Home / Browse projects / Mumbai Suburban, Maharashtra / SIESTA
SIESTA
By PRESTIGE MULUND REALTY PRIVATE LIMITED
RG-MH-10347 · RERA P51800005285 · Last updated on MahaRERA portal: 3 Jul 2025
Source: official MahaRERA filing
Red flags
- 12 complaints at MahaRERA
- Completion date moved by 18 months
- 1 extension taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
- All 3 completed earlier projects delivered on promise
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SIESTA is a Residential / Group Housing project by PRESTIGE MULUND REALTY PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800005285 on 11 Aug 2017. The registration is recorded completed; possession was promised by 30 Jun 2025. The completion date has moved by 18 months from the original filing. 12 complaints are on record with the regulator.
At a glance
Project
- NameSIESTA
- TypeResidential / Group Housing
- Location
- SWAPNA NAGARI
- MULUND WEST
- Andheri
- Mumbai Suburban
- 400080
- Pincode400080
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800005285
- ReraGenie IDRG-MH-10347
Builder
- NamePRESTIGE MULUND REALTY PRIVATE LIMITED
- Entity typeCompany
- CINU45309MH2016PTC287566
- GSTIN27AAOCA9048H2Z7
- CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
- DirectorsZYAD NOAMAN, UZMA IRFAN
- Other registrations5 more →
- Completed1 of 6
- Declared earlier projects5 →
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on11 Aug 2017
- Promised completion30 Jun 2025
- Revised completionRevised to 30 Jun 2025 (originally 30 Dec 2023)
- Buildings1 building record
- Documents filed127 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SIESTA | NA | 68 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 3 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
7 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 90%.
SIESTA: 78% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 40% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 25% |
Progress on shared amenities15
As on 3 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 15% |
| Water Supply | Yes | 40% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 30% |
| Storm Water Drains | Yes | 10% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 30% |
| Electrical meter room, sub-station, receiving station | Yes | 10% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed646
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Partner | Role in project |
|---|---|
| PRESTIGE MULUND REALTY PRIVATE LIMITED | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThis project is taken over through Resolution Plan passed by NCLT court order dated 23 Mar 2021. Home buyers Association was also a part of the Resolution Plan passed by Majority and approved by NCLT.
Litigation declared5
| Case | Court | Status |
|---|---|---|
| 1161/2009 | HIGH COURT ORIGINAL SIDE | This Suit is clubbed with below Suit and are at the stage of Evidence |
| 1138/2011 | HIGH COURT ORIGINAL SIDE | This Suit is clubbed with above Suit and are at the stage of Evidence |
| 1448/2005 | HIGH COURT ORIGINAL SIDE | For filling written statement |
| 16078/2014 | HIGH COURT APPELLATE SIDE | Order against the Chief Controlling Revenue Authorities and Ors |
| IA 15 IN CIVIL APPEAL 1103 OF 2014 ARISING OUT OF SLP 10760 OF 2008/2016 | HON SUPREME COURT OF INDIA | SLP was allowed and IA is taken out for Refund of NPV which is pending for hearing |
Complaints filed with MahaRERA12
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000001668 | Ramakrishna K Kotian and Usha K Kotian | M/s Ariisto Developers | 08/11/2017 |
| CC006000000022887 | SURINDERSINGH MOKHA | ARIISTO DEVELOPERS PVT. LTD. | 13/01/2018 |
| CC006000000044438 | Ratneshchand Jain | Ariisto Developers Private Limited | 08/05/2018 |
| CC006000000056109 | ARIISTO ALLOTEES WELFARE ASSOCIATION | ARIISTO DEVELOPERS PRIVATE LIMITED (FORMERLY KNOWN AS M/S ARIISTO DEVELOPERS) | 14/09/2018 |
| CC006000000054900 | Rajesh Kriplani & Sheetal Kriplani | M/s Ariisto Developers | 13/06/2018 |
| CC006000000056239 | Gautam J Bhatt | Ariisto Developers Private Limited | 19/09/2018 |
| CC006000000057275 | SATISH KOLHAPURE | ARIISTO DEVELOPERS PRIVATE LIMITED | 21/12/2018 |
| CC006000000078495 | Subrata Haridas Dey | Mr. Atithi Patel | 15/03/2019 |
| CC006000000397589 | mahesh vishandas chandwani | Prestige Mulund Realty Private Limited | 29/09/2023 |
| CC12500814 | Vijesh Dayaldas Narwani | PRESTIGE MULUND REALTY PRIVATE LIMITED | 10/03/2025 |
| CC12504387 | Vipin R Nair | PRESTIGE MULUND REALTY PRIVATE LIMITED | 09/12/2025 |
| CC12602123 | Pritam Dattatraya Wani | PRESTIGE MULUND REALTY PRIVATE LIMITED | 10/04/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 9 May 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 9 May 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 21 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 23 May 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 3 Jul 2025
Documents filed127
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 127 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupancy Certificate Siesta_compressed.pdf | 3 Jul 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: CC - Page 2.pdf | 23 May 2025 |
| Declaration about Commencement CertificateFile: Declaratiom - Land Cost.pdf | 23 May 2025 |
| Declaration about Commencement CertificateFile: FORMAT D- CC Declaration-siesta.pdf | 23 May 2025 |
| Certificates of CA (Form 3)File: Form 3 - PMRPL-Siesta (Annexure 1).pdf | 7 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Siesta Q4.pdf | 19 Apr 2025 |
| Certificates of CA (Form 3)File: Form 3 Siesta Q4.pdf | 19 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Siesta Q4.pdf | 19 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Siesta Q4.pdf | 19 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Siesta Form 1 Q3.pdf | 29 Jan 2025 |
| Certificates of CA (Form 3)File: Siesta Form 3 Q3.pdf | 29 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Siesta Form 2 Q3.pdf | 29 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Siesta Sold Unsold Q3.pdf | 29 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Siesta.pdf | 20 Nov 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2 A Siesta.pdf | 20 Nov 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2 A Siesta.pdf | 20 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Siesta.pdf | 20 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Siesta Form 1 Q2.pdf | 7 Nov 2024 |
| Certificates of CA (Form 3)File: Siesta Form 3 Q2.pdf | 7 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Siesta Form 2 Q2.pdf | 7 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Siesta Sold Unsold Q2.pdf | 7 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - June 2024 (Siesta).pdf | 14 Aug 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Siesta - Form 2.pdf | 14 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: Siesta Q1 sold unsold.pdf | 14 Aug 2024 |
| Certificates of CA (Form 3)File: Siesta Form 3.pdf | 14 Aug 2024 |
| Proforma of Agreement for saleFile: Siesta Agreement for Sale.pdf | 13 May 2024 |
| Proforma of Agreement for saleFile: Siests Suplementary Agreement.pdf | 13 May 2024 |
| Proforma of Agreement for saleFile: Siesta AFS Legacy.pdf | 13 May 2024 |
| Other - LegalFile: Deed of Assignment - Part 1.pdf | 13 May 2024 |
| Other - LegalFile: Deed of Assignment - Part 2.pdf | 13 May 2024 |
| Other - LegalFile: Deed of Assignment - Part 3.pdf | 13 May 2024 |
| Other - LegalFile: Deed of Assignment - Part 4.pdf | 13 May 2024 |
| Other - LegalFile: Deed of Assignment - Part 5.pdf | 13 May 2024 |
| Other - LegalFile: Deed of Assignment - Part 6.pdf | 13 May 2024 |
| Other - LegalFile: Deed of Assignment - Part 7.pdf | 13 May 2024 |
| Other - LegalFile: Deed of Assignment - Part 8.pdf | 13 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Siesta - Q4.pdf | 2 May 2024 |
| Disclosure of sold/ booked inventoryFile: Q4- Siesta FY23-24.pdf | 2 May 2024 |
| Certificates of CA (Form 3)File: Siesta Mar 24.pdf | 2 May 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Siesta - Q4.pdf | 30 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form - 2 - Siesta.pdf | 30 Apr 2024 |
| Declaration about Commencement CertificateFile: Siesta_Declaration.pdf | 14 Mar 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Siesta Form 1 - Quater 3.pdf | 11 Mar 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Siesta Form-02 quater 3.pdf | 11 Mar 2024 |
| Disclosure of sold/ booked inventoryFile: Siesta - Sold Unsold.pdf | 11 Mar 2024 |
| Certificates of CA (Form 3)File: Siesta- CA Certificate.pdf | 11 Mar 2024 |
| Certificates of CA (Form 3)File: Form 3 -Q2 Siesta.pdf | 11 Mar 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A scan (2).pdf | 22 Dec 2023 |
| Certificates of CA (Form 3)File: Siesta Sep-23 Form 3 with Annex scan.pdf | 22 Dec 2023 |
| Declaration in FORM BFile: FORM -B (Promoter) scan.pdf | 21 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A scan.pdf | 21 Dec 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Sept 2023 scan.pdf | 20 Dec 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Sept 2023 scan.pdf | 20 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22) scan.pdf | 20 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18) scan.pdf | 20 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19) scan.pdf | 20 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20) scan.pdf | 20 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21) scan.pdf | 20 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23) scan.pdf | 20 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22) scan.pdf | 20 Dec 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Siesta Form 5 FY22-23.pdf | 18 Dec 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 7 Nov 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 7 Nov 2023 |
| Disclosure of sold/ booked inventoryFile: List of Sold - Unsold.pdf | 7 Nov 2023 |
| Certificates of CA (Form 3)File: Form 3.pdf | 7 Nov 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 3 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 3 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 3 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 3 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 3 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 3 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: List of Sold-Unsold.pdf | 3 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: List of Sold-Unsold.pdf | 3 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: List of Sold-Unsold.pdf | 3 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: List of Sold-Unsold.pdf | 3 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: List of Sold-Unsold.pdf | 3 Oct 2023 |
| Certificates of CA (Form 3)File: Form 3.pdf | 3 Oct 2023 |
| Certificates of CA (Form 3)File: Form 3.pdf | 3 Oct 2023 |
| Certificates of CA (Form 3)File: Form 3.pdf | 3 Oct 2023 |
| Certificates of CA (Form 3)File: Form 3.pdf | 3 Oct 2023 |
Promoter's earlier projects4
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| Forest Hills Ph 1 at The Prestige CityP51800077457 | Veena Nagar, Mulund (W), Mumbai Suburban | 663 | Aug 2024 | Ongoing | Dec 2030 | Not due yet |
| PRESTIGE JASDAN CLASSICP51900031285 | BYCULLA, Mumbai City | - | Oct 2021 | Completed | Dec 2025 | May 2025 |
| PRESTIGE BAGMANE TEMPLE BELLS | Sy No 54 55 56-1 56-2 56-3 56-4 57-2 Hosekerahalli Village Uttarahalli Hobli Bangalore South | 968 | - | Completed | Sep 2019 | Jun 2019 |
| PRESTIGE DEJAVU | Khata No 51-1 Promenade Road Coles Road Frazer Town Bangalore | 40 | - | Completed | Aug 2019 | Aug 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 5 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 127 filed documents as one ZIP, foldered, with a manifest
Keep SIESTA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near MULUND WEST6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 200 registered projects within 2 km.
Eternia Towers A to D
Oberoi Constructions Limited
Bellanza Phase 1 - Wing A, B, C at The Prestig
PRESTIGE MULUND REALTY PRIVATE LIMITED
Atmosphere O2
Atmosphere Realty Pvt Ltd
Bellanza Phase 2 - Wing D, E, F at The Prestig
PRESTIGE MULUND REALTY PRIVATE LIMITED
Forest Hills Ph 1 at The Prestige City
PRESTIGE MULUND REALTY PRIVATE LIMITED
Kalpataru Elitus
Arimas Real Estate Private Limited
See every Mumbai Suburban project, with the district possession charts
Builder: PRESTIGE MULUND REALTY PRIVATE LIMITED
PRESTIGE MULUND REALTY PRIVATE LIMITED has 6 registrations on MahaRERA, including SIESTA and Bellanza Phase 1 - Wing A, B, C at The Prestige City. Its filings disclose 5 earlier MahaRERA projects: declares 4 of 4 past projects completed on time. Litigation is declared on 5 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if SIESTA is delayed beyond 30 Jun 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SIESTA?
The registered promoter entity is PRESTIGE MULUND REALTY PRIVATE LIMITED, a company as per the filing. Its CIN U45309MH2016PTC287566 and GSTIN 27AAOCA9048H2Z7 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SIESTA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against SIESTA?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for SIESTA?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
What should I check before booking in SIESTA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback