Registered Litigation declared Residential / Group Housing project

SIENNAA WING F

By S D Corporation Private Limited

RG-MH-84611 · RERA P51800019693 · Last updated on MahaRERA portal: 1 Oct 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 2 cases
  • 31 complaints at MahaRERA
  • Completion date moved by 40 months
  • 2 extensions taken
  • Rs 100.00 crore secured on the land, in favour of JM Financial Credit Solutions Limited

Clear

  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Apr 2028Possession promisedmoved 40 months from the original
6 of 11Construction stages donefurthest along: Internal walls, 55%
0 of 33Units unsoldnot recorded sold or booked
31Complaints at MahaRERAon this registration
Jump to the 141 documents Report an error

SIENNAA WING F is a Residential / Group Housing project by S D Corporation Private Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800019693 on 22 Feb 2019. Possession is promised by 30 Apr 2028. The completion date has moved by 40 months from the original filing. 33 of the 33 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete. 31 complaints are on record with the regulator.

At a glance

Project

  • NameSIENNAA WING F
  • TypeResidential / Group Housing
  • Location
    • THAKUR VILLAGE ROAD
    • KANDIVALI
    • Borivali
    • Mumbai Suburban
    • 400101
  • Pincode400101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800019693
  • ReraGenie IDRG-MH-84611

Builder

  • NameS D Corporation Private Limited
  • Entity typeCompany
  • CINU70109MH1998PTC116091
  • GSTIN27AADCS4496C1Z9
  • CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
  • DirectorSrinivasan Iyer
  • Other registrations14 more →
  • No longer live4 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

this monthRegisteredFeb 2019First promiseDec 2024Revised toApr 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on22 Feb 2019
  • Promised completion30 Apr 2028
  • Revised completionRevised to 30 Apr 2028 (originally 30 Dec 2024)
  • Buildings1 building record
  • Documents filed141 files

Current status

100%33 of 33 units booked

Figures as on 1 Oct 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SIENNAA WING FNA292933033

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 1 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 55%.

SIENNAA WING F: 60% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises55%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 1 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed32

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots32
Closed/Covered32

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area319 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofJM Financial Credit Solutions Limited
Secured amountRs 100.00 crore
CERSAI search filedYes
Declared on2 Feb 2026

Approvals and building plan

Sanctioning authorityMaharashtra Housing and Area Development Authority
Permissible FSI4753.92
Proposed, not sanctioned4,754 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch240, NAVSARI BUILDING, D N ROAD, FORT, MUMBAI 400001

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectANIL KODKANI
EngineerAshok Singh
Chartered AccountantBhavesh Ramesh Nagda
Chartered AccountantHarshad Doshi & Co
PartnerRole in project
S D Corporation Private Limited-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

P51800019693/WarDec 2024 → Apr 2028

Reason as filed by the promoterNA

EXT51800024530Dec 2024 → Dec 2027

Reason as filed by the promoterThe delay in completion of the projects is attributable to a confluence of unforeseen and uncontrollable circumstances. The COVID-19 pandemic and the consequent lockdowns severely impacted labour availability, bringing construction activities to a standstill for an extended period. This disruption was further aggravated by a sharp escalation in the cost of construction materials and services, which placed significant pressure on project finances. Additionally, several vendors demanded advance payments contrary to the existing contractual terms, thereby intensifying cash flow constraints. Simul

Litigation declared2

CaseCourtStatus
1267/2009BOMBAY HIGH COURTPENDING FOR FINAL HEARING
1267/2009Bombay High CourtOngoing

Complaints filed with MahaRERA31

Case no.ComplainantRespondentFiled
CC006000000195274SD Corporation Pvt ltd.,Alim Khan17/12/2020
CC006000000396759SD Corporation Pvt LtdNinad Desai26/07/2023
CC12500116Rajat ChatterjeeS D Corporation Private Limited12/01/2025
CC12500071santosh somnath chakorS D Corporation Private Limited08/01/2025
CC12500409Mahesh Ganesh MamgaiS D Corporation Private Limited07/02/2025
CC12502089Purav GordiaS D Corporation Private Limited26/06/2025
CC12502088sunil patilS D Corporation Private Limited26/06/2025
CC12502107KAMLESH RAJENDRABHAI AGRAWALS D Corporation Private Limited27/06/2025
CC12502110sharad kadamS D Corporation Private Limited27/06/2025
CC12502111sharad kadamS D Corporation Private Limited27/06/2025
CC12502292JIGNESHKUMAR MAFATLAL MISTRYS D Corporation Private Limited07/07/2025
CC12502341Yogita ThakurS D Corporation Private Limited10/07/2025
CC12503642Shashi Kumar Ramshra YadavS D Corporation Private Limited13/10/2025
CC12504511BAIJU MARKRAND MEHTAS D Corporation Private Limited17/12/2025
CC12600153Deepika Jayesh PawarS D Corporation Private Limited09/01/2026
CC12600154Mahendra ParmarS D Corporation Private Limited09/01/2026
CC12600249Chiranjit ChattopadhyayS D Corporation Private Limited14/01/2026
CC12600301Sarit SahaS D Corporation Private Limited16/01/2026
CC12600350Shyam DhanorkarS D Corporation Private Limited19/01/2026
CC12600376santosh somnath chakorS D Corporation Private Limited20/01/2026
CC12600404santosh somnath chakorS D Corporation Private Limited22/01/2026
CC12600429Ravi DwivediS D Corporation Private Limited23/01/2026
CC12600551Mahesh Ganesh MamgaiS D Corporation Private Limited01/02/2026
CC12601947Sunil SInghS D Corporation Private Limited02/04/2026
CC12601948Deepak SinghS D Corporation Private Limited02/04/2026
CC12605271Rajat ChatterjeeS D Corporation Private Limited18/08/2026
CC12602343Pankaj Joginder NarulaS D Corporation Private Limited21/04/2026
CC12602582Pragati GadadeS D Corporation Private Limited03/05/2026
CC12602604Vidya ParabS D Corporation Private Limited04/05/2026
CC12603904Nayana ParmarS D Corporation Private Limited24/06/2026
CC12605459kiran visputeS D Corporation Private Limited24/08/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 13 Feb 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Feb 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Feb 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Feb 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Apr 2028

Documents filed141

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 141 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2024-2025)File: Siennaa wing F form 5 24 25.pdf1 Oct 2026
Form 2A (FY 2023-2024)File: Siennaa F Quality Certificate Dec 24.pdf29 Sep 2026
Form 2A (FY 2024-2025)File: Form 2A (14).pdf29 Sep 2026
Form 2A (FY 2025-2026)File: Siennaa F Quality Certificate Dec 24.pdf29 Sep 2026
Form 2A (FY 2021-2022)File: Siennaa F Quality Certificate Dec 24.pdf29 Sep 2026
Form 2A (FY 2022-2023)File: Form 2A Siennaa wing F Sep 2024.pdf29 Sep 2026
Form 2A (FY 2020-2021)File: Form 2A Siennaa wing F Sep 2024.pdf29 Sep 2026
Form 2A (FY 2019-2020)File: Form 2A (15).pdf29 Sep 2026
Form 2A (FY 2018-2019)File: Form 2A (15).pdf29 Sep 2026
Form 5 (FY 2025-2026)File: Form 5 Siennaa Wing F.pdf29 Sep 2026
Form 1File: Architect Certificate Bldg No 05 Wing F March 26.pdf2 Jul 2026
Form 2File: Engineer Certificate- Siennaa F- Mar 26.pdf2 Jul 2026
Form 3File: Sienna Wing F Form 3 March 26.pdf2 Jul 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Inventory-Sieennaa Wing F 31-March-2026.pdf2 Jul 2026
Form 1File: Form 1 - Arch Cert - Jun-25 - Siennaa F.pdf1 Jul 2026
Form 2File: Engineer Certificate- Siennaa F- Jun 25.pdf1 Jul 2026
Form 3File: 202506 Sienna Wing F Form 3.pdf1 Jul 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Inventory - Siennaa F - June 25.pdf1 Jul 2026
Form 1File: Architect cert Wing F Dt 30 Sep 25.pdf1 Jul 2026
Form 2File: Engineer Certificate- Siennaa F- Sep 25.pdf1 Jul 2026
Form 3File: 202509 Sienna Wing F Form 3.pdf1 Jul 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Inventory - Siennaa F Sept 25.pdf1 Jul 2026
Form 1File: Architect cert bldg No 5 Wing F Dt 31 Dec 25.pdf24 Jun 2026
Form 2File: Engineer Certificate- Siennaa F- Dec 25.pdf24 Jun 2026
Form 3File: Sienna Wing F Form 3 Dec 25.pdf24 Jun 2026
Disclosure of Sold and Booked InventoryFile: Dislosure of Inventory - Siennaa F - Dec 25.pdf24 Jun 2026
Form 1File: Architect Certificate Bldg No 05 Wing F March 26.pdf24 Jun 2026
Form 2File: Engineer Certificate- Siennaa F- Mar 26.pdf24 Jun 2026
Form 3File: Sienna Wing F Form 3 March 26.pdf24 Jun 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Inventory-Sieennaa Wing F 31-March-2026.pdf24 Jun 2026
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Sienna F.pdf27 Jun 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Certificate Bldg No 5 Wing F March 25.pdf20 Jun 2025
Certificates of CA (Form 3)File: 202412 Sienna Wing F Form 3 March-25.pdf20 Jun 2025
Certificates of CA (Form 3)File: 202412 Sienna Wing F Form 3 March-25.pdf20 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate- Siennaa F-March 25.pdf20 Jun 2025
Disclosure of sold/ booked inventoryFile: SD Corp - Siennaa F - Disclosure of inventory.pdf20 Jun 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Siennaa Wing F dec 24.pdf18 Jun 2025
Certificates of CA (Form 3)File: 202412 Sienna Wing F Form 3.pdf18 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Siennaa F Dec 24.pdf18 Jun 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Siennaa F Quality Certificate Dec 24.pdf18 Jun 2025
Certificates of CA (Form 3)File: 202403 Sienna Wing F Form 3 31st Mar 24.pdf14 Dec 2024
Certificates of CA (Form 3)File: 202406 Sienna Wing F Form 3 30th June 24.pdf14 Dec 2024
Certificates of CA (Form 3)File: 202409 Sienna Wing F Form 3 30th Sep 24.pdf14 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Siennaa F Jun 24.pdf14 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Siennaa Wing F Form 2 Sep 24.pdf14 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Siennaa Wing F Arch Cert Mar 24.pdf11 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Siennaa Wing F Arch Cer Jun 24.pdf11 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Siennaa Wing F Arch Cer Sep 24.pdf11 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Siennaa Wing F Form 2 Mar 24.pdf11 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Siennaa Wing F Form 2 Jun 24.pdf11 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Siennaa Wing F Form 2 Sep 24.pdf11 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Siennaa wing F Jun 2024.pdf9 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Certificate Bldg No 5 Wing F.pdf3 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate- Siennaa F Mar 2024.pdf3 Dec 2024
Declaration in FORM BFile: Form B RERA extension Wing F.pdf5 Aug 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Certificate Wing 24 Wing F.pdf31 Jul 2024
Certificates of CA (Form 3)File: RERA Certificate Siennaa F.pdf31 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Cert Wing F Sienna 31 03 2023.pdf15 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Cert Sienna F.pdf12 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Siennaa Wing F.pdf4 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Sienna F.pdf12 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Siennaa Wing F.pdf28 Mar 2024
Annual Audit Report of Statutory CA (Form 5)File: Sienna Wing F Form 5 - Mar-22.pdf27 Dec 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: B5 Wing F Cft.pdf18 May 2023
Disclosure of sold/ booked inventoryFile: Siennaa F Dislosure Of Sold.pdf18 May 2023
Certificates of CA (Form 3)File: Sienna Wing F - Form 3 - Sept-22.pdf2 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: B5 Wing F.pdf19 Dec 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sieena Wing F.pdf19 Sep 2022
Certificates of CA (Form 3)File: 202206 Sienna Wing F Form 3.pdf19 Sep 2022
Certificates of CA (Form 3)File: 202206 Sienna Wing F Form 3.pdf14 Sep 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Samata Nagar Bldg No 5 Wing F RERA Architect Certificate.pdf9 Sep 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sieena Wing F.pdf9 Sep 2022
Certificates of CA (Form 3)File: 202203 Sienna Wing F Form 3.pdf9 Sep 2022
Disclosure of sold/ booked inventoryFile: Siennaa Wing F.pdf19 Jul 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate - Siennaa Wing F Dec 2021.pdf21 Jun 2022
Certificates of CA (Form 3)File: Form 3 - SIENNAA - Wing F.pdf21 Jun 2022
Disclosure of sold/ booked inventoryFile: RERA - Siennaa Wing F - Disclosure of Inventory - Mar 31, 2022.pdf26 Apr 2022
Disclosure of sold/ booked inventoryFile: Siennaa F.pdf27 Jan 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate - Siennaa Wing F Dec 2021.pdf10 Jan 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality Assurance certificate - Siennaa Wing F Dec 2021.pdf10 Jan 2022

How this compares with Mumbai Suburban

100%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 40 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SIENNAA WING F on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KANDIVALI6,700+ in Mumbai Suburban

2 kmSIENNAA WING FCompleted 25Lapsed / revoked 13Other 46Dot size: filed unitsN

Filed coordinates, straight-line distance. 84 registered projects within 2 km.

Builder: S D Corporation Private Limited

S D Corporation Private Limited has 15 registrations on MahaRERA, including SIENNAA WING A and SIENNAA WING B. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Litigation is declared on 11 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if SIENNAA WING F is delayed beyond 30 Apr 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SIENNAA WING F?

The registered promoter entity is S D Corporation Private Limited, a company as per the filing. Its CIN U70109MH1998PTC116091 and GSTIN 27AADCS4496C1Z9 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SIENNAA WING F?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SIENNAA WING F?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SIENNAA WING F?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SIENNAA WING F?

The professionals named in the filing: Architect: ANIL KODKANI; Engineer: Ashok Singh; Chartered Accountant: Bhavesh Ramesh Nagda; Chartered Accountant: Harshad Doshi & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SIENNAA WING F?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SIENNAA WING F. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SIENNAA WING F to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.