Home / Browse projects / Thane, Maharashtra / SIDDHI VINAYAK RESIDENCY
SIDDHI VINAYAK RESIDENCY
RG-MH-96041 · RERA P51700017031 · Last updated on MahaRERA portal: 29 Jun 2018
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 40 months past the filed date
- 10 complaints at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SIDDHI VINAYAK RESIDENCY is a Residential / Group Housing project by RAINBOW DEVELOPERS in Thane, Maharashtra, registered with MahaRERA as P51700017031 on 4 Jul 2018. Possession was promised by 30 Jun 2023 and is now 40 months past that date. 10 complaints are on record with the regulator.
At a glance
Project
- NameSIDDHI VINAYAK RESIDENCY
- TypeResidential / Group Housing
- Location
- BHIWANDI OVALI ROAD
- NEXT TO DIVA VASAI RAILWAY LINE
- Bhiwandi (M Corp.)
- Bhiwandi
- Thane
- 421305
- Pincode421305
- RERA no.P51700017031
- ReraGenie IDRG-MH-96041
Builder
- NameRAINBOW DEVELOPERS
- Entity typePartnership
- PartnersSOHANLAL BIHARILAL GUPTA, KAMLESH RAMSAHAY GUPTA
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on4 Jul 2018
- Promised completion30 Jun 2023
- Revised completionNone
- Buildings2 building records
- Documents filed19 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| BUILDING A | NA | 12 | 0 | 0 | 0 | 0 |
| BUILDING C | NA | 9 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 29 Jun 2018, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
6 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 90%.
BUILDING A45%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 80% |
| Slabs of Super Structure | 27% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUILDING C28%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 13% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 29 Jun 2018, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed45
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| BUILDING A | 1 | 23 | 24 |
| BUILDING C | 1 | 20 | 21 |
Land and ownership2
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| SUBHASH SAKARAM CHOUDHARY | Bhiwandi (M Corp.) | Thane |
| SANTOSH CHAUDHARI | Bhiwandi (M Corp.) | Thane |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | FOUZI & ASSOCIATES |
| Engineer | FOUZI & ASSOCIATES |
| Partner | Role in project |
|---|---|
| RAINBOW DEVELOPERS | - |
Complaints filed with MahaRERA10
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000303136 | RehanAnsari | Rainbow Developers | 21/10/2022 |
| CC006000000591575 | Rehan Ansari | Rainbow Developers | 16/08/2024 |
| CC006000000591577 | Rehan Ansari | Rainbow Developers | 16/08/2024 |
| CC006000000591578 | Rehan Ansari | Rainbow Developers | 16/08/2024 |
| CC006000000591579 | Rehan Ansari | Rainbow Developers | 16/08/2024 |
| CC006000000591580 | Rehan Ansari | Rainbow Developers | 16/08/2024 |
| CC006000000396781 | kanchan suraj khanna | M/s. Rainbow Developers | 30/07/2023 |
| CC12504071 | VISHAL RAJESH WAGHMARE | RAINBOW DEVELOPERS | 19/11/2025 |
| CC12504213 | SHRINIVAS CHANDRAYA KAMTAM | shrinivas chandraya kamtam | 28/11/2025 |
| CC12504216 | vilas viththal jadhav | VILAS VITHTHAL JADHAV | 28/11/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 25 Jun 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 25 Jun 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 25 Jun 2018 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 22 Jun 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed19
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Declaration in FORM BFile: Ramesh Gupta Form B.pdf | 29 Jun 2018 |
| Certificates of CA (Form 3)File: CA Certificate_0002.pdf | 29 Jun 2018 |
| Layout approvalFile: 10 Copy of Layout Approval.pdf | 25 Jun 2018 |
| Building plan approvalFile: Building A Part 1.pdf | 25 Jun 2018 |
| Building plan approvalFile: Building A Part 2.pdf | 25 Jun 2018 |
| Building plan approvalFile: Building C Part 1.pdf | 25 Jun 2018 |
| Building plan approvalFile: Building C Part 2.pdf | 25 Jun 2018 |
| Copy of the legal title reportFile: 9 Legal Title Report.pdf | 25 Jun 2018 |
| Details of encumbrancesFile: 8 No Encumbrence Certificate.pdf | 25 Jun 2018 |
| Copy of Layout Approval (in case of layout)File: 10 Copy of Layout Approval.pdf | 25 Jun 2018 |
| Building Plan Approval (IOD)File: Building A Part 1.pdf | 25 Jun 2018 |
| Building Plan Approval (IOD)File: Building A Part 2.pdf | 25 Jun 2018 |
| Building Plan Approval (IOD)File: Building C Part 1.pdf | 25 Jun 2018 |
| Building Plan Approval (IOD)File: Building C Part 2.pdf | 25 Jun 2018 |
| PAN CardFile: PAN Card.pdf | 22 Jun 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: 6 Construction Permission-ilovepdf-compressed.pdf | 22 Jun 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 4 Architect Certificate.pdf | 22 Jun 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 7 Engineer Certificate.pdf | 22 Jun 2018 |
| Proforma of Allotment letterFile: Proforma Agreement for Sale.pdf | 22 Jun 2018 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- All 19 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep SIDDHI VINAYAK RESIDENCY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near NEXT TO DIVA VASAI RAILWAY LINE7,600+ in Thane
SHIV SAI AWAS
VIDISHA CONSTRUCTIONS
STAR HOMES
BHIWANDI DEVELOPERS
SHAMBHU SHANKAR RESIDENCY
VIDISHA CONSTRUCTIONS
SKY CITY
SUNRISE REALTORS
SHIVAM RESIDENCY PHASE II
SHIVAM DEVELOPERS
ONE SILVER AVENUE
SHIV SAMYAK BUILDERS & DEVELOPERS LLP
See every Thane project, with the district possession charts
Builder: RAINBOW DEVELOPERS
RAINBOW DEVELOPERS has 1 registration on MahaRERA, including SIDDHI VINAYAK RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What does it mean that SIDDHI VINAYAK RESIDENCY shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if SIDDHI VINAYAK RESIDENCY is delayed beyond 30 Jun 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SIDDHI VINAYAK RESIDENCY?
The registered promoter entity is RAINBOW DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SIDDHI VINAYAK RESIDENCY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against SIDDHI VINAYAK RESIDENCY?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for SIDDHI VINAYAK RESIDENCY?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SIDDHI VINAYAK RESIDENCY?
The professionals named in the filing: Architect: FOUZI & ASSOCIATES; Engineer: FOUZI & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SIDDHI VINAYAK RESIDENCY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback