Home / Browse projects / Thane, Maharashtra / Harmony

Registered No litigation declared Residential / Group Housing project

Harmony

By Trimity Constructions

RG-MH-12684 · RERA P51700022306 · Last updated on MahaRERA portal: 1 Aug 2026

Source: official MahaRERA filing

Red flags

  • 7 complaints at MahaRERA
  • Completion date moved by 45 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 45 months from the original
5 of 11Construction stages donefurthest along: Staircases, 80%
25 of 48Units unsoldnot recorded sold or booked
7Complaints at MahaRERAon this registration
Jump to the 158 documents Report an error

Harmony is a Residential / Group Housing project by Trimity Constructions in Thane, Maharashtra, registered with MahaRERA as P51700022306 on 9 Sep 2019. Possession is promised by 31 Dec 2026. The completion date has moved by 45 months from the original filing. 23 of the 48 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete. 7 complaints are on record with the regulator.

At a glance

Project

  • NameHarmony
  • TypeResidential / Group Housing
  • Location
    • Baji Prabhu Deshpande Road
    • Vishnu Nagar
    • Thane (M Corp.)
    • Thane
    • 400602
  • Pincode400602
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700022306
  • ReraGenie IDRG-MH-12684

Builder

  • NameTrimity Constructions
  • Entity typePartnership
  • PartnersDevadatta Vinayak Joshi, Swapnil Yuvraj Marathe
  • Other registrations3 more →
  • Completed2 of 4
  • Declared earlier projects4 →

Key dates

this monthRegisteredSep 2019First promiseMar 2023Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on9 Sep 2019
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Mar 2023)
  • Buildings1 building record
  • Documents filed158 files

Current status

48%23 of 48 units booked
77.7%Work done, per cost certificate

Figures as on 1 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
HarmonyNA141248048

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 1 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 80%.

Harmony: 60% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises55%
Sanitary Fittings within the flats / premises30%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 1 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed39

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots39
Closed/Covered39

Land and ownership12

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,003 sq m
Land owned byNot the promoter
Named landowners12
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on7 Aug 2025
LandownerVillageDistrict
Trimity ConstructionsThane (M Corp.)Thane
Anant Waman Oak-Thane
Madhusudan Waman OakThane (M Corp.)Thane
Mehul SatraThane (M Corp.)Thane
Hitesh SatraThane (M Corp.)Thane
Arvind Mahadeo PatankarThane (M Corp.)Thane
Pushmala Saanand PatankarThane (M Corp.)Thane
Samir Sadanand PatankarThane (M Corp.)Thane
Vivek Sadanand PatankarThane (M Corp.)Thane
Aakansha Ashok BiwalkarThane (M Corp.)Thane
Jayashree Sudhakar PatankarThane (M Corp.)Thane
Manjusha Milind KelkarThane (M Corp.)Thane

Approvals and building plan

Sanctioning authorityThane Municipal Corporation
Permissible FSI3529.18
Proposed, not sanctioned3,529 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchICICI BANK LTD, PATHARE BLDG, GOKHALE ROAD, NAUPADA, THANE 400 602
Estimated costRs 7.00 cr
Cost incurredRs 5.44 cr
Work done77.72%
BuildingWingEstimatedIncurred
HarmonyNARs 7.00 crRs 5.44 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
Architect10 Folds Architects and Consultants
EngineerVitesh infrastructure Pvt Ltd
EngineerPentacon Structural Consultants Ltd
EngineerPawan Nishikant Mahindrakar
Chartered AccountantKapureandKaprechartredAccountants
Chartered AccountantShripati Gandhi Choudhari & Co
PartnerRole in project
Trimity Constructions-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700015407Mar 2023 → Mar 2024

Reason as filed by the promoterAs per the attachment

EXT51700019072Mar 2023 → Dec 2025

Reason as filed by the promoterAs per the attachment

EA31102518216Mar 2023 → Dec 2026

Reason as filed by the promoterWe started construction work in the full swing. Quality of the construction is our primary preference and therefore we do not compromise with the quality of construction over speed of the construction. Therefore, as per the given circumstances, the construction work progressed. The main reason for the delay is slow pace of sales. Though the current number of sold units out of total units available for sale is better, the pace of sales was slow due to which cash flow of the project got effected which in turn resulted into delay in completion of the project. Further, the contractor who was entru

Complaints filed with MahaRERA7

Case no.ComplainantRespondentFiled
CC006000000198154Krupasagar Padmakar PatwardhanM/s Trimity Constructions01/09/2021
CC006000000591353Nenshi BorichaM/s Trimity Constructions29/07/2024
CC006000000591354Panchiben BorichaM/s Trimity Constructions29/07/2024
CC006000000591356Rasila BorichaM/s Trimity Constructions29/07/2024
CC006000000591355Chetan BorichaM/s Trimity Constructions29/07/2024
CC12502577SNEHAL PRAVIN JOSHITrimity Constructions27/07/2025
CC12502624Snehal Pravin JoshiTrimity Constructions30/07/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Aug 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 26 Nov 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Jun 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Jun 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed158

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 158 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2025-2026)File: Harmony - From 5 - 2025-26.pdf1 Aug 2026
Withdrawal Update Form 1File: Harmony - Form 1- April to June 26.pdf20 Jul 2026
Withdrawal Update Form 2File: Harmony - Form 2 - April to June 26.pdf20 Jul 2026
Withdrawal Update Form 3File: Harmony - Form 3 - April to June 26.pdf20 Jul 2026
Form 2A (FY 2025-2026)File: Harmony - Form 2A - March 26.pdf28 May 2026
Withdrawal Update Form 1File: Harmony - From 1 - Jan to March 2026.pdf19 May 2026
Withdrawal Update Form 2File: Harmony - From 2 - Jan to March 2026.pdf19 May 2026
Withdrawal Update Form 3File: Harmony - Form 3 - Jan to March 2026.pdf19 May 2026
Withdrawal Update Form 1File: Harmony - Form 1 - Oct to Dec 25.pdf3 Feb 2026
Withdrawal Update Form 2File: Harmony - Form 2 - Oct to Dec 25.pdf3 Feb 2026
Withdrawal Update Form 3File: Harmony - Form 3 - Dec 2025_compressed.pdf3 Feb 2026
Form 2A (FY 2019-2020)File: Form _ 2A_ 2020.pdf12 Nov 2025
Form 2A (FY 2020-2021)File: Form 2A_ 2021.pdf12 Nov 2025
Form 2A (FY 2021-2022)File: Form 2A_ 2022.pdf12 Nov 2025
Form 2A (FY 2023-2024)File: Form 2 A Harmony 2024.pdf12 Nov 2025
Form 2A (FY 2024-2025)File: Harmony -Form 2A 24- 25.pdf12 Nov 2025
Form 2A (FY 2022-2023)File: Form 2A_ 2023.pdf12 Nov 2025
Form 5 (FY 2019-2020)File: Form-5 March 20.pdf12 Nov 2025
Form 5 (FY 2020-2021)File: Form -5 March 21.pdf12 Nov 2025
Form 5 (FY 2021-2022)File: Form -5 March 22.pdf12 Nov 2025
Form 5 (FY 2022-2023)File: Form 5_ Trimity Constructions.pdf12 Nov 2025
Form 5 (FY 2023-2024)File: Harmony Form 5 TC.pdf12 Nov 2025
Form 5 (FY 2024-2025)File: Harmony form 5 2024-25.pdf12 Nov 2025
Withdrawal Update Form 1File: Harmony - Form 1 - Sept 2025.pdf31 Oct 2025
Withdrawal Update Form 2File: Harmony Form 2- 18-10-2025.pdf31 Oct 2025
Withdrawal Update Form 3File: TC _Harmony Form 3 QPR _0001.pdf31 Oct 2025
Withdrawal Update Form 1File: Harmony Form 1 - april to June 25.pdf23 Aug 2025
Withdrawal Update Form 2File: harmony Form -2 - april to june.pdf23 Aug 2025
Withdrawal Update Form 3File: Harmony Form 3 June 2025.pdf23 Aug 2025
Withdrawal Update Form 1File: Harmony Form 1 - april to June 25.pdf18 Aug 2025
Withdrawal Update Form 2File: harmony Form -2 - april to june.pdf18 Aug 2025
Withdrawal Update Form 3File: Harmony Form 3 June 2025.pdf18 Aug 2025
Withdrawal Update Form 1File: Harmony Form 1 - april to June 25.pdf11 Aug 2025
Withdrawal Update Form 2File: harmony Form -2 - april to june.pdf11 Aug 2025
Withdrawal Update Form 3File: Harmony Form 3 June 2025.pdf11 Aug 2025
Form 1File: Harmony Form 1 - april to June 25.pdf7 Aug 2025
Form 2File: harmony Form -2 - april to june.pdf7 Aug 2025
Form 3File: Harmony Form 3 June 2025.pdf7 Aug 2025
Disclosure of Sold and Booked InventoryFile: Harmony - Disclosuer June 2025.pdf7 Aug 2025
Form 1File: Trimity Constrcutions - Harmony Architech Certificate - Jan to March 25.pdf22 Jul 2025
Form 2File: Harmony Engineer's Certificate - Form 2 - Jan to March 25.pdf22 Jul 2025
Form 3File: Form 3 -Harmony - Mar 2025_compressed.pdf22 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Inventory - Harmony Jan to March 2025.pdf22 Jul 2025
Building plan approvalFile: Harmony_1.PDF25 Jun 2025
Building plan approvalFile: Harmony_2.PDF25 Jun 2025
Building plan approvalFile: Harmony_3.PDF25 Jun 2025
Building plan approvalFile: Harmony_4.PDF25 Jun 2025
Building plan approvalFile: Harmony_5.PDF25 Jun 2025
Building plan approvalFile: Harmony_6.PDF25 Jun 2025
Building plan approvalFile: Harmony_1.PDF25 Jun 2025
Building plan approvalFile: Harmony_2.PDF25 Jun 2025
Building plan approvalFile: Harmony_3.PDF25 Jun 2025
Building plan approvalFile: Harmony_4.PDF25 Jun 2025
Building plan approvalFile: Harmony_5.PDF25 Jun 2025
Building plan approvalFile: Harmony_6.PDF25 Jun 2025
Commencement Certificates / NA Order for plotted developmentFile: 20250602072827.pdf25 Jun 2025
Building Plan Approval / NA Order for plotted developmentFile: Harmony_1.PDF25 Jun 2025
Building Plan Approval / NA Order for plotted developmentFile: Harmony_2.PDF25 Jun 2025
Building Plan Approval / NA Order for plotted developmentFile: Harmony_3.PDF25 Jun 2025
Building Plan Approval / NA Order for plotted developmentFile: Harmony_4.PDF25 Jun 2025
Building Plan Approval / NA Order for plotted developmentFile: Harmony_5.PDF25 Jun 2025
Building Plan Approval / NA Order for plotted developmentFile: Harmony_6.PDF25 Jun 2025
Commencement Certificates / NA Order for plotted developmentFile: 20250602072827.pdf25 Jun 2025
Building Plan Approval / NA Order for plotted developmentFile: Harmony_1.PDF25 Jun 2025
Building Plan Approval / NA Order for plotted developmentFile: Harmony_2.PDF25 Jun 2025
Building Plan Approval / NA Order for plotted developmentFile: Harmony_3.PDF25 Jun 2025
Building Plan Approval / NA Order for plotted developmentFile: Harmony_4.PDF25 Jun 2025
Building Plan Approval / NA Order for plotted developmentFile: Harmony_5.PDF25 Jun 2025
Building Plan Approval / NA Order for plotted developmentFile: Harmony_6.PDF25 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 -Harmony - Mar 2025_compressed.pdf25 Apr 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Inventory - Harmony Jan to March 2025.pdf25 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Harmony Form 5 TC.pdf25 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Trimity Constrcutions - Harmony Architech Certificate - Jan to March 25.pdf23 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Harmony Engineer's Certificate - Form 2 - Jan to March 25.pdf23 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate_ Harmony_ 04122024.pdf28 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_ Harmony_24012025_compressed.pdf28 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Harmony Engineer's Certificate 31122024.pdf28 Jan 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Book Inventory_ Harmony.pdf28 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate _ 10 folds.pdf20 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Harmony Form 3 30092024.pdf23 Nov 2024

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise2 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
ASAVARI CO OP HSG SOC LTDP51700045809NAUPADA, Thane14Jun 2022OngoingDec 2024Not delivered
SHRI SHIVANAND CHSP51700024183BHASKAR COLONY, Thane-Jan 2020OngoingJun 2023Not delivered
Trimity AshwaOpp Rosa classique Ghodbunder road kasarwadavali28-CompletedDec 2017Dec 2017

How this compares with Thane

48%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 45 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Harmony on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Vishnu Nagar7,600+ in Thane

2 kmHarmonyCompleted 104Lapsed / revoked 75Other 142Dot size: filed unitsN

Filed coordinates, straight-line distance. 321 registered projects within 2 km.

Builder: Trimity Constructions

Trimity Constructions has 4 registrations on MahaRERA, including Trimity Ashwa and Harmony. Its filings disclose 4 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Harmony is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Harmony?

The registered promoter entity is Trimity Constructions, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Harmony?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Harmony?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Harmony?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Harmony?

The professionals named in the filing: Architect: 10 Folds Architects and Consultants; Engineer: Vitesh infrastructure Pvt Ltd; Engineer: Pentacon Structural Consultants Ltd; Engineer: Pawan Nishikant Mahindrakar; Chartered Accountant: KapureandKaprechartredAccountants; Chartered Accountant: Shripati Gandhi Choudhari & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Harmony?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Harmony. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Harmony to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.