Home / Browse projects / Mumbai Suburban, Maharashtra / Shubham Trident - Sundew, Sunrise and Sunglow

Registration lapsed No litigation declared Residential / Group Housing project

Shubham Trident - Sundew, Sunrise and Sunglow

By Shubham Homes and Contractors Pvt. Ltd.

RG-MH-70570 · RERA P51800008658 · Last updated on MahaRERA portal: 21 Feb 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 22 months past the filed date
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2024Possession promised22 months past this date
26 of 33Construction stages doneacross 3 buildings; furthest along: Sanitary Fittings within the flats /..., 75%
0Complaints at MahaRERAon this registration
Jump to the 85 documents Report an error

Shubham Trident - Sundew, Sunrise and Sunglow is a Residential / Group Housing project by Shubham Homes and Contractors Pvt. Ltd. in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800008658 on 19 Aug 2017. Possession was promised by 29 Dec 2024 and is now 22 months past that date. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameShubham Trident - Sundew, Sunrise and Sunglow
  • TypeResidential / Group Housing
  • Location
    • Ghatla Road
    • Chembur
    • Kurla
    • Mumbai Suburban
    • 400071
  • Pincode400071
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800008658
  • ReraGenie IDRG-MH-70570

Builder

  • NameShubham Homes and Contractors Pvt. Ltd.
  • Entity typeCompany
  • CINU37200MH2021PTC370156
  • PartnersNimesh Subodh Dalal, Dinesh Vinodchandra Shah

Key dates

22 months past promisethis monthRegisteredAug 2017First promiseDec 2023Revised toDec 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on19 Aug 2017
  • Promised completion29 Dec 2024
  • Revised completionRevised to 29 Dec 2024 (originally 30 Dec 2023)
  • Buildings3 building records
  • Documents filed85 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SundewNA150000
SunriseNA150000
SunglowNA150000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 21 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

26 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 75%.

Sundew89%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises75%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Sunrise89%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises75%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Sunglow84%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises75%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%

Progress on shared amenities17

As on 21 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes95%
Open ParkingNoNot applicable
SOCIETY OFFICEYes100%
GYMNASIUMYes100%

Parking filed77

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots77
Closed/Covered65
Open Space12
BuildingClosed/CoveredOpen SpaceTotal
Sundew22022
Sunrise121224
Sunglow31031

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,652 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityBMC
Permissible FSI4784.84
Proposed, not sanctioned4,645 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAnchorage Building, 170/171, Central Avenue Road, Chembur, Mumbai - 400 071

Certifying professionals and partners

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

PartnerRole in project
Shubham Homes and Contractors Pvt. Ltd.-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800012146Dec 2023 → Dec 2024

Reason as filed by the promoterDate: 30th June, 2022 To, The Chairman, Maharashtra Real Estate Regulatory Authority, 3rd Floor, A-Wing Slum Rehabilitation Authority, Administrative Building, Anant Kanekar Marg, Bandra (E), Mumbai - 400 051. Ref: Extension of possession date of project SHUBHAM TRIDENT - SUNDEW, SUNRISE & SUNGLOW (P51800008658) Respected Sir, The captioned project is registered with MAHARERA under registration number P51800008658 and in the Form B declaration, the date of possession mentioned is 31st December, 2023. We would like to inform you that due to scarcity of availability of resources, the onset of CO

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 21 Feb 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Mar 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 11 Jun 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 21 Feb 2025

Documents filed85

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 85 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Building 10.pdf21 Feb 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Signed Sundew Sunrise.pdf19 Aug 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arc Certificate 2024.pdf7 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: QA Certificate 2024.pdf7 Aug 2024
Commencement Certificates / NA Order for plotted developmentFile: Building No 10 Full CC.pdf11 Jun 2024
Certificates of CA (Form 5)File: Form 5 - 22-23.pdf18 Mar 2024
Commencement Certificates / NA Order for plotted developmentFile: Building No 1 2 Full CC.pdf14 Mar 2024
Layout approvalFile: Building No 1 2 Signed Approved Plans 2024.pdf21 Feb 2024
Copy of Layout Approval (in case of layout)File: Building No 1 2 Signed Approved Plans 2024.pdf21 Feb 2024
Proforma of Agreement for saleFile: RERA Draft Agreement.pdf24 Jan 2024
Proforma of Agreement for saleFile: RERA AGREEMENT SHUBHAM TRIDENT SUNDEW SUNRISE SUNGLOW.pdf3 Jan 2024
Layout approvalFile: Building No 10 - Approved Plans (2023).pdf13 Sep 2023
Copy of Layout Approval (in case of layout)File: Building No 10 - Approved Plans (2023).pdf13 Sep 2023
Commencement Certificates / NA Order for plotted developmentFile: Building No 10 - Latest CC.pdf13 Sep 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 21-22.pdf13 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 20-21.pdf3 Apr 2023
Commencement Certificates / NA Order for plotted developmentFile: Building No 1_2 - Full CC (16092022).pdf16 Sep 2022
Commencement Certificates / NA Order for plotted developmentFile: Building No 10 - Full CC (30082022).pdf16 Sep 2022
Commencement Certificates / NA Order for plotted developmentFile: Building No 10 - Full CC (30082022).pdf31 Aug 2022
Proforma of Allotment letterFile: 13072022 RERA AGREEMENT SHUBHAM TRIDENT.pdf25 Jul 2022
CERSAI detailsFile: Cersai Asset based report.pdf20 Apr 2022
CERSAI detailsFile: CERSAI Report.pdf4 Apr 2022
Certificates of CA (Form 3)File: 2022 Form 3.pdf4 Apr 2022
OtherFile: Buyer Consent.pdf4 Apr 2022
Certificates of CA (Form 3)File: CA Form 3 2022.pdf29 Mar 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Engineer's Quality Assurance.pdf17 Mar 2022
Declaration about Commencement CertificateFile: Declaration for CC.pdf16 Mar 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2022 ENGINEERS CERTIFICATE.pdf16 Mar 2022
CERSAI detailsFile: CERSAI Report.pdf16 Mar 2022
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Inventory.pdf16 Mar 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arc Certificate (2022).pdf14 Mar 2022
PAN CardFile: SHCPL PAN Card.pdf11 Mar 2022
Details of encumbrancesFile: Details of encumbrances.pdf11 Mar 2022
Layout approvalFile: 2021-22-Building No 1_2-Approved Plans Signed 1.pdf10 Mar 2022
Layout approvalFile: 2022-Building No 1_2-Approved Plans Signed 2.pdf10 Mar 2022
Layout approvalFile: Building No 1_2 - Signed Approved Plan Plans (2022) 3.pdf10 Mar 2022
Layout approvalFile: Building No 1_2 - Signed Approved Plan Plans (2022) 4.pdf10 Mar 2022
Layout approvalFile: 2022-Building No 10-Approved Plans Signed 1.pdf10 Mar 2022
Layout approvalFile: 2022-Building No 10-Approved Plans Signed 2.pdf10 Mar 2022
Layout approvalFile: Building No 10 - Signed Approved Plans (2022) 3.pdf10 Mar 2022
Layout approvalFile: Building No 10 - Signed Approved Plans (2022) 3.pdf10 Mar 2022
Building plan approvalFile: 2021-22-Building No 10-IOD Signed.pdf10 Mar 2022
Copy of Layout Approval (in case of layout)File: 2021-22-Building No 1_2-Approved Plans Signed 1.pdf10 Mar 2022
Copy of Layout Approval (in case of layout)File: 2022-Building No 1_2-Approved Plans Signed 2.pdf10 Mar 2022
Copy of Layout Approval (in case of layout)File: Building No 1_2 - Signed Approved Plan Plans (2022) 3.pdf10 Mar 2022
Copy of Layout Approval (in case of layout)File: Building No 1_2 - Signed Approved Plan Plans (2022) 4.pdf10 Mar 2022
Copy of Layout Approval (in case of layout)File: 2022-Building No 10-Approved Plans Signed 1.pdf10 Mar 2022
Copy of Layout Approval (in case of layout)File: 2022-Building No 10-Approved Plans Signed 2.pdf10 Mar 2022
Copy of Layout Approval (in case of layout)File: Building No 10 - Signed Approved Plans (2022) 3.pdf10 Mar 2022
Copy of Layout Approval (in case of layout)File: Building No 10 - Signed Approved Plans (2022) 3.pdf10 Mar 2022
Building Plan Approval (IOD)File: 2021-22-Building No 10-IOD Signed.pdf10 Mar 2022
Commencement Certificates / NA Order for plotted developmentFile: Building No 10 - CC (2022).pdf10 Mar 2022
Commencement Certificates / NA Order for plotted developmentFile: Building No 1_2 - CC (04032022).pdf10 Mar 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: SHUBHAM HOMES 2018-2019.pdf29 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: SHUBHAM HOMES 2019-2020.pdf29 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: SHUBHAM HOMES 2020-21.pdf29 Aug 2021
Certificates of CA (Form 5)File: Shubham Homes.PDF15 Oct 2018
Commencement Certificates / NA Order for plotted developmentFile: SUNDEW - BLDG 1 - CC.pdf25 Oct 2017
Commencement Certificates / NA Order for plotted developmentFile: SUNRISE - BLDG 2 - CC.pdf25 Oct 2017
Commencement Certificates / NA Order for plotted developmentFile: SUNGLOW - BLD 10 - CC.pdf25 Oct 2017
Details of encumbrancesFile: Shubham Homes.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SHUBHAM TRIDENT - ENGINEER CERTIFICATE -4.pdf31 Jul 2017
Certificates of CA (Form 3)File: DC_2503408-min-1.pdf31 Jul 2017
Certificates of CA (Form 3)File: DC_2503408-min-2.pdf31 Jul 2017
Certificates of CA (Form 3)File: DC_2503408-min-3.pdf31 Jul 2017
Certificates of CA (Form 3)File: DC_2503408-min-4.pdf31 Jul 2017
Certificates of CA (Form 3)File: DC_2503408-min-5.pdf31 Jul 2017
Layout approvalFile: Greenfields Bldg 1 and 2 - Layout Plan Approved.pdf30 Jul 2017
Layout approvalFile: Greenfields Bldg 10 - Layout Plan Approved.pdf30 Jul 2017
Building plan approvalFile: Greenfields CHSL Bldg 10 - IOD.pdf30 Jul 2017
Building plan approvalFile: Greenfields CHSL Bldg 1 - IOD.pdf30 Jul 2017
PAN CardFile: PAN CARD - SH.pdf30 Jul 2017
Copy of the legal title reportFile: Greenfields CHSL - Title Certificate.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: Greenfields Bldg 10 - Layout Plan Approved.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: Greenfields Bldg 1 and 2 - Layout Plan Approved.pdf30 Jul 2017
Building Plan Approval (IOD)File: Greenfields CHSL Bldg 1 - IOD.pdf30 Jul 2017
Building Plan Approval (IOD)File: Greenfields CHSL Bldg 10 - IOD.pdf30 Jul 2017
Declaration in FORM BFile: SHUBHAM HOMES.pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Shubham Homes.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SHUBHAM TRIDENT - ENGINEER CERTIFICATE -1.pdf30 Jul 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 12 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Shubham Trident - Sundew, Sunrise and Sunglo on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Chembur6,700+ in Mumbai Suburban

2 kmShubham Trident - SundewCompleted 156Lapsed / revoked 119Other 146Dot size: filed unitsN

Filed coordinates, straight-line distance. 421 registered projects within 2 km.

Builder: Shubham Homes and Contractors Pvt. Ltd.

Shubham Homes and Contractors Pvt. Ltd. has 1 registration on MahaRERA, including Shubham Trident - Sundew, Sunrise and Sunglow. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that Shubham Trident - Sundew, Sunrise and Sunglow shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Shubham Trident - Sundew, Sunrise and Sunglow is delayed beyond 29 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Shubham Trident - Sundew, Sunrise and Sunglow?

The registered promoter entity is Shubham Homes and Contractors Pvt. Ltd., a company as per the filing. Its CIN U37200MH2021PTC370156 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Shubham Trident - Sundew, Sunrise and Sunglow?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Shubham Trident - Sundew, Sunrise and Sunglow?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

What should I check before booking in Shubham Trident - Sundew, Sunrise and Sunglow?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Shubham Trident - Sundew, Sunrise and Sunglow. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Shubham Trident - Sundew, Sunrise and Sunglo to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.