ASAVARI CO OP HSG SOC LTD
RG-MH-83341 · RERA P51700045809 · Last updated on MahaRERA portal: 1 Aug 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 22 months
- 3 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
ASAVARI CO OP HSG SOC LTD is a Residential / Group Housing project by Trimity Constructions in Thane, Maharashtra, registered with MahaRERA as P51700045809 on 15 Jun 2022. Possession is promised by 31 Oct 2026. The completion date has moved by 22 months from the original filing. 4 of the 14 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete.
At a glance
Project
- NameASAVARI CO OP HSG SOC LTD
- TypeResidential / Group Housing
- Location
- BHAGAWATI ROAD
- NAUPADA
- Thane (M Corp.)
- Thane
- 400602
- Pincode400602
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700045809
- ReraGenie IDRG-MH-83341
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on15 Jun 2022
- Promised completion31 Oct 2026
- Revised completionRevised to 31 Oct 2026 (originally 31 Dec 2024)
- Buildings1 building record
- Documents filed92 files
Current status
Figures as on 1 Aug 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| ASAVARI CO OP HSG SOC LTD | NA | 9 | 0 | 14 | 0 | 14 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 1 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 95%.
ASAVARI CO OP HSG SOC LTD: 90% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 95% |
Progress on shared amenities15
As on 1 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed15
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership2
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| ASAVARI CHS LTD | Thane (M Corp.) | Thane |
| TRIMITY CONSTRUCTIONS | Thane (M Corp.) | Thane |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| ASAVARI CO OP HSG SOC LTD | NA | Rs 1.91 cr | Rs 1.84 cr |
| - | NA | Rs 31.16 lakh | - |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Jitesh Pawar |
| Engineer | D K Patel |
| Engineer | Pawan Mahindrakar |
| Chartered Accountant | KapureandKaprechartredAccountants |
| Chartered Accountant | Shripati Gandhi Choudhari & Co |
| Partner | Role in project |
|---|---|
| Trimity Constructions | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterAs per attachment
Reason as filed by the promoterWe started construction work in the full swing. Quality of the construction is our primary preference and therefore we do not compromise with the quality of construction over speed of the construction. Therefore, as per the given circumstances, the construction work progressed.The main reason for the delay is slow pace of sales. Though the current number of sold units out of total units available for sale is better, the pace of sales was slow due to which cash flow of the project got effected which in turn resulted into delay in completion of the project.In addition to poor cash flows, cost ov
Reason as filed by the promoterThe current facts of the case are being explained hereunder. It may be noted that the construction of the project has been completed, and the Part Occupancy Certificate has been obtained as of 03/07/2026. The Occupancy Certificate received is for all the flats expect the flat No 702. It may be noted that the possession letter has also been handed over to the allottees. Accordingly, we are seeking an extension of the project registration solely for the purpose of completing the pending work and related formalities for Flat No. 702. The extension is not sought for any other reason. It is further
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 1 Jun 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 1 Jun 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 1 Jun 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 1 Jun 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Oct 2026
Documents filed92
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 92 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 5 (FY 2025-2026)File: Asavari - from 5 - 2025-26.pdf | 1 Aug 2026 |
| Withdrawal Update Form 1File: Asavari - Form 1 - April to June 26.pdf | 20 Jul 2026 |
| Withdrawal Update Form 2File: Asavari - From 2 - April to June 26.pdf | 20 Jul 2026 |
| Withdrawal Update Form 3File: Asavari - Form 3 - April to June 26.pdf | 20 Jul 2026 |
| Form 2A (FY 2025-2026)File: Asavari - Form 2A - March 26.pdf | 28 May 2026 |
| Withdrawal Update Form 1File: Asawari - Form 1 - Jan to March 26.pdf | 19 May 2026 |
| Withdrawal Update Form 2File: Asavari - From 2 - Jan to March 26.pdf | 19 May 2026 |
| Withdrawal Update Form 3File: Asavari - Form 3 - Jan to March 2026.pdf | 19 May 2026 |
| Withdrawal Update Form 1File: Asavari Form 1 - Oct to Dec 25.pdf | 2 Feb 2026 |
| Withdrawal Update Form 2File: Asavari Form 2 - Oct to Dec 25.pdf | 2 Feb 2026 |
| Withdrawal Update Form 3File: Asawari - form 3 - Dec 2025_compressed.pdf | 2 Feb 2026 |
| Form 2A (FY 2022-2023)File: Asavari Form 2A 01042023.pdf | 12 Nov 2025 |
| Form 2A (FY 2023-2024)File: Asavari Form 2A 01042024.pdf | 12 Nov 2025 |
| Form 2A (FY 2024-2025)File: Asavari -Form 2A 24-25.pdf | 12 Nov 2025 |
| Form 5 (FY 2022-2023)File: Asavari _ Form 5.pdf | 12 Nov 2025 |
| Form 5 (FY 2023-2024)File: Form 5 Asavari March 24.pdf | 12 Nov 2025 |
| Form 5 (FY 2024-2025)File: Asawari -Form 5 - 24-25.pdf | 12 Nov 2025 |
| Withdrawal Update Form 1File: Asawari Form 1 - July to Sept 2025.pdf | 4 Nov 2025 |
| Withdrawal Update Form 2File: Asavari form 2 - July to Sept 2025.pdf | 4 Nov 2025 |
| Withdrawal Update Form 3File: Asawari Form 3 - July to Sept 2025.pdf | 4 Nov 2025 |
| Withdrawal Update Form 1File: Asawari - Form 1April to June 25.pdf | 23 Aug 2025 |
| Withdrawal Update Form 2File: Asavari Form 2 - April to June 25.pdf | 23 Aug 2025 |
| Withdrawal Update Form 3File: Aasavari Form 3 - April to June 25.pdf | 23 Aug 2025 |
| Withdrawal Update Form 1File: Asawari - Form 1April to June 25.pdf | 11 Aug 2025 |
| Withdrawal Update Form 2File: Asavari Form 2 - April to June 25.pdf | 11 Aug 2025 |
| Withdrawal Update Form 3File: Aasavari Form 3 - April to June 25.pdf | 11 Aug 2025 |
| Form 2File: Asavari Form 2 - April to June 25.pdf | 7 Aug 2025 |
| Form 1File: Asawari - Form 1April to June 25.pdf | 7 Aug 2025 |
| Form 3File: Aasavari Form 3 - April to June 25.pdf | 7 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure Asavari April to June 25.pdf | 7 Aug 2025 |
| Form 1File: Aasawari Architect Certificate Jan to March 2025.pdf | 12 Jun 2025 |
| Form 2File: Asavari Engineer's Certificate Jan to March 25.pdf | 12 Jun 2025 |
| Form 3File: Form 3 - Asavari Mar 2025_compressed.pdf | 12 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Asawari Disclosure09062025.pdf | 12 Jun 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Asavari Mar 2025_compressed.pdf | 25 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Discloure of sold inventory Asavari Jan to March 2025.pdf | 25 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Aasawari Architect Certificate Jan to March 2025.pdf | 23 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Asavari Engineer's Certificate Jan to March 25.pdf | 23 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Asavari Architect Certificate 15-01-2025.pdf | 31 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_ Asavari CHS_ 24012025.pdf | 31 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Asavari Engineer Certificate 31-12-2024.pdf | 31 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Asavari Disclosure 31-12-2024.pdf | 31 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Asavari March 24.pdf | 28 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Asavari Form 3 30092024.pdf | 23 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Asavari Engineer Certificate 30092024pdf.pdf | 23 Nov 2024 |
| Declaration in FORM BFile: Asavari Rera Extension Form B .pdf | 19 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Sold book Inventory Asavari 30092024.pdf | 19 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Asavari form 1 30092024.pdf | 11 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Asavari _ Form 2_ Engineer Certificate .pdf | 9 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ASAVARI RERA ARCHITECT CERTIFICATE.pdf | 16 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure Of Inventory Asavari.pdf | 30 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form - 3 30-06-24.pdf | 30 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Asavari Form 2A 01042023.pdf | 28 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Asavari Form 2A 01042024.pdf | 28 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Asavari Engineer Certificate March 2024.pdf | 15 Jun 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Form 3 31032024.pdf | 29 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Asavari01042024.pdf | 20 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Asavari List of Inventory.pdf | 20 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Asavari Engineers certificate 31122023.pdf | 5 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Asavari _ Form 5.pdf | 5 Mar 2024 |
| Disclosure of sold/ booked inventoryFile: Asavari 30062023.pdf | 4 Mar 2024 |
| Disclosure of sold/ booked inventoryFile: Asavari30092023.pdf | 4 Mar 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of inventory Dec 2023.pdf | 4 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Asavari Dec 22_compressed.pdf | 4 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Asavari March 23_compressed.pdf | 4 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Asavari June 23_compressed (1).pdf | 4 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form - 3 Asavari Sep 23_compressed.pdf | 4 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Asavari March 23_compressed.pdf | 4 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Asavari Dec 23_compressed.pdf | 4 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Asavari RER Architect Certificate January 2024.pdf | 20 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Asavari 31-12-2022.pdf | 20 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Asavari 31-03-2023.pdf | 20 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Asavari 30-09-2023.pdf | 20 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Asavari 30-06-2023.pdf | 20 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Asavari Architect certificate 09102023.pdf | 20 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Architect Certifiacte.pdf | 26 Sep 2023 |
| Layout approvalFile: 1 Copy of Layout Approval (in case of layout).pdf | 1 Jun 2022 |
| Building plan approvalFile: 1 Building Plan Approval _ NA Order for plotted development.pdf | 1 Jun 2022 |
| PAN CardFile: 1 PAN Card.pdf | 1 Jun 2022 |
| Copy of the legal title reportFile: 1 Copy of the legal title report (1).pdf | 1 Jun 2022 |
Promoter's earlier projects3
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| SHRI SHIVANAND CHSP51700024183 | BHASKAR COLONY, Thane | - | Jan 2020 | Ongoing | Jun 2023 | Not delivered |
| HarmonyP51700022306 | Vishnu Nagar, Thane | 48 | Sep 2019 | Ongoing | Mar 2023 | Not delivered |
| Trimity Ashwa | Opp Rosa classique Ghodbunder road kasarwadavali | 28 | - | Completed | Dec 2017 | Dec 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 3 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 92 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep ASAVARI CO OP HSG SOC LTD on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near NAUPADA7,600+ in Thane
Stellar
Trimity Realty LLP
SAMRIN HERITAGE
SAMRIN INFRA PRIVATE LIMITED
L&T Realty Vayam Tower 3
ELANTE PROPERTIES PRIVATE LIMITED, J S K E
L&T Realty Vayam Tower 4
ELANTE PROPERTIES PRIVATE LIMITED, J S K E
Codename LIT Tower A
Camrose Realtors Private Limited
Codename LIT Tower B
Camrose Realtors Private Limited
See every Thane project, with the district possession charts
Builder: Trimity Constructions
Trimity Constructions has 4 registrations on MahaRERA, including Trimity Ashwa and Harmony. Its filings disclose 4 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What are my rights if ASAVARI CO OP HSG SOC LTD is delayed beyond 31 Oct 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of ASAVARI CO OP HSG SOC LTD?
The registered promoter entity is Trimity Constructions, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in ASAVARI CO OP HSG SOC LTD?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for ASAVARI CO OP HSG SOC LTD?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at ASAVARI CO OP HSG SOC LTD?
The professionals named in the filing: Architect: Jitesh Pawar; Engineer: D K Patel; Engineer: Pawan Mahindrakar; Chartered Accountant: KapureandKaprechartredAccountants; Chartered Accountant: Shripati Gandhi Choudhari & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ASAVARI CO OP HSG SOC LTD?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback