ReraGenieLog inGet a buyer report

Home / Browse projects / Nashik, Maharashtra / SHRI KRISHNA DARSHAN

Completed No litigation declared Residential / Group Housing project

SHRI KRISHNA DARSHAN

By SARWDNYA BUILDCON

RG-MH-14322 · RERA P51600032470 · Last updated on MahaRERA portal: 22 Mar 2024

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 3 completed earlier projects delivered on promise

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 3 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Dec 2029Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 41 documents Report an error

SHRI KRISHNA DARSHAN is a Residential / Group Housing project by SARWDNYA BUILDCON in Nashik, Maharashtra, registered with MahaRERA as P51600032470 on 4 Jan 2022. The registration is recorded completed; possession was promised by 31 Dec 2029.

At a glance

Project

  • NameSHRI KRISHNA DARSHAN
  • TypeResidential / Group Housing
  • Location
    • EKTA VELLY ROAD
    • KHANDERAO NAGAR PATHARDI
    • Nashik (M Corp.)
    • Nashik
    • 422010
  • Pincode422010
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51600032470
  • ReraGenie IDRG-MH-14322

Builder

  • NameSARWDNYA BUILDCON
  • Entity typePartnership
  • PartnersPRAVIN SAPURDA GAWANDE, GOKUL TANAJI ANARTHE
  • Other registrations3 more →
  • Completed2 of 4
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects5 →

Key dates

this monthRegisteredJan 2022PromisedDec 2029Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on4 Jan 2022
  • Promised completion31 Dec 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed41 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHRI KRISHNA DARSHANNA70000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 22 Mar 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

SHRI KRISHNA DARSHAN: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 22 Mar 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyNoNot applicable
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed20

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots20
Closed/Covered20

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area837 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI2351.6
Proposed, not sanctioned2,352 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAMBAD NASHIK

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHRISHIKESH PAWAR
EngineerR K SINGH
Chartered AccountantN S DHUMAL
PartnerRole in project
SARWDNYA BUILDCON-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 24 Nov 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Mar 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Mar 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Nov 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 14 Jul 2023

Documents filed41

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: RA - 21-22.pdf22 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: RA- 22-23.pdf22 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: shri krishna darshan Sept22 Signed copy.pdf17 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: shri krishna darshan Dec22 Signed copy.pdf17 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: shri krishna darshan MArch23 Signed copy.pdf17 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: shree krishna darshan Sept22.pdf17 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Shri Krishna Darshan Dec22.pdf17 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Shri Krishna Darshan March23.pdf17 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Sep22- Final.pdf17 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Dec22-Final.pdf17 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate Mar23- Final.pdf17 Feb 2024
Disclosure of sold/ booked inventoryFile: Sold Booked.pdf14 Jul 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: complition certificate.pdf14 Jul 2023
Architect’s Certificate on Completion of Project (Form 4)File: Form 04 (1).pdf14 Jul 2023
Disclosure of sold/ booked inventoryFile: Doc Apr 20 2023 1130.pdf21 Apr 2023
Other - TechnicalFile: Doc Apr 20 2023 1130-1.pdf21 Apr 2023
Disclosure of sold/ booked inventoryFile: Doc Jan 09 2023 15 42.pdf9 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Sarwandnya CA Certificate_signed.pdf29 Aug 2022
Layout approvalFile: New Plan_page-0001.pdf25 Mar 2022
Building plan approvalFile: New Plan_page-0001.pdf25 Mar 2022
Copy of Layout Approval (in case of layout)File: New Plan_page-0001.pdf25 Mar 2022
Building Plan Approval / NA Order for plotted developmentFile: New Plan_page-0001.pdf25 Mar 2022
Declaration about Commencement CertificateFile: Format D.pdf25 Mar 2022
Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf25 Mar 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Sarwadnya Buildcon signed.pdf25 Mar 2022
CERSAI detailsFile: Cersai Report.pdf22 Dec 2021
Declaration in FORM BFile: 08_FORM B RERA SB_NEW.pdf6 Dec 2021
Proforma of Allotment letterFile: 19_Draft Agreement_merged.pdf6 Dec 2021
Layout approvalFile: 04_Layout-DARSHAN_compressed.pdf24 Nov 2021
Building plan approvalFile: 05_BUILDING PLAN DARSHAN.pdf24 Nov 2021
PAN CardFile: 01_PAN CARD FIRM.pdf24 Nov 2021
Copy of the legal title reportFile: 02_Title Shrikrishna Darshan_compressed.pdf24 Nov 2021
Details of encumbrancesFile: 03_NON ENCUMBRANCES_DARSHAN.pdf24 Nov 2021
Copy of Layout Approval (in case of layout)File: 04_Layout-DARSHAN_compressed.pdf24 Nov 2021
Building Plan Approval / NA Order for plotted developmentFile: 05_BUILDING PLAN DARSHAN.pdf24 Nov 2021
Commencement Certificates / NA Order for plotted developmentFile: 06_Commencement Certificate_DARSHAN_compressed.pdf24 Nov 2021
Declaration about Commencement CertificateFile: 07_FORM D COMMENCEMENT DECLARATION.pdf24 Nov 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 09_ARCHITECT CERTIFICATE_FORM 1 _SB_compressed.pdf24 Nov 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 10_ENGINEERS CERTIFICATE_FORM 2_SB_compressed.pdf24 Nov 2021
Disclosure of sold/ booked inventoryFile: 13_DECLARATION OF INVENTORY_compressed.pdf24 Nov 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 12_ CA CERTIFICATE_FORM 3_SB_compressed.pdf24 Nov 2021

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered on promise1 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
SHRI KRUSHNA LUXRIYAP51600079977PATHARDI SHIWAR, Nashik27Apr 2025OngoingDec 2028Not due yet
SHREE KRISHNA EMPIRESR NO 72 PLOT NO 9 AND 101-CompletedJun 2019Jun 2019
SHREE KRISHNA BLOSSMSR NO 327-2-2-A PLOT NO 241-CompletedFeb 2015Feb 2015
SHREE KRISHNA RESIDENCYSR NO 70A AND B 1 PLOT NO 24 AND 251-CompletedApr 2012Apr 2012

How this compares with Nashik

10%of Nashik projects moved their completion datethis one has not
19%of Nashik registrations have lapsed or been cancelledthis one is completed

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHRI KRISHNA DARSHAN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KHANDERAO NAGAR PATHARDI4,100+ in Nashik

2 kmSHRI KRISHNA DARSHANCompleted 153Lapsed / revoked 39Other 94Dot size: filed unitsN

Filed coordinates, straight-line distance. 286 registered projects within 2 km.

Builder: SARWDNYA BUILDCON

SARWDNYA BUILDCON has 4 registrations on MahaRERA, including GOKUL PLAZA and SHRI KRISHNA DARSHAN. Its filings disclose 5 earlier MahaRERA projects: declares 4 of 4 past projects completed on time. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What are my rights if SHRI KRISHNA DARSHAN is delayed beyond 31 Dec 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHRI KRISHNA DARSHAN?

The registered promoter entity is SARWDNYA BUILDCON, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHRI KRISHNA DARSHAN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHRI KRISHNA DARSHAN?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHRI KRISHNA DARSHAN?

The professionals named in the filing: Architect: HRISHIKESH PAWAR; Engineer: R K SINGH; Chartered Accountant: N S DHUMAL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHRI KRISHNA DARSHAN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHRI KRISHNA DARSHAN. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHRI KRISHNA DARSHAN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.