Home / Browse projects / SHUBHANKAR DURVAA PHASE II A

Registered Litigation declared Residential / Group Housing project

SHUBHANKAR DURVAA PHASE II A

By Atul Dnyaneshwar Bahirat

RG-MH-27563 · RERA P52100033886 · Last updated on MahaRERA portal: 20 Jul 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 4 cases
  • 1 complaint at MahaRERA
  • Completion date moved by 6 months
  • 1 extension taken

Clear

  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
Dec 2026Possession promisedmoved 6 months from the original
2 of 11Construction stages donefurthest along: Slabs of Super Structure, 80%
40 of 84Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 60 documents Report an error

SHUBHANKAR DURVAA PHASE II A is a Residential / Group Housing project by Atul Dnyaneshwar Bahirat in DHANORI, 411015, registered with MahaRERA as P52100033886 on 14 Mar 2022. Possession is promised by 31 Dec 2026. The completion date has moved by 6 months from the original filing. 44 of the 84 units on this registration are recorded sold or booked, and 2 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameSHUBHANKAR DURVAA PHASE II A
  • TypeResidential / Group Housing
  • Location
    • TINGARE NAGAR - DHANORI ROAD
    • DHANORI
    • 411015
  • Pincode411015
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100033886
  • ReraGenie IDRG-MH-27563

Builder

  • NameAtul Dnyaneshwar Bahirat
  • Entity typeIndividual
  • GSTIN27AIVPB2327G1ZA
  • Other registrations1 more →
  • Completed1 of 2
  • Declared earlier projects2 →

Key dates

this monthRegisteredMar 2022First promiseJun 2026Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on14 Mar 2022
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Jun 2026)
  • Buildings1 building record
  • Documents filed60 files

Current status

52%44 of 84 units booked
13.6%Work done, per cost certificate

Figures as on 20 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ANA141484084

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 80%.

A: 30% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 20 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed68

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots68
Closed/Covered66
Open Space2

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area5,400 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on12 Feb 2026

Approvals and building plan

Sanctioning authorityATUL DNYANESHWAR BAHIRAT
Permissible FSI16850.0
Proposed, not sanctioned15,600 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGOKALE NAGAR MODEL COLONY SHIVAJINAGAR PUNE
Estimated costRs 25.22 cr
Cost incurredRs 3.44 cr
Work done13.63%
BuildingWingEstimatedIncurred
ANARs 24.22 crRs 3.44 cr
-NARs 1.01 cr-

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAamitesh Architect & Interior Designer
EngineerSK Consultants & Engineers
Chartered AccountantNB Sayed & Associates
Chartered AccountantRutuja Narsingh & Associates
PartnerRole in project
Atul Dnyaneshwar Bahirat-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA04032620089Jun 2026 → Dec 2026

Reason as filed by the promoterWe, Mr. Atul Dnyaneshwar Bahirat, the promoter of the project “SHUBHANKAR DURVAA PHASE II A” (Registration No. P52100033886) under MahaRERA hereby submit our request for an extension of time for completion of the project with 51%consent.The construction work of the project is substantially progressed, and major structural work has been completed However the project faced a delay of approximately 8 months due to pending approval of revised plans from Pune Municipal Corporation arising from ambiguity regarding the applicability of Environmental Clearance NOC. The revised sanction was ultimately

Litigation declared4

CaseCourtStatus
1148/2014CJJDSETTLED
144/2015CJJDSETTLED
1875/2017CJSDPENDING
1519/2017CJJDSETTLED

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC005000000116951Juber Mushtaque AhmedAtul Dnyaneshwar Bahirat17/04/2022

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 Mar 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 12 Feb 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 12 Feb 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Feb 2026Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed60

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 - Shubhankar Durvaa Phase II A as on June 2026.pdf20 Jul 2026
Withdrawal Update Form 2File: Form 2 - Shubhankar Durvaa Phase II A as on June 2026.pdf20 Jul 2026
Withdrawal Update Form 3File: Form 3 - Shubhankar Durvaa Phase II A as on June 2026.pdf20 Jul 2026
Form 5 (FY 2024-2025)File: Form 5 - SHUBHANKAR DURVAA PHASE II A for FY 24-25.pdf9 Jun 2026
Withdrawal Update Form 1File: Form 1 - SHUBHANKAR DURVAA PHASE II A as on March 2026.pdf4 May 2026
Withdrawal Update Form 2File: Form 2 Shubhankar Durvaa Phase II A as on 31-03-2026.pdf4 May 2026
Withdrawal Update Form 3File: Form 3 Shubhankar Durvaa Phase II A as on 31-03-2026.pdf4 May 2026
Commencement certificateFile: CC-1157-24-31-07-2024.pdf12 Feb 2026
Layout approvalFile: 1-1.pdf12 Feb 2026
Building plan approvalFile: 1-4.pdf12 Feb 2026
Building plan approvalFile: 2-4.pdf12 Feb 2026
Building plan approvalFile: 3-4.pdf12 Feb 2026
Building plan approvalFile: 4-4.pdf12 Feb 2026
Withdrawal Update Form 1File: Form 1 - Shubhankar Durvaa Phase II A as on Dec 2025.pdf12 Feb 2026
Withdrawal Update Form 2File: Form 2 - Shubhankar Durvaa Phase II A as on Dec 2025.pdf12 Feb 2026
Withdrawal Update Form 3File: Form 3 - Shubhankar Durvaa Phase II A as on Dec 2025.pdf12 Feb 2026
Form 1File: Form 1 - SHUBHANKAR DURVAA PHASE II A as on June 2025.pdf3 Jan 2026
Form 2File: Form 2 - Shubhankar Durvaa Phase II A as on June 2025.pdf3 Jan 2026
Form 3File: Form 3 Shubhankar Durvaa Phase II A as on 30-06-2025.pdf3 Jan 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 - Shubhankar Durvaa Phase II A as on Sept 2025.pdf3 Jan 2026
Form 1File: Form 1 - SHUBHANKAR DURVAA PHASE II A as on Sep 2025.pdf16 Oct 2025
Form 2File: Form 2 - Shubhankar Durvaa Phase II A as on Sept 2025.pdf16 Oct 2025
Form 3File: Form 3 Shubhankar Durvaa Phase II A as on 30-09-2025.pdf16 Oct 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 - Shubhankar Durvaa Phase II A as on Sept 2025.pdf16 Oct 2025
Form 2A (FY 2024-2025)File: Engineers Certificate.pdf9 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2 ND SLAB.pdf24 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate.pdf14 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate (2).pdf14 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE.pdf7 Aug 2024
Other - TechnicalFile: Self - Declaration.pdf7 Aug 2024
Building plan approvalFile: 2-4.pdf5 Aug 2024
Building Plan Approval / NA Order for plotted developmentFile: 2-4.pdf5 Aug 2024
Layout approvalFile: layout.pdf3 Aug 2024
Copy of Layout Approval (in case of layout)File: layout.pdf3 Aug 2024
Commencement Certificates / NA Order for plotted developmentFile: LAYOUT CC.pdf3 Aug 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure - A.pdf1 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: QA-APRIL-24.pdf8 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: ENG CERTFCT.pdf10 Apr 2024
OtherFile: Declaration.pdf11 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality Assurance - Annexure -C.pdf22 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: BUILDING-A-FINAL QAC- 2022.pdf8 Jul 2022
Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf11 Mar 2022
Proforma of Allotment letterFile: Agreement for A building.pdf11 Mar 2022
OtherFile: dhondabai DA.pdf11 Mar 2022
OtherFile: HAZARE DA.pdf11 Mar 2022
OtherFile: Vimal Tingare DA.pdf11 Mar 2022
Copy of the legal title reportFile: LEGAL TITLE REPORT.pdf10 Mar 2022
Layout approvalFile: LAYOUT.pdf28 Feb 2022
Building plan approvalFile: PLAN COMP.pdf28 Feb 2022
PAN CardFile: pan.pdf28 Feb 2022
Details of encumbrancesFile: self declaration.pdf28 Feb 2022
Copy of Layout Approval (in case of layout)File: LAYOUT.pdf28 Feb 2022
Building Plan Approval / NA Order for plotted developmentFile: PLAN COMP.pdf28 Feb 2022
Commencement Certificates / NA Order for plotted developmentFile: CC_A.pdf28 Feb 2022
Declaration about Commencement CertificateFile: self declaration for cc.pdf28 Feb 2022
Declaration in FORM BFile: Form -B.pdf28 Feb 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate.pdf28 Feb 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineer certificate.pdf28 Feb 2022
CERSAI detailsFile: self declaration.pdf28 Feb 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate.pdf28 Feb 2022

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Shubhankar Durvaa Phase 2P52100005238Dhanori65Aug 2017CompletedJun 2022Registered original: Jun 2021Jan 2022

Keep SHUBHANKAR DURVAA PHASE II A on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near DHANORI

2 kmSHUBHANKAR DURVAA PHASE Completed 38Lapsed / revoked 19Other 18Dot size: filed unitsN

Filed coordinates, straight-line distance. 75 registered projects within 2 km.

Builder: Atul Dnyaneshwar Bahirat

Atul Dnyaneshwar Bahirat has 2 registrations on MahaRERA, including Shubhankar Durvaa Phase 2 and SHUBHANKAR DURVAA PHASE II A. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record.

Frequently asked questions

What are my rights if SHUBHANKAR DURVAA PHASE II A is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHUBHANKAR DURVAA PHASE II A?

The registered promoter entity is Atul Dnyaneshwar Bahirat, an individual as per the filing. Its GSTIN 27AIVPB2327G1ZA can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHUBHANKAR DURVAA PHASE II A?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SHUBHANKAR DURVAA PHASE II A?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SHUBHANKAR DURVAA PHASE II A?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHUBHANKAR DURVAA PHASE II A?

The professionals named in the filing: Architect: Aamitesh Architect & Interior Designer; Engineer: SK Consultants & Engineers; Chartered Accountant: NB Sayed & Associates; Chartered Accountant: Rutuja Narsingh & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHUBHANKAR DURVAA PHASE II A?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHUBHANKAR DURVAA PHASE II A. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHUBHANKAR DURVAA PHASE II A to a free account