Home / Browse projects / Pune, Maharashtra / Shubharambh Clara
Shubharambh Clara
RG-MH-05743 · RERA P52100076634 · Last updated on MahaRERA portal: 28 May 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
Nothing adverse is on this record. The buyer report still reads the filed documents themselves.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Shubharambh Clara is a Residential / Group Housing project by Shubharambh Landmarks in Pune, Maharashtra, registered with MahaRERA as P52100076634 on 18 Jun 2024. Possession is promised by 31 Dec 2028. 129 of the 129 units on this registration are recorded sold or booked, and 1 of 22 construction stages are filed complete.
At a glance
Project
- NameShubharambh Clara
- TypeResidential / Group Housing
- Location
- Near Chandrabhaga Corner
- Ravet
- Haveli
- Pune
- 412101
- Pincode412101
- RERA no.P52100076634
- ReraGenie IDRG-MH-05743
Builder
- NameShubharambh Landmarks
- Entity typePartnership
- GSTIN27AEXFS0408P1Z8
- PartnersSagar Vijay Gawade, Pramod Pandurang Bhondave, Satish Bhaskar Bhoir, Kundan Ramchandra Jachak, TEERAVISTA PROPERTIES LLP THROUGH PARTNER VIJAY SUBHASH PARANDE, Siddhant Ganesh Bhondve
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on18 Jun 2024
- Promised completion31 Dec 2028
- Revised completionNone
- Buildings2 building records
- Documents filed75 files
Current status
Figures as on 28 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Wing A | NA | 28 | 27 | 129 | 0 | 129 |
| Mhada Wing | NA | 8 | 7 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 28 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
1 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Basement (if any), at 60%.
Wing A20%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 60% |
| Podiums (if any) | 0% |
| Plinth | 60% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Mhada Wing0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 28 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed222
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| Wing A | 143 | 59 | 202 |
| Mhada Wing | 8 | 12 | 20 |
Land and ownership14
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Bhondve Ganesh Tukaram | Ravet | Pune |
| Bhondve Vrunda Ganesh | Ravet | Pune |
| Bhondve Siddhant Ganesh | Ravet | Pune |
| Bhondve Swapnil Pandurang | Ravet | Pune |
| Bhondave Pramod Pandurang | Ravet | Pune |
| Bhondve Pandurang Tukaram | Ravet | Pune |
| Bhondve Shivaji Tukaram | Ravet | Pune |
| Bhondave Aryan Shivaji | Ravet | Pune |
| Jayashree Pandurang Bhondave | Ravet | Pune |
| Bharti Kundan Jachak | Pimpale Saudagar | Pune |
| Sunita Balasaheb Datir | Chinchwad | Pune |
| Dhanashree Abhijit Pawar | Pimple Nilakh | Pune |
| Ujwala Shivaji Bhondve | Ravet | Pune |
| Mayuri Shivaji Bhondave | Ravet | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Kimaya Associates |
| Engineer | Nilesh Prabhakar Kolhe |
| Chartered Accountant | SCT and Company |
| Chartered Accountant | Ekta Anil Mulchandani |
| Partner | Role in project |
|---|---|
| Shubharambh Landmarks | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 27 May 2024 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 7 May 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 7 May 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 7 May 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2028
Documents filed75
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2025-2026)File: FORM 2A-FY 25-26_Quality Assurance Certificate-25-05-2026.pdf | 28 May 2026 |
| Form 1File: 1 Form 1 Architect Certificate.pdf | 25 Apr 2026 |
| Form 2File: 2 FORM 2 Enginner certificate.pdf | 25 Apr 2026 |
| Form 3File: 3 Form 3_11zon.pdf | 25 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: 4 Disclosure sold unsold inventory.pdf | 25 Apr 2026 |
| Form 1File: Architect Certificate Form 1.pdf | 6 Feb 2026 |
| Form 2File: Engineer Certificate Form 2.pdf | 6 Feb 2026 |
| Form 3File: CA Certificate Form 3.pdf | 6 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory.pdf | 6 Feb 2026 |
| Form 1File: Form 1-Q2.pdf | 3 Dec 2025 |
| Form 2File: Form 2-Engineer Certificate.pdf | 3 Dec 2025 |
| Form 3File: CA Certificate Form 3-Signed.pdf | 3 Dec 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold-Unsold Inventory.pdf | 3 Dec 2025 |
| Form 2A (FY 2024-2025)File: Form 2A.pdf | 3 Dec 2025 |
| Form 5 (FY 2024-2025)File: Form-5_Mar 25.pdf | 1 Oct 2025 |
| Form 1File: Architect Certificate From 1 Dt8-7-25_250711_111958.pdf | 22 Sep 2025 |
| Form 2File: Engineers Certificate Dt10-07-25.pdf | 22 Sep 2025 |
| Form 3File: Form 3_compressed.pdf | 22 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold unsold Inventory_Compressed.pdf | 22 Sep 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form -3 CA Certificate_upload_compressed.pdf | 10 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 25 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf | 25 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2.pdf | 25 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 25 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf | 25 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2.pdf | 25 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed_Form 3-CA Certificate.pdf | 9 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed_Form 3-CA Certificate.pdf | 9 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architects Certificate_Jul24 to sep 24.pdf | 6 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Dt 28-11-24.pdf | 6 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architects Certificate_Jul24 to sep 24.pdf | 6 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Dt 28-11-24.pdf | 6 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SLandmarks Form 3 Q12425_11zon.pdf | 23 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SLandmarks Form 3 Q12425_11zon.pdf | 23 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1-Q1-SLM-2425.pdf | 13 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2-Q1-SLM-2425.pdf | 13 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3-Final Upload_11zon.pdf | 10 Jun 2024 |
| Other - TechnicalFile: Decln-Order50-Upload.pdf | 1 Jun 2024 |
| Copy of the legal title reportFile: 1STR Revised.pdf | 27 May 2024 |
| Details of encumbrances concerned to FinanceFile: 1 a Details of encumbrances concerned to Finance.pdf | 27 May 2024 |
| Details of encumbrances concerned to FinanceFile: 1 b Details of encumbrances concerned to Legal.pdf | 27 May 2024 |
| Details of encumbrances concerned to LegalFile: 1 a Details of encumbrances concerned to Finance.pdf | 27 May 2024 |
| Details of encumbrances concerned to LegalFile: 1 b Details of encumbrances concerned to Legal.pdf | 27 May 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Decln-Satish Bhoir.pdf | 27 May 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Decln-Kundan Jachak.pdf | 27 May 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BankDecln-Revised.pdf | 27 May 2024 |
| Other - LegalFile: Decln-Order50.pdf | 27 May 2024 |
| Other - TechnicalFile: CCVerification-PCMC.pdf | 27 May 2024 |
| Details of encumbrances concerned to FinanceFile: Encumbrance Finance and Legal.pdf | 17 May 2024 |
| Details of encumbrances concerned to LegalFile: Encumbrance Finance and Legal.pdf | 17 May 2024 |
| CERSAI detailsFile: Encumbrance Certificate - Finance 2.pdf | 17 May 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest annexur A Teeravista properties LLP.pdf | 17 May 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest Annexure A (1).pdf | 17 May 2024 |
| Layout approvalFile: Plan1.pdf | 7 May 2024 |
| Layout approvalFile: Plan2.pdf | 7 May 2024 |
| Layout approvalFile: Plan3.pdf | 7 May 2024 |
| Layout approvalFile: Plan4.pdf | 7 May 2024 |
| Layout approvalFile: Plan5.pdf | 7 May 2024 |
| Building plan approvalFile: Plan6.pdf | 7 May 2024 |
| PAN CardFile: PANCard-Shubharambh.pdf | 7 May 2024 |
| Copy of Layout Approval (in case of layout)File: Plan1.pdf | 7 May 2024 |
| Copy of Layout Approval (in case of layout)File: Plan2.pdf | 7 May 2024 |
| Copy of Layout Approval (in case of layout)File: Plan3.pdf | 7 May 2024 |
| Copy of Layout Approval (in case of layout)File: Plan4.pdf | 7 May 2024 |
| Copy of Layout Approval (in case of layout)File: Plan5.pdf | 7 May 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan6.pdf | 7 May 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: CommencementCertificate-SNO76.pdf | 7 May 2024 |
| Declaration about Commencement CertificateFile: Declaration-Commencement.pdf | 7 May 2024 |
| Declaration in FORM BFile: Form B Shubharambh landmarks.pdf | 7 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architects Certificate_New Format.pdf | 7 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2-Engineer-Regn.pdf | 7 May 2024 |
| Proforma of Agreement for saleFile: Agreement To Sale-RERA draft.pdf | 7 May 2024 |
| Proforma of Allotment letterFile: ANNEXURE 1 MODAL FROM OF ALLOTMENT LETTER_1_11zon.pdf | 7 May 2024 |
| Deviation Report with respect to Allotment letterFile: Deviation-Allotment.pdf | 7 May 2024 |
| Deviation Report with respect to model copy of AgreementFile: Deviation-Aggreement.pdf | 7 May 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- All 75 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Shubharambh Clara on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Ravet13,700+ in Pune
Godrej Park Greens
Godrej Skyline Developers Limited
FOREST GROVE AT GODREJ PARK GREENS
Godrej Skyline Developers Limited
Om Mangalam Samruddhi
NDG Homes LLP
PCMC EWS KIWALE
Pimpri Chinchwad Municipal Corporation
Godrej Nurture
Godrej Skyline Developers Limited
My Home Sanctuary Phase I
MAMURDI DEVELOPERS LLP
Builder: Shubharambh Landmarks
Shubharambh Landmarks has 1 registration on MahaRERA, including Shubharambh Clara. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Shubharambh Clara is delayed beyond 31 Dec 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Shubharambh Clara?
The registered promoter entity is Shubharambh Landmarks, a partnership as per the filing. Its GSTIN 27AEXFS0408P1Z8 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Shubharambh Clara?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Shubharambh Clara?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Shubharambh Clara?
The professionals named in the filing: Architect: Kimaya Associates; Engineer: Nilesh Prabhakar Kolhe; Chartered Accountant: SCT and Company; Chartered Accountant: Ekta Anil Mulchandani. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Shubharambh Clara?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback