Home / Browse projects / Kohinoor Viva Pixel- Phase II

Registered Litigation declared Residential / Group Housing project

Kohinoor Viva Pixel- Phase II

By RISING ASSOCIATES

RG-MH-81986 · RERA P52100054823 · Last updated on MahaRERA portal: 8 Sep 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 2 cases
  • Completion date moved by 4 months
  • 1 extension taken

Clear

  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
Oct 2028Possession promisedmoved 4 months from the original
27 of 77Construction stages doneacross 7 buildings; furthest along: Slabs of Super Structure, 96%
207 of 624Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 160 documents Report an error

Kohinoor Viva Pixel- Phase II is a Residential / Group Housing project by RISING ASSOCIATES in Dhanori, 411015, registered with MahaRERA as P52100054823 on 15 Feb 2024. Possession is promised by 30 Oct 2028. The completion date has moved by 4 months from the original filing. 417 of the 624 units on this registration are recorded sold or booked, and 27 of 77 construction stages are filed complete.

At a glance

Project

  • NameKohinoor Viva Pixel- Phase II
  • TypeResidential / Group Housing
  • Location
    • Dhanori
    • 411015
  • Pincode411015
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100054823
  • ReraGenie IDRG-MH-81986

Builder

  • NameRISING ASSOCIATES
  • Entity typePartnership
  • PartnersVINEET KRISHNAKUMAR GOYAL, RAJESH KRISHNAKUMAR GOYAL
  • Other registrations12 more →
  • Completed8 of 13
  • No longer live3 lapsed, de-registered or revoked

Key dates

this monthRegisteredFeb 2024First promiseJun 2028Revised toOct 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on15 Feb 2024
  • Promised completion30 Oct 2028
  • Revised completionRevised to 30 Oct 2028 (originally 30 Jun 2028)
  • Buildings7 building records
  • Documents filed160 files

Current status

67%417 of 624 units booked
59.4%Work done, per cost certificate

Figures as on 8 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower 3NA171560060
Tower 4NA17151200120
Tower 5NA171560060
Inclusive HousingNA121282082
Tower 1NA131292092
Tower 2NA17151500150
Tower 6NA171560060

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building7

As on 8 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

27 of 77 construction stages are filed complete across 7 buildings. The stage furthest along is Slabs of Super Structure, at 96%.

Tower 363%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises65%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.45%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%
Tower 455%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises56%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Tower 565%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks65%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.65%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%
Inclusive Housing52%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure85%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises27%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks45%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.5%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Tower 147%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure96%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.20%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Tower 244%
ActivityProgress
Excavation100%
Basement (if any)70%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises42%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks49%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.20%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
Tower 659%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure96%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises45%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks55%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.40%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%

Progress on shared amenities15

As on 8 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed473

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots473
Closed/Covered461
Open Space12
BuildingClosed/CoveredOpen SpaceTotal
Tower 31100110
Tower 42520252
Tower 595095
Inclusive Housing11213
Tower 1101
Tower 2101
Tower 6101

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area16,450 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on28 Jun 2025
LandownerVillageDistrict
Rahul Shivajirao KadamKothrudPune

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI68575.87
Proposed, not sanctioned31,715 sq m
Buildings approved7
Buildings sanctioned7

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch421A, Gokhale Road, Near Symbiosis Center, Ashoknagar, Pune-411016
Estimated costRs 186.21 cr
Cost incurredRs 110.60 cr
Work done59.39%
BuildingWingEstimatedIncurred
Tower 2NARs 39.33 crRs 14.21 cr
Tower 4NARs 32.77 crRs 14.21 cr
Tower 1NARs 31.13 crRs 14.21 cr
-NARs 22.35 crRs 11.11 cr
Tower 3NARs 16.39 crRs 14.21 cr
Tower 5NARs 16.39 crRs 14.21 cr
Tower 6NARs 16.39 crRs 14.21 cr
Inclusive HousingNARs 11.47 crRs 14.21 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVK a architecture
EngineerPlanedge Consultants P Limited
Chartered AccountantBHANDARI S A A J & ASSOCIATES
Chartered AccountantVinod Nikam and Co
Chartered AccountantJAYESH N JAIN & ASSOCIATES
PartnerRole in project
RISING ASSOCIATES-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

P52100054823/WarJun 2028 → Oct 2028

Reason as filed by the promoterNA

Litigation declared2

CaseCourtStatus
101/2022Civil Court PunePending
101/2022/2022District and Sessions Court, PuneOngoing

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 9 Jan 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Apr 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Apr 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Apr 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Oct 2028

Documents filed160

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 160 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2025-2026)File: Form 05_Viva Pixel II..pdf8 Sep 2026
Form 2A (FY 2025-2026)File: Form 02A- Viva Pixel II..pdf7 Sep 2026
Withdrawal Update Form 1File: Viva pixel 2.pdf18 Jul 2026
Withdrawal Update Form 2File: Form 02_Viva Pixel II.pdf18 Jul 2026
Withdrawal Update Form 3File: Form 03_Viva Pixel II.pdf18 Jul 2026
Withdrawal Update Form 1File: Form 1 - pixel 2.pdf21 Apr 2026
Withdrawal Update Form 2File: Form 02_Viva Pixel Ph II.pdf21 Apr 2026
Withdrawal Update Form 3File: Form 03_Viva Pixel II.pdf21 Apr 2026
Withdrawal Update Form 1File: FORM 1_VIVA PIXEL II.pdf20 Jan 2026
Withdrawal Update Form 2File: Form 02_Viva Pixel Ph II.pdf20 Jan 2026
Withdrawal Update Form 3File: Form 03_Viva Pixel Ph II.pdf20 Jan 2026
Form 2A (FY 2024-2025)File: Form 2A_Viva Pixel II.pdf29 Nov 2025
Form 5 (FY 2024-2025)File: Form 05_Viva Pixel Ph II.pdf8 Nov 2025
Withdrawal Update Form 1File: FORM 1-VIVA PIXEL II.pdf25 Oct 2025
Withdrawal Update Form 2File: Form 02_Viva Pixel Ph II.pdf25 Oct 2025
Withdrawal Update Form 3File: Form 03_Viva Pixel Ph II.pdf25 Oct 2025
Withdrawal Update Form 1File: Viva Pixel 2.pdf6 Aug 2025
Withdrawal Update Form 2File: Form 02_Viva Pixel II.pdf6 Aug 2025
Withdrawal Update Form 3File: Form 03_Viva Pixel Ph II.pdf6 Aug 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 02_Viva Pixel II.pdf9 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 03_Viva Pixel II.pdf6 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 K VIVA PIXEL PH II.pdf19 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_VIVA PIXEL II.pdf27 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2_VIVA PIXEL II.pdf27 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Viva pixel 2.pdf20 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A_VIVA PIXEL.pdf3 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A_VIVA PIXEL 2.pdf3 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Pixel 2.pdf19 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Pixel 2.pdf19 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Viva pixel 2.pdf15 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - Viva Pixel- Phase II.pdf8 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-01 Q1 FY 24-25 VIVA PIXEL PHASE II.pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-02 Q1 FY 24-25 VIVA PIXEL II.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-03 Q1 FY 24-25 VIVA PIXEL PHASE II.pdf20 Jul 2024
Building plan approvalFile: 4-33_.pdf25 Apr 2024
Building plan approvalFile: 5-33_.pdf25 Apr 2024
Building plan approvalFile: 6-33_.pdf25 Apr 2024
Building plan approvalFile: 7-33_.pdf25 Apr 2024
Building plan approvalFile: 8-33_.pdf25 Apr 2024
Building plan approvalFile: 9-33_.pdf25 Apr 2024
Building plan approvalFile: 10-33_.pdf25 Apr 2024
Building plan approvalFile: 11-33_.pdf25 Apr 2024
Building plan approvalFile: 12-33_.pdf25 Apr 2024
Building plan approvalFile: 13-33_.pdf25 Apr 2024
Building plan approvalFile: 14-33_.pdf25 Apr 2024
Building plan approvalFile: 15-33_.pdf25 Apr 2024
Building plan approvalFile: 16-33_.pdf25 Apr 2024
Building plan approvalFile: 17-33_.pdf25 Apr 2024
Building plan approvalFile: 18-33_.pdf25 Apr 2024
Building plan approvalFile: 19-33_.pdf25 Apr 2024
Building plan approvalFile: 20-33_.pdf25 Apr 2024
Building plan approvalFile: 21-33_.pdf25 Apr 2024
Building plan approvalFile: 22-33_.pdf25 Apr 2024
Building plan approvalFile: 23-33_.pdf25 Apr 2024
Building plan approvalFile: 24-33_.pdf25 Apr 2024
Building plan approvalFile: 25-33_.pdf25 Apr 2024
Building plan approvalFile: 26-33_.pdf25 Apr 2024
Building plan approvalFile: 27-33_.pdf25 Apr 2024
Building plan approvalFile: 28-33_.pdf25 Apr 2024
Building plan approvalFile: 29-33_.pdf25 Apr 2024
Building plan approvalFile: 30-33_.pdf25 Apr 2024
Building plan approvalFile: 31-33_.pdf25 Apr 2024
Building plan approvalFile: 32-33_.pdf25 Apr 2024
Building plan approvalFile: 33-33_.pdf25 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: 4-33_.pdf25 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: 5-33_.pdf25 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: 6-33_.pdf25 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: 7-33_.pdf25 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: 8-33_.pdf25 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: 9-33_.pdf25 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: 10-33_.pdf25 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: 11-33_.pdf25 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: 12-33_.pdf25 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: 13-33_.pdf25 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: 14-33_.pdf25 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: 15-33_.pdf25 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: 16-33_.pdf25 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: 17-33_.pdf25 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: 18-33_.pdf25 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: 19-33_.pdf25 Apr 2024

Keep Kohinoor Viva Pixel- Phase II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Dhanori

2 kmKohinoor Viva Pixel- PhaCompleted 34Lapsed / revoked 8Other 20Dot size: filed unitsN

Filed coordinates, straight-line distance. 62 registered projects within 2 km.

Builder: RISING ASSOCIATES

RISING ASSOCIATES has 13 registrations on MahaRERA, including KOHINOOR JEEVA and KOHINOOR JEEVA C BUILDING. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 2 of its registrations. Read the full track record.

Frequently asked questions

What are my rights if Kohinoor Viva Pixel- Phase II is delayed beyond 30 Oct 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Kohinoor Viva Pixel- Phase II?

The registered promoter entity is RISING ASSOCIATES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Kohinoor Viva Pixel- Phase II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Kohinoor Viva Pixel- Phase II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Kohinoor Viva Pixel- Phase II?

The professionals named in the filing: Architect: VK a architecture; Engineer: Planedge Consultants P Limited; Chartered Accountant: BHANDARI S A A J & ASSOCIATES; Chartered Accountant: Vinod Nikam and Co; Chartered Accountant: JAYESH N JAIN & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Kohinoor Viva Pixel- Phase II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Kohinoor Viva Pixel- Phase II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Kohinoor Viva Pixel- Phase II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.