Red flags

  • 1 complaint at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2029Possession promisedno revision filed
1 of 11Construction stages donefurthest along: Basement (if any), 5%
148 of 301Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 65 documents Report an error

Codename LIT Tower A is a Residential / Group Housing project by Camrose Realtors Private Limited in Thane, Maharashtra, registered with MahaRERA as P51700079896 on 28 Mar 2025. Possession is promised by 31 Dec 2029. 153 of the 301 units on this registration are recorded sold or booked, and 1 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameCodename LIT Tower A
  • TypeResidential / Group Housing
  • Location
    • Village Naupada Near Eastern Express Highway Service Road
    • Thane
    • Thane (M Corp.)
    • 400602
  • Pincode400602
  • RERA no.P51700079896
  • ReraGenie IDRG-MH-31561

Builder

  • NameCamrose Realtors Private Limited
  • Entity typeCompany
  • DirectorRajesh Patel
  • Other registrations2 more →

Key dates

this monthRegisteredMar 2025PromisedDec 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on28 Mar 2025
  • Promised completion31 Dec 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed65 files

Current status

51%153 of 301 units booked
5.3%Work done, per cost certificate

Figures as on 6 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower ANA44413010301

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 6 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 5%.

Tower A: 10% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)5%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 6 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed828

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots828
Closed/Covered828

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,449 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on7 Jul 2025

Approvals and building plan

Sanctioning authorityThane Municipal Corporation
Permissible FSI40783.06
Proposed, not sanctioned37,190 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchUNIT NO 2 3 GROUND FLOOR INSPIRE BUSINESS PARK ADANI SHANTIGRAM AHMEDABAD GUJARAT 382421
Estimated costRs 347.85 cr
Cost incurredRs 18.59 cr
Work done5.35%
BuildingWingEstimatedIncurred
Tower ANARs 268.83 crRs 18.59 cr
-NARs 79.01 cr-

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSaakaar Architects
EngineerDavid Adamson
Chartered AccountantB R Nagda & Co
Chartered AccountantKaushal Manish & Co LLP
PartnerRole in project
Camrose Realtors Private Limited-

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12600569Devendra Amrutlal JoshiCamrose Realtors Private Limited02/02/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Mar 2025
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Mar 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Mar 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Mar 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2029

Documents filed65

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1_Codename LIT T A_Mar 26.pdf6 May 2026
Withdrawal Update Form 2File: Form 2_Codename LIT T A_Mar 26.pdf6 May 2026
Withdrawal Update Form 3File: Form 3_Codename LIT T A_Mar 26.pdf6 May 2026
Form 1File: Camrose_Form 1_Tower A.pdf5 Feb 2026
Form 2File: Camrose Form 2_Tower A.pdf5 Feb 2026
Form 3File: Camrose Form 3_Tower A.pdf5 Feb 2026
Disclosure of Sold and Booked InventoryFile: Camrose_Sold Unsold_Tower A.pdf5 Feb 2026
Form 1File: Form1Codename LIT Tower A Sept 25.pdf28 Nov 2025
Form 2File: Form2Codename LIT Tower A Sept 25.pdf28 Nov 2025
Form 3File: Form3Codename LIT Tower A Sept 25.pdf28 Nov 2025
Disclosure of Sold and Booked InventoryFile: Sold_Unsold_Codename LIT Tower A Sept 25.pdf28 Nov 2025
Form 5 (FY 2024-2025)File: AnnexureFform5ComroseFY202425Signed.pdf30 Sep 2025
Form 1File: Form1Codename LIT Tower A Jun 25.pdf2 Sep 2025
Form 2File: Form2Codename LIT Tower A Jun 25.pdf2 Sep 2025
Form 3File: Form3Codename LIT Tower A Jun 25.pdf2 Sep 2025
Disclosure of Sold and Booked InventoryFile: Codename LITTower A Disclosure of Sold UnsoldJun25.pdf2 Sep 2025
Copy of the legal title reportFile: RERA Title Report Annexure A 27 March 2025.pdf28 Mar 2025
Other - LegalFile: Deed of Conveyance.pdf28 Mar 2025
CERSAI detailsFile: Cersai Report A.pdf28 Mar 2025
Other - TechnicalFile: Sakaar Letter dated 27 March 2025.pdf28 Mar 2025
Other - TechnicalFile: New Order 50 Declaration - Annexure A- LIT - Tower A.pdf28 Mar 2025
Other - TechnicalFile: New Declaration on CC - LIT - Tower A.pdf28 Mar 2025
Proforma of Agreement for saleFile: AFS A.pdf28 Mar 2025
Proforma of Allotment letterFile: Allotment Letter Tower A.pdf26 Mar 2025
Declaration in FORM BFile: Form B - LIT - Tower A.pdf26 Mar 2025
Declaration in FORM BFile: Camrose BR for Tower A.pdf26 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - LIT - Tower A.pdf26 Mar 2025
Deviation Report with respect to Allotment letterFile: Deviation Report - Allottment Letter - LIT - Tower A.pdf26 Mar 2025
Deviation Report with respect to model copy of AgreementFile: AFS Deviation Tower A Final.pdf26 Mar 2025
Disclosure for secured/unsecured finance availed for the projectFile: Disclosure of secured - unsecured Finance - LIT - Tower A.pdf26 Mar 2025
Layout approvalFile: Layout Approval.pdf25 Mar 2025
Layout approvalFile: TMCB_7003_2025_0004_AutoDCR_Larger Land.pdf25 Mar 2025
Layout approvalFile: Building Plan 5.pdf25 Mar 2025
Building plan approvalFile: Building Plan 1.pdf25 Mar 2025
Building plan approvalFile: Building Plan 2.pdf25 Mar 2025
Building plan approvalFile: Building Plan 3.pdf25 Mar 2025
Building plan approvalFile: Building Plan 4.pdf25 Mar 2025
Building plan approvalFile: Building Plan 5.pdf25 Mar 2025
Building plan approvalFile: Building Plan 6.pdf25 Mar 2025
Building plan approvalFile: Building Plan 7.pdf25 Mar 2025
Details of encumbrances concerned to FinanceFile: Financial Encumbrance - LIT - Tower A.pdf25 Mar 2025
Details of encumbrances concerned to FinanceFile: Legal Encumbrance - LIT - Tower A.pdf25 Mar 2025
Copy of Layout Approval (in case of layout)File: Layout Approval.pdf25 Mar 2025
Copy of Layout Approval (in case of layout)File: TMCB_7003_2025_0004_AutoDCR_Larger Land.pdf25 Mar 2025
Copy of Layout Approval (in case of layout)File: Building Plan 5.pdf25 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - LIT - Tower A.pdf25 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - LIT - Tower A.pdf25 Mar 2025
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf25 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 7.pdf25 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 6.pdf25 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 5.pdf25 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 3.pdf25 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 2.pdf25 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 1.pdf25 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: Building Plan 4.pdf25 Mar 2025
Declaration about Commencement CertificateFile: Declaration on CC - LIT - Tower A.pdf25 Mar 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Declaration about RERA Designated Bank Accounts - Format A - LIT - Tower A.pdf25 Mar 2025
Details of encumbrances concerned to LegalFile: Legal Encumbrance - LIT - Tower A.pdf25 Mar 2025
Details of encumbrances concerned to LegalFile: Financial Encumbrance - LIT - Tower A.pdf25 Mar 2025
Other - TechnicalFile: Declaration on FSI - LIT - Tower A.pdf25 Mar 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosures in Real Estate Projects.pdf25 Mar 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Order 56 Declaration B_Tower A.pdf25 Mar 2025
Layout approvalFile: LOI Certificate.pdf15 Jan 2025
PAN CardFile: Camrose Pancard.pdf15 Jan 2025
Copy of Layout Approval (in case of layout)File: LOI Certificate.pdf15 Jan 2025

How this compares with Thane

51%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Codename LIT Tower A on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Thane7,600+ in Thane

Builder: Camrose Realtors Private Limited

Camrose Realtors Private Limited has 3 registrations on MahaRERA, including Codename LIT Tower A and Codename LIT Tower B. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Codename LIT Tower A is delayed beyond 31 Dec 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Codename LIT Tower A?

The registered promoter entity is Camrose Realtors Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Codename LIT Tower A?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Codename LIT Tower A?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Codename LIT Tower A?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Codename LIT Tower A?

The professionals named in the filing: Architect: Saakaar Architects; Engineer: David Adamson; Chartered Accountant: B R Nagda & Co; Chartered Accountant: Kaushal Manish & Co LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Codename LIT Tower A?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Codename LIT Tower A. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Codename LIT Tower A to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.