Home / Browse projects / Pune, Maharashtra / SILVENIA
SILVENIA
RG-MH-43730 · RERA P52100053357 · Last updated on MahaRERA portal: 6 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 4 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- All 4 completed earlier projects delivered on promise
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SILVENIA is a Residential / Group Housing project by Associated Recons LLP in Pune, Maharashtra, registered with MahaRERA as P52100053357 on 27 Oct 2023. Possession was promised by 30 Jun 2026 and is now 4 months past that date. 33 of the 39 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.
At a glance
Project
- NameSILVENIA
- TypeResidential / Group Housing
- Location
- LANE NO 20
- SUVARNABAUG COLONY
- Kothrud
- Haveli
- Pune
- 411038
- Pincode411038
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100053357
- ReraGenie IDRG-MH-43730
Builder
- NameAssociated Recons LLP
- Entity typePartnership
- GSTIN27AAYFA3148F1Z7
- GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
- Designated PartnersKEDAR PRABHAKAR SABNE, DEEPAK ANANT KULKARNI
- Other registrations6 more →
- Completed4 of 7
- No longer live1 lapsed, de-registered or revoked
- Declared earlier projects7 →
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on27 Oct 2023
- Promised completion30 Jun 2026
- Revised completionNone
- Buildings1 building record
- Documents filed87 files
Current status
Figures as on 6 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SILVENIA | NA | 10 | 10 | 39 | 0 | 39 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 6 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 80%.
SILVENIA: 50% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 80% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 50% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 20% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 6 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed38
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership2
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| SILVERLINE APARTMENTS CONDOMINIUM | Khadakwasala | Pune |
| Nishigandh apartments condominium | Kothrud | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | AJAY AMLE |
| Engineer | SANTOSH TURKE |
| Chartered Accountant | Anand Deshpande |
| Chartered Accountant | OMKAR RAVINDRA KULKARNI & ASSOCIATES |
| Partner | Role in project |
|---|---|
| Associated Recons LLP | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 12 Jun 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 12 Jun 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 9 Nov 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 9 Nov 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed87
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 87 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 5 (FY 2025-2026)File: ilovepdf_merged (9).pdf | 6 Jul 2026 |
| Form 5 (FY 2024-2025)File: ilovepdf_merged (8).pdf | 6 Jul 2026 |
| Form 2A (FY 2025-2026)File: Silvenia - Form 2A.pdf | 2 Jul 2026 |
| Form 1File: FORM 1 31 MARCH 2026.pdf | 21 Apr 2026 |
| Form 3File: Silvenia Form 3 q4_compressed.pdf | 21 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: Silvenia Disclousre.pdf | 21 Apr 2026 |
| Form 2File: Silvenia Form-2 Q4.pdf | 21 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclousere of Inventory.pdf | 19 Feb 2026 |
| Form 1File: FORM 1 31DEC 2025.pdf | 19 Feb 2026 |
| Form 2File: FORM-2.pdf | 19 Feb 2026 |
| Form 3File: SILVENIA Form-3_compressed.pdf | 19 Feb 2026 |
| Form 1File: FORM 1 30 sept 2025 (2).pdf | 25 Nov 2025 |
| Form 2File: SEP 25.pdf | 25 Nov 2025 |
| Form 3File: Sep 25_compressed.pdf | 25 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: Inventory PDF.pdf | 25 Nov 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Silvenia form 3 As on 31ST MARCH 2025 REVISED.pdf | 14 Jun 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 MARCH 25.pdf | 10 Jun 2025 |
| Disclosure of sold/ booked inventoryFile: s and b Silvenia.pdf | 10 Jun 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A Mar 25.pdf | 2 Jun 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 31 MARCH 2025.pdf | 31 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Silvenia form 3 As on 31ST MARCH 2025.pdf | 31 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: DEC 2024.pdf | 7 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 - DEC 24.pdf | 22 Mar 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A dec 24.pdf | 22 Mar 2025 |
| Details of encumbrances concerned to FinanceFile: encumberance r1.pdf | 29 Jan 2025 |
| Details of encumbrances concerned to LegalFile: encumberance r1.pdf | 29 Jan 2025 |
| Details of encumbrances concerned to FinanceFile: encumberance certificate.pdf | 28 Jan 2025 |
| Details of encumbrances concerned to FinanceFile: encumberance certificate.pdf | 28 Jan 2025 |
| Details of encumbrances concerned to LegalFile: encumberance certificate.pdf | 28 Jan 2025 |
| Details of encumbrances concerned to LegalFile: encumberance certificate.pdf | 28 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Engineers Certificate Form 2A FY 2023-24.pdf | 16 Jan 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE 30NOV2024-1.pdf | 10 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate 31-03-2024.pdf | 6 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate 30-06-2024.pdf | 6 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate 01-10-2024.pdf | 6 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate 2 30-09-2024.pdf | 6 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate 2 30-06-2024.pdf | 6 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate 2 31-03-2024 new.pdf | 6 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A (1).pdf | 6 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5 .pdf | 6 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 Nov 2024.pdf | 13 Dec 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A Silvenia.pdf | 12 Dec 2024 |
| Proforma of Agreement for saleFile: agreement.pdf | 28 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 31MARCH2024.pdf | 12 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 30 JUNE 2024.pdf | 12 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 30 SEPT 2024.pdf | 12 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE 30SEPT2024.pdf | 12 Nov 2024 |
| Building plan approvalFile: final sanction sl PLAN.pdf | 9 Nov 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: silvenia final cc.pdf | 9 Nov 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: final sanction sl PLAN.pdf | 9 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 sept 24.pdf | 8 Nov 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A sept 24.pdf | 8 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: silvenia form 3 sept.pdf | 7 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE 30JUNE2024.pdf | 5 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 JUNE 24.pdf | 8 Aug 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A JUNE 24.pdf | 8 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: silvenia form 3 june 2024.pdf | 8 Aug 2024 |
| Disclosure for secured/unsecured finance availed for the projectFile: NON ENCUMBRANCES FINANCE.pdf | 12 Jul 2024 |
| Disclosure for secured/unsecured finance availed for the projectFile: Scan 1.pdf | 12 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 - march 23.pdf | 11 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD AND BOOK INVENTORY - UPTO MARCH 24.pdf | 11 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Silvenia March 24_11zon.pdf | 9 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 Silvenia Dec 23.pdf | 30 Jan 2024 |
| PAN CardFile: ASSOCIATED RECONS PAN COPY.pdf | 6 Oct 2023 |
| Deviation Report with respect to model copy of AgreementFile: Declaration AFS.pdf | 11 Sep 2023 |
| Proforma of Agreement for saleFile: AFS- REVISED SILVENIA.pdf | 21 Aug 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: disclosure of interest by dak.pdf | 16 Aug 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: disclosure of interest by ks.pdf | 16 Aug 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: commencement silvenia.pdf | 28 Jul 2023 |
| Declaration about Commencement CertificateFile: commencement declaration.pdf | 28 Jul 2023 |
| Details of encumbrances concerned to FinanceFile: financial encumbrance report.pdf | 27 Jul 2023 |
| Details of encumbrances concerned to FinanceFile: legal encumbrance report.pdf | 27 Jul 2023 |
| Details of encumbrances concerned to LegalFile: financial encumbrance report.pdf | 27 Jul 2023 |
| Details of encumbrances concerned to LegalFile: legal encumbrance report.pdf | 27 Jul 2023 |
| Declaration in FORM BFile: Form B rev.pdf | 27 Jul 2023 |
| Other - LegalFile: legal encumbrance report.pdf | 27 Jul 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank letter for RERA.pdf | 6 Jul 2023 |
| Other - FinanceFile: PAN declaration.pdf | 6 Jul 2023 |
| Proforma of Allotment letterFile: allotment letter.pdf | 30 Jun 2023 |
| Deviation Report with respect to Allotment letterFile: declaration on deviation in allotment letter.pdf | 30 Jun 2023 |
Promoter's earlier projects6
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| JAIP52100080254 | SHIVDARSHAN, Pune | 16 | May 2025 | Ongoing | Jun 2028 | Not due yet |
| TEJASWIP52100077281 | TULSHIBAUGWALE COLONY, Pune | 26 | Aug 2024 | Ongoing | Jun 2027 | Not due yet |
| YUVRAJ APARTMENTSP52100032032 | NAVKETAN SOCIETY, Pune | - | Dec 2021 | Completed | Sep 2024 | Jun 2024 |
| SAI SMRUTIP52100030613 | DAHANUKAR COLONY, Pune | - | Sep 2021 | Completed | Sep 2024 | Feb 2024 |
| SAROJ CHSLP52100014747 | DAHANUKAR COLONY, Pune | - | Jan 2018 | Completed | Mar 2021 | Aug 2020 |
| AVANTILI CHSL | PLOT NO 2 HAPPY COLONY PUNE | 28 | - | Completed | Mar 2017 | Mar 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 6 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 87 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep SILVENIA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near SUVARNABAUG COLONY13,700+ in Pune
Filed coordinates, straight-line distance. 303 registered projects within 2 km.
Pratik Nagar Palladio Kothrud Central
Vilas Javdekar Infinitee Developers Pvt. L
NEW FRIENDS
MAJESTIQUE DUROPOLIS PRIVATE LIMITED
SARVATRA CO-OP HSG SOCIETY LTD
Suryakant Kakade
Kshitij Residency
Yash Buildcon
MAYUK
MAYUR CORPORATION
Pune Baner Project-Tower 4 and 5
Goel Ganga Ventures India Private Limited
Builder: Associated Recons LLP
Associated Recons LLP has 7 registrations on MahaRERA, including SAROJ CHSL and SNEH PARK. Its filings disclose 7 earlier MahaRERA projects: declares 5 of 5 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that SILVENIA shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if SILVENIA is delayed beyond 30 Jun 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SILVENIA?
The registered promoter entity is Associated Recons LLP, a partnership as per the filing. Its GSTIN 27AAYFA3148F1Z7 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SILVENIA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SILVENIA?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SILVENIA?
The professionals named in the filing: Architect: AJAY AMLE; Engineer: SANTOSH TURKE; Chartered Accountant: Anand Deshpande; Chartered Accountant: OMKAR RAVINDRA KULKARNI & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SILVENIA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback