ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / NYATI ERA I

Completed Litigation declared Residential / Group Housing project

NYATI ERA I

By NYATI CONSTRUCTION PRIVATE LIMITED

RG-MH-23074 · RERA P52100032682 · Last updated on MahaRERA portal: 19 Dec 2025

Source: official MahaRERA filing

Red flags

  • Litigation declared, 4 cases
  • 3 complaints at MahaRERA
  • Completion date moved by 2 months
  • 1 extension taken

Clear

  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Aug 2025Possession promisedregistration recorded completed
31 of 77Construction stages doneacross 7 buildings; furthest along: Slabs of Super Structure, 99%
1 of 364Units unsoldnot recorded sold or booked
3Complaints at MahaRERAon this registration
Jump to the 120 documents Report an error

NYATI ERA I is a Residential / Group Housing project by NYATI CONSTRUCTION PRIVATE LIMITED in Pune, Maharashtra, registered with MahaRERA as P52100032682 on 24 Jan 2022. The registration is recorded completed; possession was promised by 8 Aug 2025. The completion date has moved by 2 months from the original filing. 363 of the 364 units on this registration are recorded sold or booked, and 31 of 77 construction stages are filed complete. 3 complaints are on record with the regulator.

At a glance

Project

  • NameNYATI ERA I
  • TypeResidential / Group Housing
  • Location
    • DHANORI LOHEGAON ROAD
    • DHANORI
    • Haveli
    • Pune
    • 411015
  • Pincode411015
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100032682
  • ReraGenie IDRG-MH-23074

Builder

  • NameNYATI CONSTRUCTION PRIVATE LIMITED
  • Entity typeCompany
  • CINU45202MH1996PTC102517
  • GSTIN27AAACN6421D1ZU
  • CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
  • DirectorsPRANAV NITIN NYATI, NITIN DWARKADAS NYATI
  • Other registrations5 more →
  • Completed2 of 6

Key dates

this monthRegisteredJan 2022First promiseJun 2025Revised toAug 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on24 Jan 2022
  • Promised completion8 Aug 2025
  • Revised completionRevised to 8 Aug 2025 (originally 30 Jun 2025)
  • Buildings7 building records
  • Documents filed120 files

Current status

100%363 of 364 units booked
94.0%Work done, per cost certificate

Figures as on 19 Dec 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING-ANA151352052
WING-BNA151352052
WING-CNA151352052
WING-GNA151352052
WING-HNA151352052
WING-INA151352052
WING-RNA151352052

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building7

As on 19 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

31 of 77 construction stages are filed complete across 7 buildings. The stage furthest along is Slabs of Super Structure, at 99%.

WING-A81%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises86%
Sanitary Fittings within the flats / premises65%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks96%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.79%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.68%
WING-B81%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises84%
Sanitary Fittings within the flats / premises64%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks94%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.68%
WING-C81%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises82%
Sanitary Fittings within the flats / premises64%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks93%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.81%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.68%
WING-G76%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure98%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises79%
Sanitary Fittings within the flats / premises41%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks92%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.65%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.66%
WING-H76%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises74%
Sanitary Fittings within the flats / premises41%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks91%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.64%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.66%
WING-I75%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure98%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises67%
Sanitary Fittings within the flats / premises43%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks74%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.66%
WING-R79%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure99%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises81%
Sanitary Fittings within the flats / premises51%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks92%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.78%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.67%

Progress on shared amenities15

As on 19 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes80%
Storm Water DrainsYes10%
Landscaping & Tree PlantingYes3%
Street LightingYes3%
Community BuildingsYes61%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes13%
Energy managemcntYes75%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes79%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed91

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots91
Closed/Covered91
BuildingClosed/CoveredTotal
WING-A1313
WING-B1313
WING-C1313
WING-G1313
WING-H1313
WING-I1313
WING-R1313

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area9,982 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on27 Jun 2025
LandownerVillageDistrict
COOJI ALIAS COOVERJI DADY KATRAKPune (CB)Pune

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI40786.82
Proposed, not sanctioned40,787 sq m
Buildings approved7
Buildings sanctioned7

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKHARADI PUNE 411014
Estimated costRs 118.10 cr
Cost incurredRs 111.06 cr
Work done94.04%
BuildingWingEstimatedIncurred
-NARs 26.42 crRs 23.37 cr
WING-GNARs 13.44 crRs 12.62 cr
WING-INARs 13.44 crRs 12.90 cr
WING-ANARs 13.44 crRs 12.93 cr
WING-CNARs 13.44 crRs 12.93 cr
WING-HNARs 13.25 crRs 12.60 cr
WING-BNARs 13.24 crRs 12.69 cr
WING-RNARs 11.43 crRs 11.01 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSHIRISH DASNURKAR
ArchitectSANJEEV MUKUND MEHTA
EngineerACHYUT WATVE
EngineerVishwanath Dhande
EngineerSANDEEP HIROLIKAR
Chartered AccountantNICKY HIRANAND MILANI
PartnerRole in project
NYATI CONSTRUCTION PRIVATE LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA27062501822Jun 2025 → Aug 2025

Reason as filed by the promoterWe have received OC on 08/08/2025 and are applying for an Extension till the date of OC

Litigation declared4

CaseCourtStatus
1046/2023CIVIL JUDGE SENIOR DIVISION PUNEOngoing
721/2024CIVIL COURT SENIOR DIVISIONOngoing
608/2020CIVIL COURT SENIOR DIVISIONOngoing
1867/2024CIVIL COURT SENIOR DIVISIONOngoing

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC005000000471362CHARUSHILA DHANKAWADENITIN DWARKADAS NYATI21/07/2024
CC12604746Archana Shivaji BhoiteNYATI CONSTRUCTION PRIVATE LIMITED28/07/2026
CC12604747Archana Shivaji BhoiteNYATI CONSTRUCTION PRIVATE LIMITED28/07/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 7 Oct 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 Mar 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 Jul 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 Mar 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed120

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 120 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2024-2025)File: Nyati Era-I Form 5.pdf19 Dec 2025
Withdrawal Update Form 1File: FORM 1.pdf16 Dec 2025
Withdrawal Update Form 2File: FORM 2.pdf16 Dec 2025
Withdrawal Update Form 3File: Era I FORM 3.pdf16 Dec 2025
Form 2A (FY 2024-2025)File: Nyati Era I Form 2A 2024-2025.pdf16 Dec 2025
Occupational CertificateFile: OC.pdf16 Dec 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf17 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf15 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf15 Apr 2025
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD UNSOLD INVENTORY.pdf4 Apr 2025
Layout approvalFile: Sanction Layout.pdf6 Mar 2025
Copy of Layout Approval (in case of layout)File: Sanction Layout.pdf6 Mar 2025
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf6 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf16 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf7 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf7 Jan 2025
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD UNSOLD INVENTORY.pdf7 Jan 2025
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD UNSOLD INVENTORY.pdf29 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf19 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf18 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf18 Oct 2024
Copy of the legal title reportFile: TITLE CERTIFICATE 03102024.pdf7 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Nyati Era I - Form 5.pdf7 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.PDF17 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf8 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf8 Jul 2024
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD UNSOLD INVENTORY.pdf8 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A.pdf18 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: NCPL Form 3 - Era I_11zon.pdf11 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf8 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf8 Apr 2024
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD UNSOLD INVENTORY.pdf8 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf16 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf16 Jan 2024
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD UNSOLD INVENTORY.pdf16 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf16 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf19 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf16 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf16 Oct 2023
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD UNSOLD INVERTORY.pdf16 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Nyati Era I.pdf30 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf28 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf28 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Era I.pdf27 Jul 2023
Building plan approvalFile: Wing R Floor Plan.pdf20 Jul 2023
Building Plan Approval / NA Order for plotted developmentFile: Wing R Floor Plan.pdf20 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Era I.pdf29 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ERA 1.pdf29 Apr 2023
Layout approvalFile: Sanction Layout.pdf27 Apr 2023
Copy of Layout Approval (in case of layout)File: Sanction Layout.pdf27 Apr 2023
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf27 Apr 2023
Declaration about Commencement CertificateFile: Declaration about CC Era I 17042023.pdf27 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE-ERA I .pdf17 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE.pdf17 Apr 2023
Proforma of Agreement for saleFile: NYATI ERA I UNIT AGREEMENT 020123clean Revised 050423 clean.pdf12 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A.pdf4 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CERTIFICATE.pdf31 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A.pdf25 Jan 2023
Proforma of Agreement for saleFile: Revised Unit Agreement 020123.pdf2 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A.pdf20 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Nyati Era I.pdf30 Sep 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A.pdf29 Jul 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A.pdf5 May 2022
CERSAI detailsFile: CERSAI CERIFICATE.pdf18 Jan 2022
Proforma of Allotment letterFile: LETTER OF ALLOTMENT.pdf17 Jan 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate .pdf6 Jan 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf6 Jan 2022
Proforma of Allotment letterFile: NYATI ERA I UNIT AGREEMENT final 060122.pdf6 Jan 2022
Details of encumbrancesFile: Self Declaration.pdf29 Dec 2021
Declaration about Commencement CertificateFile: FORMAT D DECLARATION ABOUT CC.pdf29 Dec 2021
Declaration in FORM BFile: Form B NCPL New.pdf29 Dec 2021
CERSAI detailsFile: CERSAI UNDERTAKING.pdf29 Dec 2021
Layout approvalFile: Sanction BP Layout.pdf23 Dec 2021
Layout approvalFile: Sanction DP Layout.pdf23 Dec 2021
Layout approvalFile: Parking Layout.pdf23 Dec 2021
Building plan approvalFile: Wing A Elevation.pdf23 Dec 2021
Building plan approvalFile: Wing A Plans.pdf23 Dec 2021
Building plan approvalFile: Wing A Sections.pdf23 Dec 2021
Building plan approvalFile: Wing B Elevation.pdf23 Dec 2021
Building plan approvalFile: Wing B Plans.pdf23 Dec 2021

How this compares with Pune

100%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 2 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep NYATI ERA I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near DHANORI13,700+ in Pune

2 kmNYATI ERA ICompleted 87Lapsed / revoked 26Other 49Dot size: filed unitsN

Filed coordinates, straight-line distance. 162 registered projects within 2 km.

Builder: NYATI CONSTRUCTION PRIVATE LIMITED

NYATI CONSTRUCTION PRIVATE LIMITED has 6 registrations on MahaRERA, including NYATI ERA I and NYATI ERA II. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 5 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if NYATI ERA I is delayed beyond 8 Aug 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of NYATI ERA I?

The registered promoter entity is NYATI CONSTRUCTION PRIVATE LIMITED, a company as per the filing. Its CIN U45202MH1996PTC102517 and GSTIN 27AAACN6421D1ZU can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in NYATI ERA I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against NYATI ERA I?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for NYATI ERA I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at NYATI ERA I?

The professionals named in the filing: Architect: SHIRISH DASNURKAR; Architect: SANJEEV MUKUND MEHTA; Engineer: ACHYUT WATVE; Engineer: Vishwanath Dhande; Engineer: SANDEEP HIROLIKAR; Chartered Accountant: NICKY HIRANAND MILANI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NYATI ERA I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NYATI ERA I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NYATI ERA I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.