ENSO SANZA
RG-MH-66611 · RERA P51800013955 · Last updated on MahaRERA portal: 24 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 4 months past the filed date
- 30 complaints at MahaRERA
- Completion date moved by 30 months
- 3 extensions taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
ENSO SANZA is a Others project by Sai Aastha Developers in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800013955 on 2 Nov 2017. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 30 months from the original filing. 389 of the 671 units on this registration are recorded sold or booked, and 11 of 22 construction stages are filed complete. 30 complaints are on record with the regulator.
At a glance
Project
- NameENSO SANZA
- TypeOthers
- Location
- Waderpada Road No 2
- Hanuman Nagar
- Borivali
- Mumbai Suburban
- 400101
- Pincode400101
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800013955
- ReraGenie IDRG-MH-66611
Builder
- NameSai Aastha Developers
- Entity typePartnership
- PartnersShakrendra Dhanpat Seth, Dhanpat Parshuram Seth, Nimish Thakarshi Dharamshi, AMIT HARESH DUHLANI
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on2 Nov 2017
- Promised completion30 Jun 2026
- Revised completionRevised to 30 Jun 2026 (originally 30 Dec 2023)
- Buildings2 building records
- Documents filed142 files
Current status
Figures as on 24 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SaiNath SRA CHS Ltd | NA | 24 | 22 | 244 | 11 | 255 |
| ENSO SANZA | NA | 25 | 23 | 407 | 9 | 416 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 24 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
11 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 92%.
SaiNath SRA CHS Ltd88%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 92% |
| Sanitary Fittings within the flats / premises | 92% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 92% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 92% |
ENSO SANZA77%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 45% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 81% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 70% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 70% |
Progress on shared amenities15
As on 24 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 60% |
| Water Supply | Yes | 65% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 85% |
| Storm Water Drains | Yes | 85% |
| Landscaping & Tree Planting | Yes | 40% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 88% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 75% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 75% |
| Electrical meter room, sub-station, receiving station | Yes | 35% |
| Aggregate area of recreational Open Space | Yes | 90% |
| Open Parking | No | Not applicable |
Parking filed111
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| SaiNath SRA CHS Ltd | 47 | 47 |
| ENSO SANZA | 64 | 64 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| SaiNath SRA CHS Ltd | NA | Rs 53.59 cr | Rs 50.14 cr |
| ENSO SANZA | NA | Rs 53.59 cr | Rs 50.14 cr |
| - | NA | Rs 10.65 cr | Rs 63.02 lakh |
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | CREATIVE CONSULTANCY |
| Engineer | M.S SHAIKH |
| Chartered Accountant | KANU DOSHI ASSOCIATES LLP |
| Partner | Role in project |
|---|---|
| Sai Aastha Developers | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to the Covid-19 outbreak and shortage labourer caused the delay in completion of the project
Reason as filed by the promoterDelays in Approvals Administrative delays from the Municipal Corporation of Greater Mumbal (MCGM) and the Slum Rehabilitation Authority (SRA) occurred due to election-related duties. Specifically, Loksabha Election Code of Conduct Implemented from 20th March 2024 to 1st June 2024, during which officers were deputed for election duties, and Vidhan Sabha Election Code of Conduct: Implemented from 15th October 2024 to 23rd November 2024, further contributing to delays in the approval process B. Labour Shortage. The construction sector faced a widespread labour shortage. further disrupting the pro
Reason as filed by the promoterReasons for Seeking Extension: 1. COVID-19 Pandemic: The outbreak of the COVID-19 pandemic has severely impacted our construction timelines. The lockdowns and restrictions imposed led to a complete halt of construction activities. The pandemic is recognized as a force majeure event, affecting not only our operations but also the availability of Labour and raw materials. 2. Labour Shortages: Following the pandemic, we faced considerable challenges in securing adequate Labour. The shortage of skilled Labourers has further delayed the progress of construction despite our best efforts to expedite
Complaints filed with MahaRERA30
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000344270 | MUKESH SHANKAR PARDESHI | DHANPAT PARSHURAM SETH | 09/02/2023 |
| CC006000000397169 | Om Prakash Singh | M/s. Sai Astha Developer Partner Nimish Thakarshi Dharamshi | 21/08/2023 |
| CC006000000429245 | joel dsouza | Sai Aastha Developers | 14/02/2024 |
| CC006000000591325 | Virendra C Shirdhankar | Sai Aastha Developers | 31/07/2024 |
| CC12503760 | sharad shivaji kolekar | Sai Aastha Developers | 27/10/2025 |
| CC12500122 | Roshani Jain | Sai Aastha Developers | 13/01/2025 |
| CC12500640 | VIRAL PARESH CHAWDA | Sai Aastha Developers | 23/02/2025 |
| CC12501228 | Manish Suryakant Patkar | Sai Aastha Developers | 13/04/2025 |
| CC12502867 | Alok Rajan Pandey | Sai Aastha Developers | 15/08/2025 |
| CC12503692 | Vrunda Milind Kandalkar | Sai Aastha Developers | 16/10/2025 |
| CC12504388 | Mayur Pramod Dhumal | Sai Aastha Developers | 09/12/2025 |
| CC12600387 | Abhijeet Vijay Ghag | Sai Aastha Developers | 21/01/2026 |
| CC12600494 | Kiran Narayan Patil | Sai Aastha Developers | 27/01/2026 |
| CC12600664 | Shridhar Jinde | Sai Aastha Developers | 04/02/2026 |
| CC12602142 | Sukanya Ketan Joshi | Sai Aastha Developers | 11/04/2026 |
| CC12602145 | MADHURI SATYAVIJAY TAWADE | Sai Aastha Developers | 11/04/2026 |
| CC12602190 | BHAVNA NANDKUMAR CHEULKAR | Sai Aastha Developers | 14/04/2026 |
| CC12602191 | CHANDRAKANT SOPAN HAGAVANE | Sai Aastha Developers | 14/04/2026 |
| CC12602192 | MANOJ DATTARAM BHATKAR | Sai Aastha Developers | 14/04/2026 |
| CC12602219 | SHEETAL VIVEK SHINDE | Sai Aastha Developers | 15/04/2026 |
| CC12602220 | CHANDRASHEKAR TEJURAM YADAV | Sai Aastha Developers | 15/04/2026 |
| CC12602909 | Jayesh Dinesh Mali | Sai Aastha Developers | 17/05/2026 |
| CC12604190 | Sonam Gupta | Sai Aastha Developers | 04/07/2026 |
| CC12603532 | Rahul Mohani Nautiyal | Sai Aastha Developers | 08/06/2026 |
| CC12604087 | Shruti Laxmana Shetty | Sai Aastha Developers | 30/06/2026 |
| CC12604628 | Prasad Surendra More | Sai Aastha Developers | 24/07/2026 |
| CC12604248 | Viraj Gajanan Ghanekar | Sai Aastha Developers | 06/07/2026 |
| CC12604482 | Sunita Rodrigues | Sai Aastha Developers | 18/07/2026 |
| CC12604627 | Arvind Valji Bhanushali | Sai Aastha Developers | 24/07/2026 |
| CC12604687 | Zoya Javed Qureshi | Sai Aastha Developers | 26/07/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 18 Aug 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 27 Oct 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 7 May 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 24 Jul 2026Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed142
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 142 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Commencement certificateFile: Full CC.pdf | 24 Jul 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 24 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 Q1 202627.pdf | 24 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 Q1 202627.pdf | 24 Jul 2026 |
| Withdrawal Update Form 1File: Signed Form 1 - Q4- 2025-26.pdf | 8 Jun 2026 |
| Withdrawal Update Form 1File: Signed Form 1 - Q4- 2025-26.pdf | 8 Jun 2026 |
| Withdrawal Update Form 2File: Form 2 - Q4 - FY 2025-26.PDF | 8 Jun 2026 |
| Withdrawal Update Form 2File: Form 2 - Q4 - FY 2025-26.PDF | 8 Jun 2026 |
| Withdrawal Update Form 3File: Signed Form 3 - Q4 - FY 2025-26.pdf | 8 Jun 2026 |
| Withdrawal Update Form 3File: Signed Form 3 - Q4 - FY 2025-26.pdf | 8 Jun 2026 |
| Form 2A (FY 2025-2026)File: Signed Form 2A - FY 2025-26.PDF | 8 Jun 2026 |
| Withdrawal Update Form 1File: form 1 final.pdf | 27 Jan 2026 |
| Withdrawal Update Form 2File: Form 2 Q3.pdf | 27 Jan 2026 |
| Withdrawal Update Form 3File: Form 3 - Q3_0001 (1).pdf | 27 Jan 2026 |
| Withdrawal Update Form 1File: FORM 1.pdf | 24 Jan 2026 |
| Withdrawal Update Form 1File: FORM 1 FINAL.pdf | 24 Jan 2026 |
| Withdrawal Update Form 2File: Form 2 - Q1.pdf | 24 Jan 2026 |
| Withdrawal Update Form 2File: Form 2 - Q2_0001.pdf | 24 Jan 2026 |
| Withdrawal Update Form 3File: Form -3 Q-1.pdf | 24 Jan 2026 |
| Withdrawal Update Form 3File: Form-3 Q-2 (1).pdf | 24 Jan 2026 |
| Certificates of CA (Form 3)File: Form-3 - Final (1).pdf | 14 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of inventory - Final (1).pdf | 14 Apr 2025 |
| Declaration in FORM BFile: Form B.pdf | 12 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Disclouser of Sold booked inventory.pdf | 12 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Wing A.pdf | 10 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Wing B.pdf | 10 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Wing C.pdf | 10 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Wing D.pdf | 10 Mar 2025 |
| CERSAI detailsFile: CERSAI Declaration.pdf | 10 Mar 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: AD - Disclosure of Interest.pdf | 10 Mar 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: DS - Disclosure of Interest.pdf | 10 Mar 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: SS - Disclosure of Interest - Original.pdf | 10 Mar 2025 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: Format A.pdf | 26 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1-B Wing.pdf | 19 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: D wing Form 1.pdf | 19 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: C Wing Form 1.pdf | 19 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: A Wing Form 1.pdf | 19 Feb 2025 |
| Certificates of CA (Form 3)File: Form 3.pdf | 19 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 19 Feb 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: FCC 19112024.pdf | 17 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 2223.pdf | 7 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 2324.pdf | 7 Jan 2025 |
| Certificates of CA (Form 3)File: Form 3.pdf | 30 Dec 2024 |
| Certificates of CA (Form 3)File: Form 3.pdf | 30 Dec 2024 |
| Certificates of CA (Form 3)File: Form 3.pdf | 30 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: RERA Certificate form -5.pdf | 27 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: D Wing Sale Bldg.pdf | 26 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: C Wing Sale Bldg.pdf | 26 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: B Wing Sale Bldg.pdf | 26 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: A Wing Sale Bldg.pdf | 26 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Rehab Bldg Phase II.pdf | 26 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Rehab Bldg Phase I.pdf | 26 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: C and D Wing Sale Bldg.pdf | 26 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: B Wing Sale Bldg.pdf | 26 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Rehab Bldg Phase II.pdf | 26 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Rehab Bldg Phase I.pdf | 26 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: C and D Wing Sale Bldg.pdf | 26 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: B Wing Sale Bld.pdf | 26 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: A Wing.pdf | 26 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: A Wing Sale Bldg.pdf | 26 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf | 26 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 30062024.pdf | 26 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 30092024.pdf | 26 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: C D Wing Sale Bldg.pdf | 25 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: A Wing Sale Bldg.pdf | 25 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: B Wing Sale Bldg.pdf | 25 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Sai Aastha Form -2-1-4.pdf | 25 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Sai Aastha Form -2-1-4.pdf | 25 Jan 2024 |
| Certificates of CA (Form 3)File: sai astha form 3.pdf | 25 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 A WING_0001.pdf | 6 Dec 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 B WING_0001.pdf | 6 Dec 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 SALE_0001.pdf | 6 Dec 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2_0001.pdf | 6 Dec 2023 |
| Certificates of CA (Form 3)File: Sai Ashtha Form 3 (1).pdf | 6 Dec 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: A Wing Sale Bldg.pdf | 22 Aug 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: B Wing Sale Bldg.pdf | 22 Aug 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: C D Wing Sale Bldg.pdf | 22 Aug 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 22 Aug 2023 |
| Certificates of CA (Form 3)File: SAI AASTHA DEVELOPERS -FORM 3 (1).pdf | 22 Aug 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Rehab 30 Nov 2022.pdf | 22 Feb 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 142 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep ENSO SANZA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Hanuman Nagar6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 180 registered projects within 2 km.
Sheetal Uptown
SIDHESHWAR LIFESPACES PRIVATE LIMITED
SPRINGWOODS
PRATIK CONSTRUCTION
Godrej Nest
Shivam Megastructures Pvt Ltd
PATON TOWERS
PRAVIN VIRAM SATRA
Godrej Bliss
SHIVAM DEVELOPERS
SHEETAL UPTOWN PHASE II
SIDHESHWAR LIFESPACES PRIVATE LIMITED
See every Mumbai Suburban project, with the district possession charts
Builder: Sai Aastha Developers
Sai Aastha Developers has 1 registration on MahaRERA, including ENSO SANZA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that ENSO SANZA shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if ENSO SANZA is delayed beyond 30 Jun 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of ENSO SANZA?
The registered promoter entity is Sai Aastha Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in ENSO SANZA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against ENSO SANZA?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for ENSO SANZA?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at ENSO SANZA?
The professionals named in the filing: Architect: CREATIVE CONSULTANCY; Engineer: M.S SHAIKH; Chartered Accountant: KANU DOSHI ASSOCIATES LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ENSO SANZA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback