SILICON BAY PHASE II
By KARAN JANHAVI DEVELOPMENT COROPORATION
RG-MH-17113 · RERA P52100027850 · Last updated on MahaRERA portal: 6 Nov 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 33 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: .Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SILICON BAY PHASE II is a Residential / Group Housing project by KARAN JANHAVI DEVELOPMENT COROPORATION in Near Nyati Medows, 411014, registered with MahaRERA as P52100027850 on 8 Jan 2021. Possession was promised by 31 Jan 2024 and is now 33 months past that date.
At a glance
Project
- NameSILICON BAY PHASE II
- TypeResidential / Group Housing
- Location
- Suncity Road
- Near Nyati Medows
- 411014
- Pincode411014
- RERA no.P52100027850
- ReraGenie IDRG-MH-17113
Builder
- NameKARAN JANHAVI DEVELOPMENT COROPORATION
- Entity typePartnership
- PartnersRAJIV CHANDRAKANT GALANDE, RAJIV CHANDRAKANT GALANDE, PRAVIN PRATAPRAO GAIKWAD, VISHWAJIT VASANTRAO GAIKWAD, Suhas Ashokrao Gaikwad
- Other registrations2 more →
- Completed2 of 3
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on8 Jan 2021
- Promised completion31 Jan 2024
- Revised completionNone
- Buildings1 building record
- Documents filed31 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| C Building | NA | 17 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 6 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
7 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 95%.
C Building: 95% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 80% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 95% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
Progress on shared amenities15
As on 6 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 10% |
| Water Supply | Yes | 10% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 10% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 40% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 10% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 40% |
| Electrical meter room, sub-station, receiving station | Yes | 70% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed120
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Karan Janhavi Development Corporation | Pune (CB) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Mr Vikas Achalkar |
| Engineer | Mr Pritam Sambhaji Koli |
| Chartered Accountant | Mr Paras Vijapure |
| Partner | Role in project |
|---|---|
| KARAN JANHAVI DEVELOPMENT COROPORATION | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 31 Dec 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 18 Jun 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 31 Dec 2020 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 15 Jun 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 19 May 2023
Documents filed31
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate on Completion of Project (Form 4)File: form 4 dec 2023.pdf | 6 Nov 2024 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: form 4 dec 2023.pdf | 6 Nov 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OCCUPANCY CERTIFICATE PHASE -II.pdf | 19 May 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: KJDC PHASE II FORM 5.pdf | 15 Feb 2023 |
| Details of encumbrances concerned to FinanceFile: LEGAL CONCERNED PHASE II.pdf | 11 Feb 2023 |
| Details of encumbrances concerned to LegalFile: LEGAL CONCERNED PHASE II.pdf | 11 Feb 2023 |
| CERSAI detailsFile: CERSAI PHASE II.pdf | 11 Feb 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A.pdf | 11 Feb 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BANK AC PHASE II.pdf | 11 Feb 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Phase II 2022 Form 2A.pdf | 10 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: form_5__5ut__disclosure_of_sold_booked_inventory-merged-merged-compressed.pdf | 31 Mar 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Engineer Cer Silicon bay Phase II.pdf | 20 Oct 2021 |
| Disclosure of sold/ booked inventoryFile: Sold Inventory Silicon Bay Phase II.pdf | 19 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: QAP_SILICON_BAY_-Phase II_compressed.pdf | 2 Sep 2021 |
| Declaration about Commencement CertificateFile: Declaration about Commencement KJDC.pdf | 28 Aug 2021 |
| Layout approvalFile: 001.pdf | 18 Jun 2021 |
| Copy of Layout Approval (in case of layout)File: 001.pdf | 18 Jun 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement of Silicon 2021.pdf | 15 Jun 2021 |
| Layout approvalFile: layout silicon.pdf | 31 Dec 2020 |
| Building plan approvalFile: N_A_ORDER.pdf | 31 Dec 2020 |
| PAN CardFile: KJDC_PAN_CARD.pdf | 31 Dec 2020 |
| Copy of the legal title reportFile: Silicon Bay Search.pdf | 31 Dec 2020 |
| Details of encumbrancesFile: encrumbrases.pdf | 31 Dec 2020 |
| Copy of Layout Approval (in case of layout)File: layout silicon.pdf | 31 Dec 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: N_A_ORDER.pdf | 31 Dec 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: cOMMENCEMENT 2020_compressed (1).pdf | 31 Dec 2020 |
| Declaration in FORM BFile: Declararion Form B_compressed.pdf | 31 Dec 2020 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Silicon (2).pdf | 31 Dec 2020 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SKM_C25820123119430.pdf | 31 Dec 2020 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ANANDTARA_CA_CERTIFICATE_compressed.pdf | 31 Dec 2020 |
| Proforma of Allotment letterFile: Draft Agreement to Sale.pdf | 31 Dec 2020 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations, which the RERA portal never shows together
- All 31 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep SILICON BAY PHASE II on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Near Nyati Medows
VJ IndiLife Kharadi
VILAS JAVDEKAR GREENSCAPE DEVELOPERS LLP
VJ Central Avenue
Vilas Javdekar Eco Homes
VJ IndiWorks Kharadi Central
Vilas Javdekar Eco Homes
RIVERDALE GRAND
DUVILLE ESTATES PRIVATE LIMITED
Yashwin Orizzonte Phase II
VILAS JAVDEKAR GREENSCAPE DEVELOPERS LLP
ZEN ESTATE
DESTINATION KHARADI DEVELOPERS LLP
Builder: KARAN JANHAVI DEVELOPMENT COROPORATION
KARAN JANHAVI DEVELOPMENT COROPORATION has 3 registrations on MahaRERA, including SILICON BAY PHASE I and SILICON BAY PHASE II. Its filings disclose no earlier MahaRERA projects. Read the full track record.
Frequently asked questions
What does it mean that SILICON BAY PHASE II shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if SILICON BAY PHASE II is delayed beyond 31 Jan 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SILICON BAY PHASE II?
The registered promoter entity is KARAN JANHAVI DEVELOPMENT COROPORATION, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SILICON BAY PHASE II?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SILICON BAY PHASE II?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SILICON BAY PHASE II?
The professionals named in the filing: Architect: Mr Vikas Achalkar; Engineer: Mr Pritam Sambhaji Koli; Chartered Accountant: Mr Paras Vijapure. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SILICON BAY PHASE II?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.