Home / Browse projects / Thane, Maharashtra / Harmony
Harmony
RG-MH-12684 · RERA P51700022306 · Last updated on MahaRERA portal: 1 Aug 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 7 complaints at MahaRERA
- Completion date moved by 45 months
- 3 extensions taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Harmony is a Residential / Group Housing project by Trimity Constructions in Thane, Maharashtra, registered with MahaRERA as P51700022306 on 9 Sep 2019. Possession is promised by 31 Dec 2026. The completion date has moved by 45 months from the original filing. 23 of the 48 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete. 7 complaints are on record with the regulator.
At a glance
Project
- NameHarmony
- TypeResidential / Group Housing
- Location
- Baji Prabhu Deshpande Road
- Vishnu Nagar
- Thane (M Corp.)
- Thane
- 400602
- Pincode400602
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700022306
- ReraGenie IDRG-MH-12684
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on9 Sep 2019
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 30 Mar 2023)
- Buildings1 building record
- Documents filed158 files
Current status
Figures as on 1 Aug 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Harmony | NA | 14 | 12 | 48 | 0 | 48 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 1 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 80%.
Harmony: 60% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 55% |
| Sanitary Fittings within the flats / premises | 30% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 1 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed39
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership12
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Trimity Constructions | Thane (M Corp.) | Thane |
| Anant Waman Oak | - | Thane |
| Madhusudan Waman Oak | Thane (M Corp.) | Thane |
| Mehul Satra | Thane (M Corp.) | Thane |
| Hitesh Satra | Thane (M Corp.) | Thane |
| Arvind Mahadeo Patankar | Thane (M Corp.) | Thane |
| Pushmala Saanand Patankar | Thane (M Corp.) | Thane |
| Samir Sadanand Patankar | Thane (M Corp.) | Thane |
| Vivek Sadanand Patankar | Thane (M Corp.) | Thane |
| Aakansha Ashok Biwalkar | Thane (M Corp.) | Thane |
| Jayashree Sudhakar Patankar | Thane (M Corp.) | Thane |
| Manjusha Milind Kelkar | Thane (M Corp.) | Thane |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Harmony | NA | Rs 7.00 cr | Rs 5.44 cr |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | 10 Folds Architects and Consultants |
| Engineer | Vitesh infrastructure Pvt Ltd |
| Engineer | Pentacon Structural Consultants Ltd |
| Engineer | Pawan Nishikant Mahindrakar |
| Chartered Accountant | KapureandKaprechartredAccountants |
| Chartered Accountant | Shripati Gandhi Choudhari & Co |
| Partner | Role in project |
|---|---|
| Trimity Constructions | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterAs per the attachment
Reason as filed by the promoterAs per the attachment
Reason as filed by the promoterWe started construction work in the full swing. Quality of the construction is our primary preference and therefore we do not compromise with the quality of construction over speed of the construction. Therefore, as per the given circumstances, the construction work progressed. The main reason for the delay is slow pace of sales. Though the current number of sold units out of total units available for sale is better, the pace of sales was slow due to which cash flow of the project got effected which in turn resulted into delay in completion of the project. Further, the contractor who was entru
Complaints filed with MahaRERA7
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000198154 | Krupasagar Padmakar Patwardhan | M/s Trimity Constructions | 01/09/2021 |
| CC006000000591353 | Nenshi Boricha | M/s Trimity Constructions | 29/07/2024 |
| CC006000000591354 | Panchiben Boricha | M/s Trimity Constructions | 29/07/2024 |
| CC006000000591356 | Rasila Boricha | M/s Trimity Constructions | 29/07/2024 |
| CC006000000591355 | Chetan Boricha | M/s Trimity Constructions | 29/07/2024 |
| CC12502577 | SNEHAL PRAVIN JOSHI | Trimity Constructions | 27/07/2025 |
| CC12502624 | Snehal Pravin Joshi | Trimity Constructions | 30/07/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 29 Aug 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 26 Nov 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 25 Jun 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 25 Jun 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed158
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 158 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 5 (FY 2025-2026)File: Harmony - From 5 - 2025-26.pdf | 1 Aug 2026 |
| Withdrawal Update Form 1File: Harmony - Form 1- April to June 26.pdf | 20 Jul 2026 |
| Withdrawal Update Form 2File: Harmony - Form 2 - April to June 26.pdf | 20 Jul 2026 |
| Withdrawal Update Form 3File: Harmony - Form 3 - April to June 26.pdf | 20 Jul 2026 |
| Form 2A (FY 2025-2026)File: Harmony - Form 2A - March 26.pdf | 28 May 2026 |
| Withdrawal Update Form 1File: Harmony - From 1 - Jan to March 2026.pdf | 19 May 2026 |
| Withdrawal Update Form 2File: Harmony - From 2 - Jan to March 2026.pdf | 19 May 2026 |
| Withdrawal Update Form 3File: Harmony - Form 3 - Jan to March 2026.pdf | 19 May 2026 |
| Withdrawal Update Form 1File: Harmony - Form 1 - Oct to Dec 25.pdf | 3 Feb 2026 |
| Withdrawal Update Form 2File: Harmony - Form 2 - Oct to Dec 25.pdf | 3 Feb 2026 |
| Withdrawal Update Form 3File: Harmony - Form 3 - Dec 2025_compressed.pdf | 3 Feb 2026 |
| Form 2A (FY 2019-2020)File: Form _ 2A_ 2020.pdf | 12 Nov 2025 |
| Form 2A (FY 2020-2021)File: Form 2A_ 2021.pdf | 12 Nov 2025 |
| Form 2A (FY 2021-2022)File: Form 2A_ 2022.pdf | 12 Nov 2025 |
| Form 2A (FY 2023-2024)File: Form 2 A Harmony 2024.pdf | 12 Nov 2025 |
| Form 2A (FY 2024-2025)File: Harmony -Form 2A 24- 25.pdf | 12 Nov 2025 |
| Form 2A (FY 2022-2023)File: Form 2A_ 2023.pdf | 12 Nov 2025 |
| Form 5 (FY 2019-2020)File: Form-5 March 20.pdf | 12 Nov 2025 |
| Form 5 (FY 2020-2021)File: Form -5 March 21.pdf | 12 Nov 2025 |
| Form 5 (FY 2021-2022)File: Form -5 March 22.pdf | 12 Nov 2025 |
| Form 5 (FY 2022-2023)File: Form 5_ Trimity Constructions.pdf | 12 Nov 2025 |
| Form 5 (FY 2023-2024)File: Harmony Form 5 TC.pdf | 12 Nov 2025 |
| Form 5 (FY 2024-2025)File: Harmony form 5 2024-25.pdf | 12 Nov 2025 |
| Withdrawal Update Form 1File: Harmony - Form 1 - Sept 2025.pdf | 31 Oct 2025 |
| Withdrawal Update Form 2File: Harmony Form 2- 18-10-2025.pdf | 31 Oct 2025 |
| Withdrawal Update Form 3File: TC _Harmony Form 3 QPR _0001.pdf | 31 Oct 2025 |
| Withdrawal Update Form 1File: Harmony Form 1 - april to June 25.pdf | 23 Aug 2025 |
| Withdrawal Update Form 2File: harmony Form -2 - april to june.pdf | 23 Aug 2025 |
| Withdrawal Update Form 3File: Harmony Form 3 June 2025.pdf | 23 Aug 2025 |
| Withdrawal Update Form 1File: Harmony Form 1 - april to June 25.pdf | 18 Aug 2025 |
| Withdrawal Update Form 2File: harmony Form -2 - april to june.pdf | 18 Aug 2025 |
| Withdrawal Update Form 3File: Harmony Form 3 June 2025.pdf | 18 Aug 2025 |
| Withdrawal Update Form 1File: Harmony Form 1 - april to June 25.pdf | 11 Aug 2025 |
| Withdrawal Update Form 2File: harmony Form -2 - april to june.pdf | 11 Aug 2025 |
| Withdrawal Update Form 3File: Harmony Form 3 June 2025.pdf | 11 Aug 2025 |
| Form 1File: Harmony Form 1 - april to June 25.pdf | 7 Aug 2025 |
| Form 2File: harmony Form -2 - april to june.pdf | 7 Aug 2025 |
| Form 3File: Harmony Form 3 June 2025.pdf | 7 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Harmony - Disclosuer June 2025.pdf | 7 Aug 2025 |
| Form 1File: Trimity Constrcutions - Harmony Architech Certificate - Jan to March 25.pdf | 22 Jul 2025 |
| Form 2File: Harmony Engineer's Certificate - Form 2 - Jan to March 25.pdf | 22 Jul 2025 |
| Form 3File: Form 3 -Harmony - Mar 2025_compressed.pdf | 22 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Inventory - Harmony Jan to March 2025.pdf | 22 Jul 2025 |
| Building plan approvalFile: Harmony_1.PDF | 25 Jun 2025 |
| Building plan approvalFile: Harmony_2.PDF | 25 Jun 2025 |
| Building plan approvalFile: Harmony_3.PDF | 25 Jun 2025 |
| Building plan approvalFile: Harmony_4.PDF | 25 Jun 2025 |
| Building plan approvalFile: Harmony_5.PDF | 25 Jun 2025 |
| Building plan approvalFile: Harmony_6.PDF | 25 Jun 2025 |
| Building plan approvalFile: Harmony_1.PDF | 25 Jun 2025 |
| Building plan approvalFile: Harmony_2.PDF | 25 Jun 2025 |
| Building plan approvalFile: Harmony_3.PDF | 25 Jun 2025 |
| Building plan approvalFile: Harmony_4.PDF | 25 Jun 2025 |
| Building plan approvalFile: Harmony_5.PDF | 25 Jun 2025 |
| Building plan approvalFile: Harmony_6.PDF | 25 Jun 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: 20250602072827.pdf | 25 Jun 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: Harmony_1.PDF | 25 Jun 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: Harmony_2.PDF | 25 Jun 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: Harmony_3.PDF | 25 Jun 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: Harmony_4.PDF | 25 Jun 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: Harmony_5.PDF | 25 Jun 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: Harmony_6.PDF | 25 Jun 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: 20250602072827.pdf | 25 Jun 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: Harmony_1.PDF | 25 Jun 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: Harmony_2.PDF | 25 Jun 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: Harmony_3.PDF | 25 Jun 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: Harmony_4.PDF | 25 Jun 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: Harmony_5.PDF | 25 Jun 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: Harmony_6.PDF | 25 Jun 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 -Harmony - Mar 2025_compressed.pdf | 25 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Inventory - Harmony Jan to March 2025.pdf | 25 Apr 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Harmony Form 5 TC.pdf | 25 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Trimity Constrcutions - Harmony Architech Certificate - Jan to March 25.pdf | 23 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Harmony Engineer's Certificate - Form 2 - Jan to March 25.pdf | 23 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate_ Harmony_ 04122024.pdf | 28 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_ Harmony_24012025_compressed.pdf | 28 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Harmony Engineer's Certificate 31122024.pdf | 28 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Book Inventory_ Harmony.pdf | 28 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate _ 10 folds.pdf | 20 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Harmony Form 3 30092024.pdf | 23 Nov 2024 |
Promoter's earlier projects3
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| ASAVARI CO OP HSG SOC LTDP51700045809 | NAUPADA, Thane | 14 | Jun 2022 | Ongoing | Dec 2024 | Not delivered |
| SHRI SHIVANAND CHSP51700024183 | BHASKAR COLONY, Thane | - | Jan 2020 | Ongoing | Jun 2023 | Not delivered |
| Trimity Ashwa | Opp Rosa classique Ghodbunder road kasarwadavali | 28 | - | Completed | Dec 2017 | Dec 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 3 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 158 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Harmony on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Vishnu Nagar7,600+ in Thane
Filed coordinates, straight-line distance. 321 registered projects within 2 km.
Stellar
Trimity Realty LLP
SAMRIN HERITAGE
SAMRIN INFRA PRIVATE LIMITED
L&T Realty Vayam Tower 3
ELANTE PROPERTIES PRIVATE LIMITED, J S K E
L&T Realty Vayam Tower 4
ELANTE PROPERTIES PRIVATE LIMITED, J S K E
Codename LIT Tower A
Camrose Realtors Private Limited
Codename LIT Tower B
Camrose Realtors Private Limited
See every Thane project, with the district possession charts
Builder: Trimity Constructions
Trimity Constructions has 4 registrations on MahaRERA, including Trimity Ashwa and Harmony. Its filings disclose 4 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What are my rights if Harmony is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Harmony?
The registered promoter entity is Trimity Constructions, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Harmony?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Harmony?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Harmony?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Harmony?
The professionals named in the filing: Architect: 10 Folds Architects and Consultants; Engineer: Vitesh infrastructure Pvt Ltd; Engineer: Pentacon Structural Consultants Ltd; Engineer: Pawan Nishikant Mahindrakar; Chartered Accountant: KapureandKaprechartredAccountants; Chartered Accountant: Shripati Gandhi Choudhari & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Harmony?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback