement (if any)80%
Podiums (if any)80%
Plinth80%
Stilt Floor80%
Slabs of Super Structure82%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises25%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks47%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 11 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed132

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots132
Closed/Covered132
BuildingClosed/CoveredTotal
D16666
D26666

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area784 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofICICI HOME FINANCE LIMITED
Secured amountRs 50.00 crore
CERSAI search filedYes
Declared on11 Nov 2025

Approvals and building plan

Sanctioning authorityPMRDA
Permissible FSI15410.79
Proposed, not sanctioned15,411 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchApte Road, Pune
Estimated costRs 67.00 cr
Cost incurredRs 34.30 cr
Work done51.2%
BuildingWingEstimatedIncurred
D1NARs 30.00 crRs 16.60 cr
D2NARs 30.00 crRs 16.60 cr
-NARs 7.00 crRs 1.10 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVK a architecture
EngineerManjiri Desai
Chartered AccountantSAC & Co LLp
Chartered AccountantPriyanka Chordiya and Associates
Chartered AccountantM A Agarwal And asso
Chartered AccountantKailash Agarwal
PartnerRole in project
New World Landmark LLP-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100005973Dec 2023 → Dec 2024

Reason as filed by the promoterDue to local hindrances the work was halted, also there is a sales are poor due to slowdown. Kindly grant extension for one year upto 30.12.2024

EXT52100012592Dec 2023 → Dec 2026

Reason as filed by the promoterDue to Covid-19, there has been a substantial drop in demand of our category of product, hence the project has slowed down hence requesting the grace period to complete the project as 30/12/2026 instead of 30/12/2025. Also there are 234 units proposed out of which 178 units are presently sanctioned.

EA03082622001Dec 2023 → Mar 2028

Reason as filed by the promoterThe EC process was delayed due to the NGT Order. Additionally, geopolitical issues and the war in West Asia impacted the supply chain and project execution. Due to both reasons, the Project suffered a cumulative delay of approximately 18 months.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 4 Apr 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 Jul 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Jul 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 22 Jul 2026Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2028

Documents filed152

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 152 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2024-2025)File: Form2A SkyHigh D1D2 Mar 2025_compressed_compressed.pdf11 Aug 2026
Form 5 (FY 2018-2019)File: Form 5 2018-2019.pdf4 Aug 2026
Form 5 (FY 2020-2021)File: Form 5 2020-2021.pdf4 Aug 2026
Form 5 (FY 2021-2022)File: Form 5 2021-2022.pdf4 Aug 2026
Form 2A (FY 2025-2026)File: Form 2A SkyHigh Towers D1 D2.pdf3 Aug 2026
Form 5 (FY 2024-2025)File: Form 5_SkyHigh Towers D1-D2_FY 2024-2025 sign_compressed.pdf3 Aug 2026
Form 5 (FY 2022-2023)File: Form 5 PC FY 22-23 SkyHigh Towers D1-D2_both sign.pdf3 Aug 2026
Form 5 (FY 2023-2024)File: form 5 SkyHigh Towers D1D2 31-03-2024.pdf3 Aug 2026
Form 1File: Form1 SkyHigh D1D2 Mar 2025.pdf28 Jul 2026
Form 2File: Form2 SkyHigh D1D2 Mar 2025.pdf28 Jul 2026
Form 3File: Form 3 SkyHigh Towers D1D2 mar 2025.pdf28 Jul 2026
Disclosure of Sold and Booked InventoryFile: Inventory D1D2.pdf28 Jul 2026
OthersFile: D1D2 layout and CC.pdf28 Jul 2026
Form 1File: Form1 SkyHigh D1D2 Mar 2025.pdf28 Jul 2026
Form 2File: Form 2 SkyHigh Towers D1D2.pdf28 Jul 2026
Form 3File: Form 3 SkyHigh Towers D1D1 Dec 2024.pdf28 Jul 2026
Disclosure of Sold and Booked InventoryFile: Inventory SkyHigh Towers D1D2 Dec 2024.pdf28 Jul 2026
OthersFile: IOD Plans for SkyHigh Towers.pdf28 Jul 2026
Withdrawal Update Form 1File: Form 1 Highsky Tower D1 D2.pdf24 Jul 2026
Withdrawal Update Form 2File: Form 2- Skyhigh tower D1D2.pdf24 Jul 2026
Withdrawal Update Form 3File: Form 3 Skyhigh D1 D2 30062026 sign.pdf24 Jul 2026
Commencement certificateFile: 240716 - CC.pdf22 Jul 2026
Layout approvalFile: Layout Plans - 01-21 - 2024.pdf22 Jul 2026
Layout approvalFile: Layout Plans - 02-21 - 2024.pdf22 Jul 2026
Layout approvalFile: Layout Plans - 03-21 - 2024.pdf22 Jul 2026
Layout approvalFile: Layout Plans - 04-21 - 2024.pdf22 Jul 2026
Layout approvalFile: Layout Plans - 05-21 - 2024.pdf22 Jul 2026
Layout approvalFile: Layout Plans - 06-21 - 2024.pdf22 Jul 2026
Layout approvalFile: Layout Plans - 07-21 - 2024.pdf22 Jul 2026
Building plan approvalFile: Layout Plans - 08-21 - 2024 - D1.pdf22 Jul 2026
Building plan approvalFile: Layout Plans - 09-21 - 2024 - D1.pdf22 Jul 2026
Building plan approvalFile: Layout Plans - 10-21 - 2024 - D1.pdf22 Jul 2026
Building plan approvalFile: Layout Plans - 11-21 - 2024 - D2.pdf22 Jul 2026
Building plan approvalFile: Layout Plans - 12-21 - 2024 - D2.pdf22 Jul 2026
Building plan approvalFile: Layout Plans - 13-21 - 2024 - D2.pdf22 Jul 2026
Building plan approvalFile: Layout Plans - 14-21 - 2024.pdf22 Jul 2026
Building plan approvalFile: Layout Plans - 15-21 - 2024.pdf22 Jul 2026
Building plan approvalFile: Layout Plans - 16-21 - 2024.pdf22 Jul 2026
Building plan approvalFile: Layout Plans - 17-21 - 2024.pdf22 Jul 2026
Building plan approvalFile: Layout Plans - 18-21 - 2024.pdf22 Jul 2026
Building plan approvalFile: Layout Plans - 19-21 - 2024.pdf22 Jul 2026
Building plan approvalFile: Layout Plans - 20-21 - 2024.pdf22 Jul 2026
Building plan approvalFile: Layout Plans - 21-21 - 2024.pdf22 Jul 2026
Withdrawal Update Form 1File: Form 1 Highsky Tower D1 D2.pdf22 Jul 2026
Withdrawal Update Form 2File: Form 2- Skyhigh tower D1D2.pdf22 Jul 2026
Withdrawal Update Form 3File: Form 3 Skyhigh D1 D2 30062026 sign.pdf22 Jul 2026
Withdrawal Update Form 1File: Form 1 D1D2.pdf14 May 2026
Withdrawal Update Form 2File: Form 2 D1D2.pdf14 May 2026
Withdrawal Update Form 3File: Form 3 Skyhigh D1 D2 30032026 F sign_compressed.pdf14 May 2026
Withdrawal Update Form 1File: Form 1 SkyHigh Towers D1D2 31122025.pdf18 Feb 2026
Withdrawal Update Form 2File: Form 2 NWLLLP D1D2 31122025.pdf18 Feb 2026
Withdrawal Update Form 3File: Form 3 Skyhigh D1 D2 31122025 F sign.pdf18 Feb 2026
Withdrawal Update Form 1File: FORM 1 SKY HIGH TOWERS D1 u0026 D2.pdf11 Nov 2025
Withdrawal Update Form 1File: FORM 1 SKY HIGH TOWER D1 u0026 D2.pdf11 Nov 2025
Withdrawal Update Form 2File: Form 2 Skyhigh D1 D2 June 2025Updated.pdf11 Nov 2025
Withdrawal Update Form 2File: Form 2 Sky High Tower D1D2Upated.pdf11 Nov 2025
Withdrawal Update Form 3File: Form 3 Skyhigh D1-D2 30062025 Fsign_compressed.pdf11 Nov 2025
Withdrawal Update Form 3File: Form 3 Skyhigh D1-D2 30092025 F sign_compressed.pdf11 Nov 2025
Certificates of CA (Form 3)File: 15 Certificates of CA (Form 3).pdf2 Jul 2025
Disclosure of sold/ booked inventoryFile: CIrcular 29 - Mar 2023.pdf6 Jun 2025
Disclosure of sold/ booked inventoryFile: Circular 29 - Jun 2024.pdf6 Jun 2025
Disclosure of sold/ booked inventoryFile: Circular 29 - Sep 2024.pdf6 Jun 2025
Disclosure of sold/ booked inventoryFile: Circular 29 - Dec 2024.pdf6 Jun 2025
Declaration about Commencement CertificateFile: REVISED Format D_organized.pdf13 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 SkyHigh D1D2 Mar 2025.pdf2 May 2025
Certificates of CA (Form 3)File: Form 3 Skyhigh D1-D2 30032025_compressed.pdf2 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2 SkyHigh D1D2 Mar 2025.pdf2 May 2025
Certificates of CA (Form 3)File: form 3 sky High tower D1 D2 31-12-2024 sign_11zon.pdf12 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A FY 2019-20.pdf8 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 FY 2018-19.pdf8 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 FY 2019-20.pdf8 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 FY 2020-21.pdf8 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A FY 2020-21.pdf8 Apr 2025
Declaration about Commencement CertificateFile: Format D.pdf8 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 SkyHigh Towers D1D2-.pdf29 Jan 2025
Certificates of CA (Form 3)File: form 3 SkyHigh Towers D1D2 31-12-2024_compressed.pdf29 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 SkyHigh Towers D1D2.pdf29 Jan 2025
Disclosure of sold/ booked inventoryFile: Sky High D1 D2_compressed.pdf29 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 D1-D2.pdf11 Nov 2024
Certificates of CA (Form 3)File: form 3 Sky High Towers D1-D2 30-09-2024_compressed.pdf11 Nov 2024

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
SkyHigh Towers D4P52100048403Hinjewadi, Pune160Jan 2023OngoingDec 2029Registered original: Dec 2028Not due yet
SkyHigh Towers D3P52100048413Hinjewadi, Pune136Jan 2023OngoingDec 2027Not due yet

How this compares with Pune

69%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 51 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SkyHigh Towers - D1D2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Hinjewadi13,700+ in Pune

2 kmSkyHigh Towers - D1D2Completed 32Lapsed / revoked 11Other 39Dot size: filed unitsN

Filed coordinates, straight-line distance. 82 registered projects within 2 km.

Builder: New World Landmark LLP

New World Landmark LLP has 4 registrations on MahaRERA, including Pebbles-HighMont Phase-1 and SkyHigh Towers - D1D2. Its filings disclose 3 earlier MahaRERA projects, none completed yet. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if SkyHigh Towers - D1D2 is delayed beyond 31 Mar 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SkyHigh Towers - D1D2?

The registered promoter entity is New World Landmark LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SkyHigh Towers - D1D2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SkyHigh Towers - D1D2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SkyHigh Towers - D1D2?

The professionals named in the filing: Architect: VK a architecture; Engineer: Manjiri Desai; Chartered Accountant: SAC & Co LLp; Chartered Accountant: Priyanka Chordiya and Associates; Chartered Accountant: M A Agarwal And asso; Chartered Accountant: Kailash Agarwal. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SkyHigh Towers - D1D2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SkyHigh Towers - D1D2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SkyHigh Towers - D1D2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.