Home / Browse projects / Mumbai Suburban, Maharashtra / ENSO SANZA

Registration lapsed No litigation declared Others project

ENSO SANZA

By Sai Aastha Developers

RG-MH-66611 · RERA P51800013955 · Last updated on MahaRERA portal: 24 Jul 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date
  • 30 complaints at MahaRERA
  • Completion date moved by 30 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
11 of 22Construction stages doneacross 2 buildings; furthest along: Internal walls, 92%
282 of 671Units unsoldnot recorded sold or booked
30Complaints at MahaRERAon this registration
Jump to the 142 documents Report an error

ENSO SANZA is a Others project by Sai Aastha Developers in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800013955 on 2 Nov 2017. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 30 months from the original filing. 389 of the 671 units on this registration are recorded sold or booked, and 11 of 22 construction stages are filed complete. 30 complaints are on record with the regulator.

At a glance

Project

  • NameENSO SANZA
  • TypeOthers
  • Location
    • Waderpada Road No 2
    • Hanuman Nagar
    • Borivali
    • Mumbai Suburban
    • 400101
  • Pincode400101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800013955
  • ReraGenie IDRG-MH-66611

Builder

  • NameSai Aastha Developers
  • Entity typePartnership
  • PartnersShakrendra Dhanpat Seth, Dhanpat Parshuram Seth, Nimish Thakarshi Dharamshi, AMIT HARESH DUHLANI

Key dates

4 months past promisethis monthRegisteredNov 2017First promiseDec 2023Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on2 Nov 2017
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 30 Dec 2023)
  • Buildings2 building records
  • Documents filed142 files

Current status

58%389 of 671 units booked
85.7%Work done, per cost certificate

Figures as on 24 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SaiNath SRA CHS LtdNA242224411255
ENSO SANZANA25234079416

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 24 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 92%.

SaiNath SRA CHS Ltd88%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises92%
Sanitary Fittings within the flats / premises92%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.92%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.92%
ENSO SANZA77%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises45%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks81%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.70%

Progress on shared amenities15

As on 24 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes60%
Water SupplyYes65%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes85%
Storm Water DrainsYes85%
Landscaping & Tree PlantingYes40%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes88%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes75%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes75%
Electrical meter room, sub-station, receiving stationYes35%
Aggregate area of recreational Open SpaceYes90%
Open ParkingNoNot applicable

Parking filed111

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots111
Closed/Covered111
BuildingClosed/CoveredTotal
SaiNath SRA CHS Ltd4747
ENSO SANZA6464

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area3,563 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on23 Jan 2026

Approvals and building plan

Sanctioning authoritySLUM REHABILATION AUTHORITY
Permissible FSI21108.6
Proposed, not sanctioned15,636 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNATIONAL COLLEGE BRANCH BANDRA WEST MUMBAI 400050
Estimated costRs 117.82 cr
Cost incurredRs 100.92 cr
Work done85.65%
BuildingWingEstimatedIncurred
SaiNath SRA CHS LtdNARs 53.59 crRs 50.14 cr
ENSO SANZANARs 53.59 crRs 50.14 cr
-NARs 10.65 crRs 63.02 lakh

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectCREATIVE CONSULTANCY
EngineerM.S SHAIKH
Chartered AccountantKANU DOSHI ASSOCIATES LLP
PartnerRole in project
Sai Aastha Developers-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800017421Dec 2023 → Dec 2024

Reason as filed by the promoterDue to the Covid-19 outbreak and shortage labourer caused the delay in completion of the project

EXT51800027149Dec 2023 → Dec 2025

Reason as filed by the promoterDelays in Approvals Administrative delays from the Municipal Corporation of Greater Mumbal (MCGM) and the Slum Rehabilitation Authority (SRA) occurred due to election-related duties. Specifically, Loksabha Election Code of Conduct Implemented from 20th March 2024 to 1st June 2024, during which officers were deputed for election duties, and Vidhan Sabha Election Code of Conduct: Implemented from 15th October 2024 to 23rd November 2024, further contributing to delays in the approval process B. Labour Shortage. The construction sector faced a widespread labour shortage. further disrupting the pro

EA27012619587Dec 2023 → Jun 2026

Reason as filed by the promoterReasons for Seeking Extension: 1. COVID-19 Pandemic: The outbreak of the COVID-19 pandemic has severely impacted our construction timelines. The lockdowns and restrictions imposed led to a complete halt of construction activities. The pandemic is recognized as a force majeure event, affecting not only our operations but also the availability of Labour and raw materials. 2. Labour Shortages: Following the pandemic, we faced considerable challenges in securing adequate Labour. The shortage of skilled Labourers has further delayed the progress of construction despite our best efforts to expedite

Complaints filed with MahaRERA30

Case no.ComplainantRespondentFiled
CC006000000344270MUKESH SHANKAR PARDESHIDHANPAT PARSHURAM SETH09/02/2023
CC006000000397169Om Prakash SinghM/s. Sai Astha Developer Partner Nimish Thakarshi Dharamshi21/08/2023
CC006000000429245joel dsouzaSai Aastha Developers14/02/2024
CC006000000591325Virendra C ShirdhankarSai Aastha Developers31/07/2024
CC12503760sharad shivaji kolekarSai Aastha Developers27/10/2025
CC12500122Roshani JainSai Aastha Developers13/01/2025
CC12500640VIRAL PARESH CHAWDASai Aastha Developers23/02/2025
CC12501228Manish Suryakant PatkarSai Aastha Developers13/04/2025
CC12502867Alok Rajan PandeySai Aastha Developers15/08/2025
CC12503692Vrunda Milind KandalkarSai Aastha Developers16/10/2025
CC12504388Mayur Pramod DhumalSai Aastha Developers09/12/2025
CC12600387Abhijeet Vijay GhagSai Aastha Developers21/01/2026
CC12600494Kiran Narayan PatilSai Aastha Developers27/01/2026
CC12600664Shridhar JindeSai Aastha Developers04/02/2026
CC12602142Sukanya Ketan JoshiSai Aastha Developers11/04/2026
CC12602145MADHURI SATYAVIJAY TAWADESai Aastha Developers11/04/2026
CC12602190BHAVNA NANDKUMAR CHEULKARSai Aastha Developers14/04/2026
CC12602191CHANDRAKANT SOPAN HAGAVANESai Aastha Developers14/04/2026
CC12602192MANOJ DATTARAM BHATKARSai Aastha Developers14/04/2026
CC12602219SHEETAL VIVEK SHINDESai Aastha Developers15/04/2026
CC12602220CHANDRASHEKAR TEJURAM YADAVSai Aastha Developers15/04/2026
CC12602909Jayesh Dinesh MaliSai Aastha Developers17/05/2026
CC12604190Sonam GuptaSai Aastha Developers04/07/2026
CC12603532Rahul Mohani NautiyalSai Aastha Developers08/06/2026
CC12604087Shruti Laxmana ShettySai Aastha Developers30/06/2026
CC12604628Prasad Surendra MoreSai Aastha Developers24/07/2026
CC12604248Viraj Gajanan GhanekarSai Aastha Developers06/07/2026
CC12604482Sunita RodriguesSai Aastha Developers18/07/2026
CC12604627Arvind Valji BhanushaliSai Aastha Developers24/07/2026
CC12604687Zoya Javed QureshiSai Aastha Developers26/07/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 18 Aug 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Oct 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 7 May 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Jul 2026Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed142

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 142 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Commencement certificateFile: Full CC.pdf24 Jul 2026
Withdrawal Update Form 1File: Form 1.pdf24 Jul 2026
Withdrawal Update Form 2File: Form 2 Q1 202627.pdf24 Jul 2026
Withdrawal Update Form 3File: Form 3 Q1 202627.pdf24 Jul 2026
Withdrawal Update Form 1File: Signed Form 1 - Q4- 2025-26.pdf8 Jun 2026
Withdrawal Update Form 1File: Signed Form 1 - Q4- 2025-26.pdf8 Jun 2026
Withdrawal Update Form 2File: Form 2 - Q4 - FY 2025-26.PDF8 Jun 2026
Withdrawal Update Form 2File: Form 2 - Q4 - FY 2025-26.PDF8 Jun 2026
Withdrawal Update Form 3File: Signed Form 3 - Q4 - FY 2025-26.pdf8 Jun 2026
Withdrawal Update Form 3File: Signed Form 3 - Q4 - FY 2025-26.pdf8 Jun 2026
Form 2A (FY 2025-2026)File: Signed Form 2A - FY 2025-26.PDF8 Jun 2026
Withdrawal Update Form 1File: form 1 final.pdf27 Jan 2026
Withdrawal Update Form 2File: Form 2 Q3.pdf27 Jan 2026
Withdrawal Update Form 3File: Form 3 - Q3_0001 (1).pdf27 Jan 2026
Withdrawal Update Form 1File: FORM 1.pdf24 Jan 2026
Withdrawal Update Form 1File: FORM 1 FINAL.pdf24 Jan 2026
Withdrawal Update Form 2File: Form 2 - Q1.pdf24 Jan 2026
Withdrawal Update Form 2File: Form 2 - Q2_0001.pdf24 Jan 2026
Withdrawal Update Form 3File: Form -3 Q-1.pdf24 Jan 2026
Withdrawal Update Form 3File: Form-3 Q-2 (1).pdf24 Jan 2026
Certificates of CA (Form 3)File: Form-3 - Final (1).pdf14 Apr 2025
Disclosure of sold/ booked inventoryFile: Disclosure of inventory - Final (1).pdf14 Apr 2025
Declaration in FORM BFile: Form B.pdf12 Apr 2025
Disclosure of sold/ booked inventoryFile: Disclouser of Sold booked inventory.pdf12 Apr 2025
Disclosure of sold/ booked inventoryFile: Wing A.pdf10 Mar 2025
Disclosure of sold/ booked inventoryFile: Wing B.pdf10 Mar 2025
Disclosure of sold/ booked inventoryFile: Wing C.pdf10 Mar 2025
Disclosure of sold/ booked inventoryFile: Wing D.pdf10 Mar 2025
CERSAI detailsFile: CERSAI Declaration.pdf10 Mar 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: AD - Disclosure of Interest.pdf10 Mar 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: DS - Disclosure of Interest.pdf10 Mar 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: SS - Disclosure of Interest - Original.pdf10 Mar 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A.pdf26 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1-B Wing.pdf19 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: D wing Form 1.pdf19 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: C Wing Form 1.pdf19 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: A Wing Form 1.pdf19 Feb 2025
Certificates of CA (Form 3)File: Form 3.pdf19 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf19 Feb 2025
Commencement Certificates / NA Order for plotted developmentFile: FCC 19112024.pdf17 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 2223.pdf7 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 2324.pdf7 Jan 2025
Certificates of CA (Form 3)File: Form 3.pdf30 Dec 2024
Certificates of CA (Form 3)File: Form 3.pdf30 Dec 2024
Certificates of CA (Form 3)File: Form 3.pdf30 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: RERA Certificate form -5.pdf27 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: D Wing Sale Bldg.pdf26 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: C Wing Sale Bldg.pdf26 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: B Wing Sale Bldg.pdf26 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: A Wing Sale Bldg.pdf26 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Rehab Bldg Phase II.pdf26 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Rehab Bldg Phase I.pdf26 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: C and D Wing Sale Bldg.pdf26 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: B Wing Sale Bldg.pdf26 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Rehab Bldg Phase II.pdf26 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Rehab Bldg Phase I.pdf26 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: C and D Wing Sale Bldg.pdf26 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: B Wing Sale Bld.pdf26 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: A Wing.pdf26 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: A Wing Sale Bldg.pdf26 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf26 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 30062024.pdf26 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 30092024.pdf26 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: C D Wing Sale Bldg.pdf25 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: A Wing Sale Bldg.pdf25 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: B Wing Sale Bldg.pdf25 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Sai Aastha Form -2-1-4.pdf25 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Sai Aastha Form -2-1-4.pdf25 Jan 2024
Certificates of CA (Form 3)File: sai astha form 3.pdf25 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 A WING_0001.pdf6 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 B WING_0001.pdf6 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 SALE_0001.pdf6 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2_0001.pdf6 Dec 2023
Certificates of CA (Form 3)File: Sai Ashtha Form 3 (1).pdf6 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: A Wing Sale Bldg.pdf22 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: B Wing Sale Bldg.pdf22 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: C D Wing Sale Bldg.pdf22 Aug 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf22 Aug 2023
Certificates of CA (Form 3)File: SAI AASTHA DEVELOPERS -FORM 3 (1).pdf22 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Rehab 30 Nov 2022.pdf22 Feb 2023

How this compares with Mumbai Suburban

58%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 30 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ENSO SANZA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Hanuman Nagar6,700+ in Mumbai Suburban

2 kmENSO SANZACompleted 61Lapsed / revoked 42Other 77Dot size: filed unitsN

Filed coordinates, straight-line distance. 180 registered projects within 2 km.

Builder: Sai Aastha Developers

Sai Aastha Developers has 1 registration on MahaRERA, including ENSO SANZA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that ENSO SANZA shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if ENSO SANZA is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ENSO SANZA?

The registered promoter entity is Sai Aastha Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ENSO SANZA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against ENSO SANZA?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for ENSO SANZA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ENSO SANZA?

The professionals named in the filing: Architect: CREATIVE CONSULTANCY; Engineer: M.S SHAIKH; Chartered Accountant: KANU DOSHI ASSOCIATES LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ENSO SANZA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ENSO SANZA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ENSO SANZA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.