Home / Browse projects / Thane, Maharashtra / SHRI SHIVANAND CHS
SHRI SHIVANAND CHS
RG-MH-21806 · RERA P51700024183 · Last updated on MahaRERA portal: 7 Feb 2025
Source: official MahaRERA filing
Red flags
- 1 complaint at MahaRERA
- Completion date moved by 14 months
- 2 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SHRI SHIVANAND CHS is a Residential / Group Housing project by Trimity Constructions in Thane, Maharashtra, registered with MahaRERA as P51700024183 on 24 Jan 2020. The registration is recorded completed; possession was promised by 19 Aug 2024. The completion date has moved by 14 months from the original filing. 1 complaint is on record with the regulator.
At a glance
Project
- NameSHRI SHIVANAND CHS
- TypeResidential / Group Housing
- Location
- GAVAND PATH
- BHASKAR COLONY
- Thane (M Corp.)
- Thane
- 400602
- Pincode400602
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700024183
- ReraGenie IDRG-MH-21806
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on24 Jan 2020
- Promised completion19 Aug 2024
- Revised completionRevised to 19 Aug 2024 (originally 30 Jun 2023)
- Buildings1 building record
- Documents filed104 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SBI Employees Shri Shivanand CHS Ltd | NA | 9 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 7 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
8 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 95%.
SBI Employees Shri Shivanand CHS Ltd: 81% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
Progress on shared amenities17
As on 7 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 98% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 95% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
| Stack Parking | Yes | 100% |
| Fitness Centerr | Yes | 100% |
Parking filed26
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership2
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Trimity Constructions | Thane (M Corp.) | Thane |
| SBI Empoloyees Shri Shivanand CHS Ltd | Thane (M Corp.) | Thane |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Sakaar |
| Engineer | Roshan Katkar |
| Chartered Accountant | Kapure and Kapure Chartered accountants |
| Partner | Role in project |
|---|---|
| Trimity Constructions | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterAs per the attachment
Reason as filed by the promoterAs per attachment
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000209393 | STATE BANK OF INDIA EMPLOYEES, SHRI SHIVANAND CHS | TRIMITY CONSTRUCTIONS | 13/12/2021 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 17 Jan 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 16 Dec 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 17 Jan 2020 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 16 Dec 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 5 Nov 2024
Documents filed104
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 104 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate on Completion of Project (Form 4)File: Completion Certificate _ Shivanand Project.pdf | 7 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Shivanand Form 5 March 24.pdf | 27 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_ Shivanand 19082024.pdf | 19 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Shivanand Engineer Certificate 19082024.pdf | 19 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Inventory19082024.pdf | 19 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Shivanand Jun 2024_compressed.pdf | 9 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Shivanand Engineer Certificate 30062024.pdf | 9 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Shivanand Sold book inventory 30062024.pdf | 9 Nov 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Completion Certificate _ Shivanand Project.pdf | 5 Nov 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion Certificate _ Shivanand Project.pdf | 5 Nov 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Shivanand Occupation Certificate.pdf | 5 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect RERA Certificate.pdf | 20 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2 A Shivanand 2023.pdf | 20 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Shivanand 2024.pdf | 20 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate 31122023.pdf | 6 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate Shivanand March 24.pdf | 6 Jun 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_ Shivanand_March 2024.pdf | 6 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate 10042024.pdf | 20 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Shivanand List of Inventory.pdf | 20 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Inventory Shivanand 31122023.pdf | 11 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Shivanand _ Form 5.pdf | 5 Mar 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Inventories 30062023.pdf | 4 Mar 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Inventories30092023.pdf | 4 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form -3 Shri Shivanand Dec 22_compressed.pdf | 23 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3Shri Shivanand March 23_compressed.pdf | 23 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Shivanand June 23_compressed.pdf | 23 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Shivanand Sep 23_compressed.pdf | 23 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Shivanand Dec 23 Signed 22022024_comp.pdf | 23 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Shivanand Architect Certificate 10-01-2024.pdf | 20 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer s Certificate 31122022.pdf | 20 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer s Certificate 31032023.pdf | 20 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer s Certificate 30062023.pdf | 20 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer s Certificate 30092023.pdf | 20 Jan 2024 |
| Layout approvalFile: Shivanand 1_4_compressed.pdf | 16 Dec 2023 |
| Layout approvalFile: Shivanand 2_4_compressed.pdf | 16 Dec 2023 |
| Layout approvalFile: Shivanand 3_4_compressed.pdf | 16 Dec 2023 |
| Layout approvalFile: Shivanand 4_4_compressed.pdf | 16 Dec 2023 |
| Copy of Layout Approval (in case of layout)File: Shivanand 1_4_compressed.pdf | 16 Dec 2023 |
| Copy of Layout Approval (in case of layout)File: Shivanand 2_4_compressed.pdf | 16 Dec 2023 |
| Copy of Layout Approval (in case of layout)File: Shivanand 3_4_compressed.pdf | 16 Dec 2023 |
| Copy of Layout Approval (in case of layout)File: Shivanand 4_4_compressed.pdf | 16 Dec 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: Shri Shivanand Society _ 8th Floor_Commencement Certificate.pdf | 16 Dec 2023 |
| Declaration about Commencement CertificateFile: Shivanand Declaration _ 8th Floor.pdf | 16 Dec 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Shivanand RERA Architect Certificate_ 05_10_23.pdf | 5 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: Shivanand Letter _ RERA .pdf | 5 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Form 1.pdf | 15 Jun 2023 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold List.pdf | 15 Jun 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate 02-01-2020.pdf | 27 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate 04-01-2021.pdf | 27 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate 04-04-2020.pdf | 27 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate 04-07-2020.pdf | 27 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate 06-10-2020.pdf | 27 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate 4-1-2021.pdf | 27 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate 6-4-2021.pdf | 27 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate 6-7-2021.pdf | 27 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate 4-1-2022.pdf | 27 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate 03-11-2022.pdf | 27 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 jun 2022.pdf | 27 Mar 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form -3 March 20 _compressed.pdf | 27 Mar 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form -3 March 21_compressed.pdf | 27 Mar 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form -3 March 22 compressed.pdf | 27 Mar 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form -3 June 22 Singed Copy_compressed.pdf | 27 Mar 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form -3 Sep 22 Singed Copy_compressed.pdf | 27 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form -5 March 20.pdf | 27 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form -5 March 21.pdf | 27 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form-5 March 22.pdf | 27 Mar 2023 |
| Layout approvalFile: Plan 1.pdf | 9 Nov 2022 |
| Layout approvalFile: Shivanand Project - 1st -3rd Floor.pdf | 9 Nov 2022 |
| Layout approvalFile: Shivanand Project 4th -7th Floor.pdf | 9 Nov 2022 |
| Layout approvalFile: Shivanand Project -Terrace layout.pdf | 9 Nov 2022 |
| Copy of Layout Approval (in case of layout)File: Plan 1.pdf | 9 Nov 2022 |
| Copy of Layout Approval (in case of layout)File: Shivanand Project - 1st -3rd Floor.pdf | 9 Nov 2022 |
| Copy of Layout Approval (in case of layout)File: Shivanand Project 4th -7th Floor.pdf | 9 Nov 2022 |
| Copy of Layout Approval (in case of layout)File: Shivanand Project -Terrace layout.pdf | 9 Nov 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: Shivanand latest cc 25072022.pdf | 9 Nov 2022 |
| Declaration about Commencement CertificateFile: Shivanand - Declaration about Commencement Certificate.pdf | 9 Nov 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate 4-4-20.pdf | 9 Nov 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate 4-7-20.pdf | 9 Nov 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate 6-10-20.pdf | 9 Nov 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate 4-1-21.pdf | 9 Nov 2022 |
Promoter's earlier projects3
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| ASAVARI CO OP HSG SOC LTDP51700045809 | NAUPADA, Thane | 14 | Jun 2022 | Ongoing | Dec 2024 | Not delivered |
| HarmonyP51700022306 | Vishnu Nagar, Thane | 48 | Sep 2019 | Ongoing | Mar 2023 | Not delivered |
| Trimity Ashwa | Opp Rosa classique Ghodbunder road kasarwadavali | 28 | - | Completed | Dec 2017 | Dec 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 3 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 104 filed documents as one ZIP, foldered, with a manifest
Keep SHRI SHIVANAND CHS on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near BHASKAR COLONY7,600+ in Thane
Filed coordinates, straight-line distance. 91 registered projects within 2 km.
Stellar
Trimity Realty LLP
SAMRIN HERITAGE
SAMRIN INFRA PRIVATE LIMITED
L&T Realty Vayam Tower 3
ELANTE PROPERTIES PRIVATE LIMITED, J S K E
L&T Realty Vayam Tower 4
ELANTE PROPERTIES PRIVATE LIMITED, J S K E
Codename LIT Tower A
Camrose Realtors Private Limited
Codename LIT Tower B
Camrose Realtors Private Limited
See every Thane project, with the district possession charts
Builder: Trimity Constructions
Trimity Constructions has 4 registrations on MahaRERA, including Trimity Ashwa and Harmony. Its filings disclose 4 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What are my rights if SHRI SHIVANAND CHS is delayed beyond 19 Aug 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SHRI SHIVANAND CHS?
The registered promoter entity is Trimity Constructions, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SHRI SHIVANAND CHS?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against SHRI SHIVANAND CHS?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for SHRI SHIVANAND CHS?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SHRI SHIVANAND CHS?
The professionals named in the filing: Architect: Sakaar; Engineer: Roshan Katkar; Chartered Accountant: Kapure and Kapure Chartered accountants. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SHRI SHIVANAND CHS?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.